TxDOT contract A00183799 bid tabulation
Widen Road - Add Lanes, SS 320 (FM 3255 to Railroad Drive). Let by Texas DOT on May 2, 2025, El Paso, El Paso District. 4 bids received; low bid $112,560,911 by Dan Williams Company, -19% against the engineer's estimate of $139,660,521.
- Owner
- Texas DOT
- Letting
- 02 MAY 2025
- Pay items
- 261
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Dan Williams Company | $112,560,911 | Low | -19% |
| 2 | Jordan Foster Construction, LLC | $116,396,410 | +3.0% | -17% |
| 3 | Webber, LLC | $129,141,414 | +15% | -8.0% |
| 4 | Pulice Construction, Inc. | $140,035,874 | +24% | 0.0% |
Engineer's estimate: $139,660,521.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Dan Williams Company | 2. Jordan Foster Construction, LLC | 3. Webber, LLC | 4. Pulice Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 275 | $4,000.00 | $7,500.00 | $12,698 | $45,077 | $50,900 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 2,900 | $75.00 | $12.00 | $36.00 | $15.55 | $9.98 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 557 | $40.00 | $14.00 | $21.00 | $17.06 | $21.78 |
| 4 | Removing concrete (curb) (104-7016) | LF | 541 | $8.00 | $4.50 | $5.95 | $7.95 | $11.93 |
| 5 | Remove (8") TRT/untrt base & asphalt pavement (105-7028) | SY | 263 | $13.00 | $18.00 | $6.05 | $14.94 | $28.07 |
| 6 | Remove (18") TRT/untrt base & asphalt pavement (105-7038) | SY | 23,432 | $15.00 | $3.75 | $7.40 | $11.04 | $10.65 |
| 7 | Remove (7"-13") TRT/untrt base & asphalt pavement (105-7058) | SY | 1,445 | $10.00 | $3.00 | $5.95 | $12.44 | $7.90 |
| 8 | Excavation (roadway) (110-7001) | CY | 187,107 | $14.00 | $9.00 | $9.60 | $8.88 | $1.85 |
| 9 | Excavation (special) (110-7003) | CY | 97,933 | $20.00 | $9.00 | $9.95 | $6.05 | $4.18 |
| 10 | Embankment (final)(DC)(type A) (132-7002) | CY | 996,181 | $20.00 | $16.00 | $16.50 | $8.99 | $13.42 |
| 11 | Sprinkling (dust control) (204-7001) | TGL | 1,000 | $80.00 | $50.00 | $47.00 | $40.00 | $189.60 |
| 12 | FL BS (compacted in place)(type A GR 1-2) (6") (247-7044) | SY | 391,479 | $12.00 | $11.00 | $11.00 | $10.95 | $10.37 |
| 13 | Cement (275-7001) | TON | 2,317 | $260.00 | $390.00 | $270.00 | $260.13 | $285.27 |
| 14 | Cement TRT (existing material)(6") (275-7002) | SY | 380,204 | $3.00 | $1.50 | $5.50 | $3.29 | $3.29 |
| 15 | Prime coat (multi option) (310-7015) | GAL | 58,800 | $6.00 | $6.50 | $7.60 | $5.70 | $8.92 |
| 16 | D-GR HMA type-B PG64-22 (341-7001) | TON | 85,030 | $125.00 | $105.00 | $88.00 | $98.99 | $166.09 |
| 17 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 41,362 | $175.00 | $125.00 | $115.00 | $123.71 | $183.69 |
| 18 | Planing asphalt concrete pavement(2") (354-7051) | SY | 7,150 | $15.00 | $2.50 | $0.90 | $3.90 | $1.43 |
| 19 | Struct excavation (box) (400-7002) | CY | 6,265 | $60.00 | $1.00 | $6.35 | $5.00 | $52.20 |
| 20 | Struct excavation (pipe) (400-7003) | CY | 9,714 | $35.00 | $1.00 | $6.15 | $5.00 | $52.20 |
| 21 | Cut & restoring pavement (400-7006) | SY | 148 | $350.00 | $300.00 | $171.00 | $508.04 | $294.87 |
| 22 | Cem stabil BKFL (400-7010) | CY | 922 | $500.00 | $225.00 | $173.00 | $235.00 | $140.56 |
| 23 | Flowable backfill (401-7001) | CY | 5,002 | $250.00 | $275.00 | $180.00 | $235.00 | $180.08 |
| 24 | Trench excavation protection (402-7001) | LF | 4,080 | $3.50 | $6.50 | $4.65 | $2.50 | $22.84 |
| 25 | Drilled shaft (18 in) (416-7002) | LF | 580 | $120.00 | $250.00 | $260.00 | $169.04 | $137.74 |
| 26 | Drilled shaft (36 in) (416-7006) | LF | 2,348 | $340.00 | $300.00 | $340.00 | $245.71 | $251.25 |
| 27 | Drilled shaft (42 in) (416-7007) | LF | 42 | $450.00 | $690.00 | $690.00 | $698.28 | $765.48 |
| 28 | Drilled shaft (48 in) (416-7008) | LF | 1,974 | $500.00 | $500.00 | $530.00 | $389.74 | $435.94 |
| 29 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 72 | $340.00 | $315.00 | $320.00 | $320.16 | $351.29 |
| 30 | Drilled shaft (sign mounts) (48 in) (416-7032) | LF | 1,213 | $500.00 | $725.00 | $720.00 | $730.36 | $805.18 |
| 31 | Drilled shaft (high mast pole) (54 in) (416-7036) | LF | 972 | $800.00 | $900.00 | $900.00 | $899.00 | $1,002.57 |
| 32 | Drilled shaft (high mast pole) (60 in) (416-7037) | LF | 352 | $900.00 | $1,200.00 | $1,200.00 | $1,196.00 | $1,333.79 |
| 33 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 169 | $500.00 | $440.00 | $440.00 | $439.00 | $489.58 |
| 34 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 22 | $700.00 | $700.00 | $700.00 | $699.40 | $779.98 |
| 35 | Class C concrete (abutment)(HPC) (420-7013) | CY | 402.60 | $1,900.00 | $1,200.00 | $1,660.00 | $1,577.06 | $999.97 |
| 36 | Class C concrete (cap)(HPC) (420-7023) | CY | 509.60 | $1,800.00 | $1,600.00 | $1,480.00 | $1,192.20 | $1,268.15 |
| 37 | Class C concrete (column)(HPC) (420-7039) | CY | 505.60 | $1,750.00 | $1,100.00 | $1,140.00 | $1,639.68 | $1,022.47 |
| 38 | Class C concrete (rail foundation) (420-7052) | CY | 317 | $1,000.00 | $550.00 | $610.00 | $878.20 | $646.97 |
| 39 | Reinforced concrete slab (HPC) (422-7002) | SF | 101,890 | $50.00 | $30.00 | $34.00 | $30.64 | $29.80 |
| 40 | Approach slab (HPC) (422-7014) | CY | 612.60 | $820.00 | $650.00 | $490.00 | $729.69 | $796.75 |
| 41 | Ret wall (MSE) (horizontal scheme) (423-7004) | SF | 258,244 | $85.00 | $50.00 | $48.00 | $78.71 | $49.10 |
| 42 | Prestressed concrete girder (TX46) (425-7004) | LF | 4,509.85 | $180.00 | $275.00 | $300.00 | $355.00 | $304.74 |
| 43 | Prestressed concrete girder (TX54) (425-7005) | LF | 8,469.66 | $190.00 | $275.00 | $310.00 | $355.00 | $304.92 |
| 44 | Concrete paint finish (427-7002) | SF | 703,597 | $1.00 | $0.70 | $0.54 | $0.32 | $0.30 |
| 45 | Opaque sealer finish (427-7003) | SF | 703,597 | $1.00 | $0.82 | $0.75 | $0.32 | $0.84 |
| 46 | Riprap (concrete)(4 in) (432-7001) | CY | 166.50 | $1,500.00 | $550.00 | $580.00 | $608.90 | $670.46 |
| 47 | Riprap (concrete)(6 in) (432-7003) | CY | 723 | $450.00 | $400.00 | $600.00 | $615.48 | $635.02 |
| 48 | Riprap (concrete)(CL B) (432-7005) | CY | 127 | $1,000.00 | $700.00 | $660.00 | $696.28 | $705.58 |
| 49 | Riprap (concrete)(flume) (432-7012) | CY | 109 | $580.00 | $800.00 | $620.00 | $644.71 | $658.54 |
| 50 | Riprap (mow strip)(4 in) (432-7013) | CY | 1,089 | $300.00 | $500.00 | $603.00 | $623.62 | $635.02 |
| 51 | Rail (type SSTR) (450-7024) | LF | 12,782 | $80.00 | $55.00 | $67.00 | $51.49 | $89.53 |
| 52 | Rail (type SSTR)(HPC) (450-7025) | LF | 5,560.30 | $190.00 | $65.00 | $85.00 | $63.39 | $109.31 |
| 53 | Rail (type T80PP-TS) (450-7053) | LF | 197 | $400.00 | $550.00 | $580.00 | $575.61 | $951.99 |
| 54 | Sealed expansion joint (5 in) (SEJ - M) (454-7005) | LF | 915 | $280.00 | $225.00 | $300.00 | $206.30 | $306.09 |
| 55 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 331 | $360.00 | $425.00 | $310.00 | $245.64 | $809.97 |
| 56 | Concrete box culvert (3 FT X 3 FT) (462-7002) | LF | 445 | $375.00 | $325.00 | $340.00 | $296.64 | $332.56 |
| 57 | Concrete box culvert (5 FT X 5 FT) (462-7009) | LF | 218 | $450.00 | $475.00 | $510.00 | $435.22 | $557.46 |
| 58 | Concrete box culvert (6 FT X 3 FT) (462-7011) | LF | 395 | $490.00 | $550.00 | $620.00 | $494.73 | $555.20 |
| 59 | Concrete box culvert (7 FT X 4 FT) (462-7016) | LF | 119 | $520.00 | $725.00 | $830.00 | $622.72 | $708.61 |
| 60 | Concrete box culvert (10 FT X 4 FT) (462-7032) | LF | 586 | $1,250.00 | $1,150.00 | $1,330.00 | $1,040.16 | $1,125.86 |
| 61 | Concrete box culvert (10 FT X 5 FT) (462-7033) | LF | 851 | $1,500.00 | $1,200.00 | $1,390.00 | $1,094.90 | $1,204.14 |
| 62 | RC pipe (CL III)(24 in) (464-7005) | LF | 3,681 | $150.00 | $100.00 | $132.00 | $107.36 | $93.55 |
| 63 | RC pipe (CL III)(48 in) (464-7011) | LF | 3,105 | $300.00 | $275.00 | $310.00 | $314.20 | $285.58 |
| 64 | RC pipe (CL IV)(18 in) (464-7019) | LF | 1,202 | $90.00 | $125.00 | $113.00 | $198.51 | $90.97 |
| 65 | Manh (complete)(PRM)(48IN) (465-7002) | EACH | 1 | $9,200.00 | $6,000.00 | $9,000.00 | $8,968.70 | $8,356.39 |
| 66 | Inlet (complete)(PSL)(FG)(6FTX6FT-4FTX4FT) (465-7141) | EACH | 17 | $11,500 | $8,500.00 | $11,400 | $11,390 | $10,356 |
| 67 | Inlet(complete)(PSL)(SFG)(4FTX4FT-4FTX4FT) (465-7147) | EACH | 3 | $11,000 | $7,500.00 | $10,600 | $12,440 | $9,529.02 |
| 68 | Inlet(complete)(pazd)(FG)(4FTX4FT-4FTX4FT) (465-7160) | EACH | 4 | $7,000.00 | $7,000.00 | $10,000 | $10,970 | $10,187 |
| 69 | JCT box (complete)(special) (465-7332) | EACH | 2 | $18,000 | $4,000.00 | $22,000 | $7,554.62 | $6,177.57 |
| 70 | Inlet (SPCL) (type MSE2) (top only) (465-7351) | EACH | 2 | $12,000 | $5,500.00 | $9,500.00 | $11,784 | $12,844 |
| 71 | Inlet (complete) (type MSE2) (465-7352) | EACH | 25 | $9,300.00 | $11,500 | $10,100 | $17,462 | $18,542 |
| 72 | Headwall (CH - FW - 0) (diameter= 48 in) (466-7011) | EACH | 1 | $12,000 | $20,000 | $15,900 | $23,723 | $8,493.86 |
| 73 | Headwall (CH - PW - 0) (diameter= 48 in) (466-7107) | EACH | 1 | $15,000 | $22,000 | $18,400 | $25,184 | $9,800.95 |
| 74 | Wingwall (FW - 0) (HW=4 FT) (466-7146) | EACH | 3 | $11,500 | $10,000 | $8,500.00 | $16,310 | $4,461.12 |
| 75 | Wingwall (FW - 0) (HW=6 FT) (466-7148) | EACH | 1 | $32,500 | $16,000 | $18,100 | $20,420 | $12,039 |
| 76 | Wingwall (FW - S) (HW=4 FT) (466-7160) | EACH | 1 | $12,000 | $15,000 | $15,300 | $16,793 | $9,821.55 |
| 77 | Wingwall (FW - S) (HW=5 FT) (466-7161) | EACH | 1 | $14,000 | $24,000 | $29,000 | $40,641 | $26,893 |
| 78 | Wingwall (FW - S) (HW=6 FT) (466-7162) | EACH | 6 | $27,000 | $25,000 | $38,000 | $44,810 | $35,313 |
| 79 | Wingwall (FW - S) (HW=7 FT) (466-7163) | EACH | 2 | $27,150 | $28,000 | $48,000 | $49,808 | $41,249 |
| 80 | Wingwall (FW - S) (HW=8 FT) (466-7164) | EACH | 1 | $27,300 | $30,000 | $60,000 | $64,817 | $56,746 |
| 81 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 3 | $15,000 | $15,000 | $12,900 | $22,286 | $19,327 |
| 82 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 1 | $23,400 | $25,000 | $13,700 | $31,714 | $49,132 |
| 83 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 2 | $25,500 | $28,000 | $22,000 | $30,875 | $60,809 |
| 84 | Wingwall (PW - 1) (HW=7 FT) (466-7177) | EACH | 1 | $40,000 | $30,000 | $17,500 | $36,219 | $86,700 |
| 85 | Wingwall (SW - 0) (HW=4 FT) (466-7203) | EACH | 1 | $12,000 | $10,000 | $8,900.00 | $17,656 | $6,782.33 |
| 86 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 25 | $1,300.00 | $2,300.00 | $2,200.00 | $3,456.12 | $3,254.09 |
| 87 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 6 | $1,700.00 | $2,400.00 | $2,700.00 | $2,531.22 | $3,448.97 |
| 88 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $2,000.00 | $2,400.00 | $2,700.00 | $2,522.23 | $3,524.40 |
| 89 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 48 | $2,200.00 | $2,400.00 | $2,600.00 | $3,780.12 | $4,006.12 |
| 90 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 1 | $1,900.00 | $2,400.00 | $3,100.00 | $2,799.30 | $4,519.12 |
| 91 | Removing structure (set) (496-7004) | EACH | 10 | $1,500.00 | $1,200.00 | $1,060.00 | $1,344.43 | $1,094.15 |
| 92 | Removing structure (box culvert) (496-7008) | LF | 317 | $200.00 | $45.00 | $79.00 | $80.68 | $42.98 |
| 93 | Mobilization (500-7001) | LS | 1 | $12,000,000 | $9,500,000 | $11,523,245 | $12,750,000 | $13,993,722 |
| 94 | Barricades, signs and traffic handling (502-7001) | MO | 59 | $3,000.00 | $25,000 | $11,000 | $50,146 | $12,601 |
| 95 | Portable changeable message sign (503-7002) | EACH | 6 | $12,250 | $15,000 | $13,000 | $18,295 | $21,844 |
| 96 | TMA (stationary) (505-7001) | DAY | 400 | $315.00 | $185.00 | $270.00 | $275.00 | $384.52 |
| 97 | TMA (mobile operation) (505-7003) | DAY | 240 | $250.00 | $550.00 | $380.00 | $350.00 | $694.15 |
| 98 | Rock filter dams (install) (type 1) (506-7001) | LF | 2,522 | $50.00 | $27.00 | $37.00 | $36.00 | $61.34 |
| 99 | Rock filter dams (remove) (506-7011) | LF | 2,522 | $22.00 | $12.00 | $15.50 | $15.00 | $27.88 |
| 100 | Construction exits (install) (type 1) (506-7020) | SY | 2,016 | $45.00 | $32.50 | $24.00 | $30.00 | $61.34 |
| 101 | Construction exits (remove) (506-7024) | SY | 2,016 | $20.00 | $14.00 | $12.50 | $12.00 | $13.38 |
| 102 | Temporary sediment control fence (install) (506-7039) | LF | 34,563 | $7.00 | $4.25 | $5.30 | $5.15 | $6.69 |
| 103 | Temporary sediment control fence (remove) (506-7041) | LF | 34,563 | $2.00 | $1.35 | $1.20 | $1.15 | $2.23 |
| 104 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 4,630 | $10.00 | $7.25 | $5.45 | $5.25 | $7.81 |
| 105 | Biodegradable erosion control logs (remove) (506-7046) | LF | 4,630 | $4.00 | $1.95 | $1.55 | $1.50 | $2.23 |
| 106 | Constructing detours (508-7001) | SY | 24,897 | $40.00 | $70.00 | $63.00 | $62.43 | $181.97 |
| 107 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 5,670 | $90.00 | $10.00 | $15.00 | $12.32 | $12.49 |
| 108 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 21,450 | $20.00 | $5.50 | $6.90 | $6.05 | $5.75 |
| 109 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 5,670 | $15.00 | $5.25 | $15.50 | $11.32 | $12.49 |
| 110 | Permanent CTB (single slope) (type 1) (54 ) (514-7009) | LF | 5,994 | $140.00 | $125.00 | $114.00 | $112.68 | $162.36 |
| 111 | Permanent CTB (single slope) (type 3) (54 ) (514-7010) | LF | 321 | $280.00 | $250.00 | $230.00 | $278.47 | $349.47 |
| 112 | Permanent CTB (single slope) (mod) (514-7035) | LF | 1,060 | $500.00 | $550.00 | $360.00 | $584.97 | $488.07 |
| 113 | Colored textured concrete (4") (527-7001) | SY | 2,628 | $130.00 | $90.00 | $83.00 | $104.48 | $88.20 |
| 114 | Concrete curb (type IV) (529-7005) | LF | 5,918 | $20.00 | $17.50 | $12.00 | $18.80 | $12.94 |
| 115 | Concrete sidewalks (5") (531-7002) | SY | 678 | $120.00 | $80.00 | $61.00 | $72.08 | $68.99 |
| 116 | Curb ramps (type 2) (531-7006) | EACH | 2 | $4,000.00 | $2,200.00 | $1,330.00 | $1,320.00 | $1,411.10 |
| 117 | Curb ramps (type 7) (531-7010) | EACH | 21 | $3,000.00 | $2,100.00 | $1,110.00 | $1,100.00 | $1,175.97 |
| 118 | Right of way markers (538-7001) | EACH | 250 | $415.00 | $350.00 | $500.00 | $463.00 | $557.60 |
| 119 | Metal W-beam guard fence (steel post) (540-7002) | LF | 10,063 | $30.00 | $30.00 | $31.00 | $30.16 | $49.31 |
| 120 | Downstream anchor terminal section (540-7015) | EACH | 53 | $2,000.00 | $1,450.00 | $2,100.00 | $1,100.00 | $3,082.04 |
| 121 | Metal thrie-beam guard fence (steel post) (540-7020) | EACH | 7 | $2,500.00 | $2,800.00 | $3,500.00 | $3,000.75 | $4,314.83 |
| 122 | Guardrail end treatment (install) (544-7001) | EACH | 60 | $3,000.00 | $3,400.00 | $3,500.00 | $2,990.00 | $4,931.25 |
| 123 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 8 | $3,500.00 | $900.00 | $1,530.00 | $1,280.00 | $7,806.45 |
| 124 | Crash cushion attenuator (remove) (545-7004) | EACH | 15 | $2,000.00 | $750.00 | $1,530.00 | $1,080.00 | $5,576.04 |
| 125 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 34 | $12,000 | $20,500 | $12,200 | $7,750.00 | $20,074 |
| 126 | Chain link fence (remove) (550-7007) | LF | 11,536 | $5.00 | $8.00 | $7.00 | $20.00 | $10.04 |
| 127 | Gate (special) (552-7009) | EACH | 6 | $2,500.00 | $8,500.00 | $4,800.00 | $8,000.00 | $6,133.63 |
| 128 | Pipe underdrains (type 8) (6") (556-7008) | LF | 11,831 | $30.00 | $20.50 | $42.00 | $33.20 | $34.20 |
| 129 | HI MST IL pole (125 FT)( 80 MPH) (613-7003) | EACH | 36 | $59,000 | $42,500 | $42,000 | $42,329 | $47,205 |
| 130 | HI MST IL pole (150 FT)( 80 MPH) (613-7005) | EACH | 11 | $62,000 | $52,500 | $52,000 | $52,049 | $58,046 |
| 131 | LED HI MST IL asm (6 fixt) (type S) (614-7001) | EACH | 3 | $43,200 | $46,100 | $46,000 | $46,100 | $51,411 |
| 132 | LED HI MST IL asm (6 fixt) (type A) (614-7002) | EACH | 13 | $41,500 | $46,000 | $46,000 | $45,929 | $51,220 |
| 133 | LED HI MST IL asm (6 fixt) (type B) (614-7003) | EACH | 27 | $41,000 | $46,250 | $46,000 | $46,201 | $51,524 |
| 134 | LED HI MST IL asm(6 fixt) (type B)SHLD (614-7010) | EACH | 4 | $40,000 | $46,700 | $47,000 | $46,669 | $52,046 |
| 135 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 36,934 | $19.50 | $29.00 | $29.00 | $28.80 | $32.12 |
| 136 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 4,975 | $34.00 | $28.00 | $28.00 | $27.50 | $30.67 |
| 137 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 37,144 | $49.00 | $30.35 | $30.00 | $30.33 | $33.82 |
| 138 | Conduit (PVC) (schedule 40) (3") (bore) (618-7037) | LF | 5,895 | $80.00 | $29.00 | $29.00 | $29.00 | $32.34 |
| 139 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 545 | $28.00 | $32.00 | $32.00 | $32.00 | $35.69 |
| 140 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 185 | $60.00 | $40.00 | $40.00 | $40.00 | $44.61 |
| 141 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 906 | $22.00 | $26.00 | $26.00 | $26.00 | $29.00 |
| 142 | Conduit (RM) (1") (618-7072) | LF | 1,720 | $34.00 | $30.00 | $30.00 | $29.87 | $33.31 |
| 143 | Conduit (prepare) (618-7090) | LF | 390 | $4.00 | $5.00 | $5.00 | $5.00 | $5.58 |
| 144 | ITS multi-duct CND (PVC-40) (619-7001) | LF | 32,914 | $49.12 | $45.00 | $45.00 | $44.91 | $50.08 |
| 145 | ITS multi-duct CND (PVC-40)(bore) (619-7002) | LF | 3,205 | $60.00 | $42.50 | $42.00 | $42.19 | $47.05 |
| 146 | Fiber optic cable road marker (619-7014) | EACH | 31 | $170.00 | $125.00 | $125.00 | $125.00 | $139.40 |
| 147 | Electrical conductor (no.14) insulated (620-7002) | LF | 39,769 | $2.00 | $1.60 | $1.60 | $1.60 | $1.78 |
| 148 | Electrical conductor (no.8) insulated (620-7008) | LF | 44,547 | $2.50 | $3.05 | $3.05 | $3.05 | $3.40 |
| 149 | Electrical conductor (no.6) insulated (620-7010) | LF | 51,464 | $5.10 | $3.15 | $3.15 | $3.15 | $3.51 |
| 150 | Electrical conductor (no.4) insulated (620-7012) | LF | 27,240 | $4.25 | $4.00 | $4.00 | $4.00 | $4.46 |
| 151 | ITS GND box (poly) type 1 (243648)W/aprn (623-7018) | EACH | 76 | $9,500.00 | $3,855.00 | $3,900.00 | $3,852.00 | $4,295.78 |
| 152 | ITS GND box (poly) type 2 (366048)W/aprn (623-7024) | EACH | 12 | $6,500.00 | $6,300.00 | $6,300.00 | $6,300.00 | $7,025.81 |
| 153 | Ground box type A (122311)W/apron (624-7002) | EACH | 162 | $1,900.00 | $1,605.00 | $1,600.00 | $1,602.00 | $1,786.56 |
| 154 | Ground box type D (162922)W/apron (624-7008) | EACH | 27 | $2,100.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,230.42 |
| 155 | Elc SRV type A 240/480 060(NS)SS(E)GC(O) (628-7044) | EACH | 4 | $12,000 | $9,000.00 | $8,900.00 | $8,900.00 | $9,925.35 |
| 156 | Elc SRV type A 240/480 100(NS)SS(E)GC(O) (628-7076) | EACH | 3 | $11,500 | $11,000 | $11,000 | $11,000 | $12,267 |
| 157 | Elc SRV type D 120/240 060(NS)GS(N)GC(O) (628-7133) | EACH | 1 | $5,000.00 | $10,000 | $10,000 | $10,000 | $11,152 |
| 158 | Elc SRV type D 120/240 060(NS)SS(N)GC(O) (628-7152) | EACH | 2 | $9,000.00 | $9,000.00 | $9,000.00 | $8,991.00 | $10,027 |
| 159 | Elc SRV type D 120/240 070(NS)GS(N)GC(O) (628-7178) | EACH | 1 | $12,000 | $9,000.00 | $9,000.00 | $8,999.00 | $10,036 |
| 160 | Aluminum signs (type G) (636-7002) | SF | 605 | $40.00 | $39.00 | $39.00 | $38.64 | $43.09 |
| 161 | Aluminum signs (type O) (636-7003) | SF | 4,283 | $50.00 | $40.00 | $40.00 | $39.66 | $44.23 |
| 162 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 56 | $900.00 | $905.00 | $900.00 | $903.00 | $1,007.03 |
| 163 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 83 | $1,000.00 | $990.00 | $990.00 | $988.00 | $1,101.83 |
| 164 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 22 | $1,150.00 | $1,250.00 | $1,210.00 | $1,214.00 | $1,353.86 |
| 165 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 5 | $1,200.00 | $1,250.00 | $1,200.00 | $1,204.00 | $1,342.71 |
| 166 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 8 | $1,250.00 | $1,850.00 | $1,850.00 | $1,846.20 | $2,058.89 |
| 167 | Install small roadside sign support and assembly TYS80(1)SA(U-2EXT) (644-7033) | EACH | 4 | $1,900.00 | $1,850.00 | $1,820.00 | $1,823.60 | $2,033.69 |
| 168 | Install small roadside sign support and assembly TYS80(2)SA(P-exal) (644-7049) | EACH | 7 | $3,000.00 | $3,500.00 | $3,300.00 | $3,333.00 | $3,716.99 |
| 169 | In bridge MNT clearance sign assembly(type S) (644-7062) | EACH | 8 | $4,000.00 | $3,600.00 | $3,600.00 | $3,596.00 | $4,010.29 |
| 170 | Remove SM RD SN sup&AM (644-7073) | EACH | 8 | $400.00 | $220.00 | $220.00 | $220.00 | $245.34 |
| 171 | In SRSS & AM (rail)(90 MPH)(P mount) (644-7078) | EACH | 5 | $5,500.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,345.62 |
| 172 | In SRSS & AM (rail)(90 MPH)(T mount) (644-7080) | EACH | 4 | $6,200.00 | $3,200.00 | $3,100.00 | $3,133.40 | $3,494.40 |
| 173 | Install LRSS (struct steel) (647-7001) | LB | 3,854 | $9.00 | $8.55 | $8.55 | $8.55 | $9.54 |
| 174 | Install overhead sign support(35 FT cant)(circ tube) (650-7040) | EACH | 12 | $140,000 | $115,000 | $111,000 | $111,227 | $124,041 |
| 175 | Install overhead sign support(40 FT cant)(circ tube) (650-7047) | EACH | 1 | $155,000 | $115,000 | $111,000 | $111,167 | $123,975 |
| 176 | Install overhead sign support(50 FT BRDG)(circ tube) (650-7060) | EACH | 1 | $175,000 | $115,000 | $111,000 | $110,970 | $123,755 |
| 177 | Install overhead sign support(55 FT BRDG)(circ tube) (650-7065) | EACH | 1 | $185,000 | $115,000 | $113,000 | $113,442 | $126,511 |
| 178 | Install overhead sign support(65 FT BRDG)(circ tube) (650-7075) | EACH | 1 | $199,000 | $125,000 | $119,000 | $118,931 | $132,633 |
| 179 | Install overhead sign support(70 FT comb)(circ tube) (650-7083) | EACH | 1 | $220,000 | $125,000 | $121,000 | $120,515 | $134,400 |
| 180 | Install overhead sign support(75 FT BRDG)(circ tube) (650-7085) | EACH | 1 | $250,000 | $180,000 | $175,000 | $175,000 | $195,162 |
| 181 | Install overhead sign support(90 FT BRDG)(circ tube) (650-7100) | EACH | 1 | $380,000 | $195,000 | $189,000 | $188,517 | $210,236 |
| 182 | Install overhead sign support(110 FT comb)(circ tube) (650-7123) | EACH | 1 | $450,000 | $210,000 | $202,000 | $201,970 | $225,238 |
| 183 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 62 | $70.00 | $60.00 | $35.00 | $35.27 | $55.48 |
| 184 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 34 | $35.00 | $60.00 | $30.00 | $45.83 | $92.46 |
| 185 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 26 | $45.00 | $60.00 | $35.00 | $34.92 | $55.48 |
| 186 | Install object marker assembly (OM-2Y)(WC)GND(BI) (658-7057) | EACH | 14 | $110.00 | $175.00 | $95.00 | $85.29 | $128.39 |
| 187 | Remove delin & object marker assms (658-7078) | EACH | 10 | $40.00 | $75.00 | $57.00 | $25.19 | $49.81 |
| 188 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 41,631 | $3.50 | $1.05 | $1.15 | $1.25 | $1.26 |
| 189 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 49,018 | $1.50 | $1.05 | $1.15 | $1.25 | $1.26 |
| 190 | Work zone pavement marking removing (traffic BTN) type W (662-7058) | LF | 41,631 | $1.00 | $1.05 | $1.15 | $1.25 | $1.26 |
| 191 | Work zone pavement marking removing (traffic BTN) type Y (662-7060) | LF | 49,018 | $3.00 | $1.05 | $1.15 | $1.25 | $1.26 |
| 192 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 1,051 | $2.00 | $2.35 | $2.75 | $2.55 | $4.94 |
| 193 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 2,123 | $2.50 | $2.35 | $2.75 | $1.47 | $4.94 |
| 194 | Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008) | LF | 4,987 | $1.15 | $1.24 | $1.35 | $1.41 | $1.49 |
| 195 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 3,487 | $2.00 | $1.34 | $1.45 | $1.53 | $1.61 |
| 196 | Reflectorized pavement marking type I (W)12"(lane drop)(090MIL) (666-7026) | LF | 3,364 | $1.50 | $2.35 | $2.55 | $2.65 | $2.82 |
| 197 | Reflectorized pavement marking type I (W)12"(solid)(090MIL) (666-7029) | LF | 1,890 | $2.90 | $3.05 | $3.35 | $3.43 | $3.67 |
| 198 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 1,217 | $14.00 | $8.00 | $8.75 | $8.63 | $9.61 |
| 199 | Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041) | EACH | 24 | $290.00 | $135.00 | $147.00 | $137.51 | $162.18 |
| 200 | Reflectorized pavement marking type I(W)(double arrow)(090MIL) (666-7044) | EACH | 16 | $240.00 | $180.00 | $197.00 | $188.72 | $216.24 |
| 201 | Reflectorized pavement marking type I(W)(lane drop arrow)(090MIL) (666-7059) | EACH | 10 | $330.00 | $350.00 | $380.00 | $355.90 | $420.48 |
| 202 | Reflectorized pavement marking type I (W)(word)(090MIL) (666-7065) | EACH | 22 | $360.00 | $150.00 | $164.00 | $148.30 | $180.21 |
| 203 | Reflectorized pavement marking type I(W)(entr gore)(090MIL) (666-7068) | EACH | 6 | $540.00 | $830.00 | $910.00 | $947.97 | $997.12 |
| 204 | Reflectorized pavement marking type I(W)(exit gore)(090MIL) (666-7071) | EACH | 6 | $550.00 | $1,240.00 | $1,350.00 | $1,420.34 | $1,489.70 |
| 205 | Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265) | LF | 39,770 | $1.70 | $1.10 | $1.20 | $1.25 | $1.33 |
| 206 | Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269) | LF | 39,791 | $2.50 | $1.10 | $1.20 | $1.25 | $1.33 |
| 207 | Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407) | LF | 17,026 | $0.90 | $0.87 | $0.95 | $1.00 | $1.05 |
| 208 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 48,674 | $1.40 | $0.81 | $0.88 | $0.92 | $0.97 |
| 209 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 55,253 | $1.20 | $0.81 | $0.88 | $0.93 | $0.97 |
| 210 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 109 | $25.00 | $6.00 | $6.55 | $6.83 | $7.20 |
| 211 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 1,404 | $15.00 | $5.25 | $5.75 | $6.83 | $6.31 |
| 212 | Eliminating existing PM & markers (4") (677-7001) | LF | 29,149 | $2.00 | $0.65 | $0.71 | $0.58 | $0.78 |
| 213 | Eliminating existing PM & markers (8") (677-7004) | LF | 444 | $2.50 | $1.30 | $1.40 | $1.44 | $1.56 |
| 214 | Eliminating existing PM & markers (24") (677-7008) | LF | 80 | $7.00 | $2.60 | $2.85 | $2.89 | $3.12 |
| 215 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 7 | $200.00 | $120.00 | $131.00 | $128.36 | $144.15 |
| 216 | Eliminating existing PM & markers (word) (677-7015) | EACH | 7 | $200.00 | $130.00 | $142.00 | $144.41 | $156.17 |
| 217 | Install highway traffic signal (isolated) (680-7002) | EACH | 2 | $50,000 | $45,000 | $39,000 | $39,444 | $43,988 |
| 218 | Install highway traffic signal (upgrade) (680-7011) | EACH | 1 | $30,000 | $37,000 | $37,000 | $36,999 | $41,262 |
| 219 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 26 | $380.00 | $440.00 | $440.00 | $440.00 | $490.69 |
| 220 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 23 | $400.00 | $429.00 | $430.00 | $429.00 | $478.42 |
| 221 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 36 | $410.00 | $422.00 | $420.00 | $422.00 | $470.62 |
| 222 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 9 | $350.00 | $406.00 | $410.00 | $406.00 | $452.77 |
| 223 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 36 | $380.00 | $421.00 | $420.00 | $421.00 | $469.50 |
| 224 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 9 | $350.00 | $400.00 | $400.00 | $400.00 | $446.08 |
| 225 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 23 | $900.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,115.21 |
| 226 | Backplate W/reflectorized border(4 sec) (682-7037) | EACH | 4 | $310.00 | $300.00 | $300.00 | $300.00 | $334.55 |
| 227 | Backplate W/reflectorized border(3 sec) (682-7054) | EACH | 41 | $225.00 | $285.00 | $290.00 | $285.00 | $317.83 |
| 228 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 10,149 | $1.90 | $1.70 | $1.70 | $1.69 | $1.88 |
| 229 | Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010) | LF | 10,325 | $3.50 | $3.00 | $3.00 | $2.99 | $3.33 |
| 230 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 2,939 | $3.75 | $3.40 | $3.35 | $3.36 | $3.75 |
| 231 | Traffic signal CBL (type A)(12 AWG)(12 conductor) (684-7017) | LF | 6,615 | $5.50 | $5.15 | $5.10 | $5.12 | $5.71 |
| 232 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 6 | $15,500 | $16,000 | $15,900 | $15,883 | $17,713 |
| 233 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 2 | $17,100 | $16,000 | $16,000 | $15,996 | $17,839 |
| 234 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 2 | $15,600 | $17,000 | $16,600 | $16,601 | $18,514 |
| 235 | Ins traffic signal PL AM(S)1 arm(48') (686-7049) | EACH | 4 | $17,300 | $17,000 | $17,000 | $16,982 | $18,938 |
| 236 | Ins traffic signal PL AM(S)1 arm(60') (686-7061) | EACH | 1 | $40,500 | $43,000 | $43,000 | $42,885 | $47,826 |
| 237 | Pedestrian pole assembly (687-7001) | EACH | 20 | $5,000.00 | $4,000.00 | $3,400.00 | $3,396.00 | $3,787.24 |
| 238 | Pedestrian detect push button (APS) (688-7001) | EACH | 23 | $1,500.00 | $935.00 | $940.00 | $935.00 | $1,042.72 |
| 239 | Pedestrian detector controller unit (688-7003) | EACH | 2 | $4,200.00 | $4,000.00 | $3,400.00 | $3,397.40 | $3,788.78 |
| 240 | Anti-graffiti coatng (permnent-type III) (740-7006) | SF | 715,146 | $1.50 | $1.80 | $1.75 | $1.70 | $0.84 |
| 241 | Membrane underseal (3005-7001) | GAL | 76,039 | $1.00 | $5.50 | $7.45 | $9.56 | $13.38 |
| 242 | Headwall (stone masonry) (5044-7001) | SF | 39,294 | $18.00 | $19.00 | $22.00 | $28.23 | $27.88 |
| 243 | ITS com CBL (ethernet) (6005-7001) | LF | 2,315 | $3.00 | $3.05 | $3.05 | $3.05 | $3.40 |
| 244 | VIVDS prosr sys (6006-7001) | EACH | 2 | $8,500.00 | $4,255.00 | $4,300.00 | $4,251.00 | $4,740.74 |
| 245 | VIVDS cam assy FXD LNS (6006-7002) | EACH | 15 | $5,900.00 | $6,000.00 | $6,000.00 | $5,981.00 | $6,670.06 |
| 246 | VIVDS CNTRL software (6006-7005) | EACH | 2 | $600.00 | $550.00 | $550.00 | $550.00 | $613.35 |
| 247 | VIVDS cabling (6006-7007) | LF | 7,624 | $4.40 | $2.60 | $2.60 | $2.59 | $2.89 |
| 248 | System integration (6009-7001) | LS | 1 | $40,000 | $32,000 | $32,000 | $32,000 | $35,687 |
| 249 | ITS RVSD(data coll only)(install only) (6010-7006) | EACH | 3 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,115.21 |
| 250 | ITS pole (55 FT)(90 MPH) (6011-7001) | EACH | 2 | $30,000 | $25,000 | $25,000 | $24,996 | $27,876 |
| 251 | ITS pole MNT cab (type 2)(conf 2) (6011-7002) | EACH | 2 | $5,500.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,691.23 |
| 252 | Ground box (prepare) (6013-7006) | EACH | 8 | $700.00 | $600.00 | $600.00 | $600.00 | $669.12 |
| 253 | Installation of cellular modem (6015-7001) | EACH | 4 | $4,500.00 | $1,755.00 | $1,760.00 | $1,755.00 | $1,957.19 |
| 254 | CCTV field equip (digital) (install only) (6018-7001) | EACH | 6 | $3,200.00 | $2,200.00 | $2,200.00 | $2,200.00 | $2,453.45 |
| 255 | Fiber optic fusion splice (6027-7004) | EACH | 180 | $160.00 | $135.00 | $135.00 | $135.00 | $150.55 |
| 256 | Fiber optic CBL(single-mode)(144 fiber) (6027-7006) | LF | 33,994 | $5.00 | $4.50 | $4.50 | $4.50 | $5.02 |
| 257 | FO splice enclosure (type 1) (6027-7009) | EACH | 14 | $4,000.00 | $2,650.00 | $2,700.00 | $2,650.00 | $2,955.30 |
| 258 | Fiber optic CBL (SNGL-mode)(72 fiber) (6027-7014) | LF | 100 | $8.00 | $15.00 | $15.00 | $15.00 | $16.73 |
| 259 | FO CBL (12 SMF)(pigtail) (6027-7020) | LF | 12,240 | $5.00 | $8.00 | $7.85 | $7.86 | $8.77 |
| 260 | Ethernet switch (install only) (6036-7001) | EACH | 2 | $400.00 | $1,075.00 | $1,070.00 | $1,072.00 | $1,195.49 |
| 261 | LED aesthetic light assembly (6101-7001) | EACH | 10 | $20,000 | $85,000 | $84,000 | $83,655 | $93,293 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 2, 2025. Compiled by Mirage Metrics.