TxDOT contract A00196756 bid tabulation

Intersection Improvements With Right And/Or Left Turn Lanes, US 290 (0.3 miles West of FM 2679 to 0.27 miles East of FM 2679). Let by Texas DOT on May 2, 2025, Washington, Bryan District. 7 bids received; low bid $965,907 by Cornerstone Paving and Construction, L.L.C., -27% against the engineer's estimate of $1,325,224.

Owner
Texas DOT
Letting
02 MAY 2025
Pay items
94
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Cornerstone Paving and Construction, L.L.C.$965,907Low-27%
2Larry Young Paving, Inc.$1,020,481+6.0%-23%
3Big Creek Construction, LTD.$1,070,801+11%-19%
4Texas Materials Group, Inc.$1,119,506+16%-16%
5Knife River Corporation - South$1,152,504+19%-13%
6Forde Construction Company, Inc.$1,218,206+26%-8.0%
7Acme Bridge Company, Inc.$1,423,698+47%+7.0%
TxDOT contract A00196756: bids by rank

Engineer's estimate: $1,325,224.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Cornerstone Paving and Construction, L.L.C.2. Larry Young Paving, Inc.3. Big Creek Construction, LTD.4. Texas Materials Group, Inc.5. Knife River Corporation - South6. Forde Construction Company, Inc.
1Remove (16"-20") TRT/untrt base & asphalt pavement (105-7016)SY910$27.50$27.50$33.00$40.00$25.00$22.00$28.00
2Excavation (roadway) (110-7001)CY1,158$18.50$29.35$43.00$30.00$40.00$21.00$42.00
3Embankment (final)(DC)(type C) (132-7006)CY306$22.50$43.29$23.00$30.00$115.00$8.00$52.00
4Furn & place topsoil (4") (160-7002)SY5,556$6.00$4.50$2.25$1.00$4.00$0.62$5.00
5Broadcast seed (permanent_rural_clay) (164-7002)SY5,556$1.25$0.85$0.75$1.00$0.26$0.94$1.00
6Broadcast seed (temporary_warm) (164-7005)SY2,778.50$0.75$0.75$1.00$1.00$0.26$0.83$0.90
7Broadcast seed (temporary_cool) (164-7006)SY2,778.50$1.75$0.75$1.00$1.00$0.26$0.83$0.90
8Vegetative watering (168-7001)TGL56$100.00$150.00$36.00$55.00$50.00$69.45$178.00
9Proof rolling (216-7001)HR2$215.00$500.00$230.00$100.00$150.00$99.00$500.00
10FL BS (compacted in place)(type A GR 1-2) (6") (247-7044)SY1,994$40.00$46.18$30.00$32.00$19.50$32.70$40.00
11Cement (275-7001)TON44$325.00$250.00$280.00$275.00$280.00$260.00$230.00
12Cement TRT (new base)(6") (275-7010)SY1,994$16.00$6.27$7.00$8.00$12.00$3.92$14.00
13Cement treat (subgrade) (8") (275-7017)SY2,193$8.00$5.70$6.25$10.00$10.00$3.56$13.00
14Asphalt (RC-250) (316-7016)GAL499$30.00$19.50$10.00$7.00$8.00$9.60$4.00
15Aggregate (type-B or L, GR-5) (316-7251)CY15$450.00$1,260.00$600.00$375.00$900.00$767.00$1,400.00
16SP mixes SP-B PG64-22 (344-7001)TON606$250.00$141.25$180.00$170.00$172.00$156.00$184.00
17SP mixes SP-C PG76-22 (344-7029)TON313$350.00$170.00$200.00$200.00$205.00$223.00$203.00
18Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009)TON235$250.00$200.00$220.00$245.00$253.00$261.00$265.00
19Plane & text asphalt concrete pavement(0" to 4") (354-7004)SY1,258$6.00$11.00$8.75$6.00$8.00$16.00$14.00
20Drilled shaft (traffic signal pole) (30 in) (416-7043)LF14$600.00$177.47$250.00$220.00$250.00$197.20$188.53
21Drilled shaft (traffic signal pole) (48 in) (416-7046)LF44$675.00$317.90$390.00$375.00$380.00$353.30$337.71
22Riprap (concrete) (CL B) (4 in) (432-7007)CY5$1,000.00$520.00$1,000.00$1,750.00$1,500.00$1,890.00$1,500.00
23Mobilization (500-7001)LS1$118,250$95,000$69,000$99,000$110,000$139,000$120,000
24Barricades, signs and traffic handling (502-7001)MO5$5,000.00$1,100.00$2,200.00$4,000.00$5,000.00$18,300$15,000
25Portable changeable message sign (503-7002)EACH2$7,500.00$8,500.00$2,500.00$20,000$15,000$4,400.00$5,000.00
26TMA (stationary) (505-7001)DAY150$275.00$220.00$280.00$130.00$200.00$500.00$200.00
27TMA (mobile operation) (505-7003)DAY4$400.00$175.00$1,500.00$600.00$200.00$900.00$200.00
28Biodegradable erosion control logs (install) (12") (506-7044)LF100$10.00$9.00$25.00$10.00$5.00$10.00$10.00
29Biodegradable erosion control logs (remove) (506-7046)LF100$6.50$4.00$6.75$5.00$5.00$4.40$3.00
30Driveways (ACP) (530-7010)SY205$95.00$16.00$68.00$65.00$220.00$149.00$220.00
31Mill rumble strips (asphalt) (shoulder) (533-7001)LF842$2.75$5.00$7.50$6.00$3.40$6.00$9.00
32Mailbox install-S (TWG-post) type 2 (560-7002)EACH2$500.00$475.00$650.00$500.00$500.00$406.00$465.00
33Conduit (PVC) (schedule 40) (2") (618-7030)LF1,894$21.00$11.70$13.00$14.00$8.50$13.00$13.00
34Conduit (PVC) (schedule 40) (2") (bore) (618-7031)LF565$27.50$15.68$22.00$20.00$15.00$17.42$17.00
35Conduit (PVC) (schedule 40) (4") (618-7040)LF105$27.50$18.10$16.00$22.00$23.00$20.00$20.00
36Conduit (PVC) (schedule 40) (4") (bore) (618-7041)LF175$105.00$19.71$24.00$25.00$25.00$22.00$21.00
37Electrical conductor (no.8) insulated (620-7008)LF445$2.75$1.71$2.25$2.00$2.00$2.00$2.00
38Electrical conductor (no.6) insulated (620-7010)LF2,650$4.00$2.35$2.00$2.75$2.00$2.61$2.50
39Ground box type B (122322)W/apron (624-7004)EACH6$1,300.00$1,097.94$1,300.00$1,300.00$1,100.00$1,220.00$1,200.00
40Ground box type D (162922)W/apron (624-7008)EACH4$1,700.00$1,097.94$1,400.00$1,300.00$1,400.00$1,220.00$1,200.00
41Aluminum signs (type A) (636-7001)SF82$50.00$45.00$61.00$75.00$32.00$32.25$50.00
42Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH7$1,025.00$496.20$680.00$700.00$510.00$612.00$690.00
43Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH10$1,200.00$584.80$800.00$850.00$600.00$834.00$830.00
44Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH2$1,350.00$712.80$970.00$1,050.00$720.00$1,067.00$960.00
45Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH1$1,100.00$831.00$1,100.00$1,200.00$900.00$1,167.00$1,100.00
46Remove SM RD SN sup&AM (644-7073)EACH24$175.00$85.00$120.00$20.00$100.00$184.00$210.00
47Work zone pavement marking non-removing (W)6"(broken) (662-7005)LF200$3.00$3.00$4.00$6.00$3.20$6.00$2.50
48Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF200$2.00$3.00$4.00$6.00$3.20$6.00$5.50
49Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF100$4.00$3.00$4.00$6.00$3.20$6.00$5.50
50Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH50$5.00$1.00$1.00$4.00$2.00$2.00$2.00
51Reflectorized pavement marking type I (W)8"(DOT)(090MIL) (666-7017)LF76$3.50$1.55$1.25$2.50$3.50$3.00$2.10
52Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023)LF1,782$3.00$1.55$2.00$2.25$1.60$1.94$1.90
53Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035)LF143$20.00$9.10$12.00$10.00$10.00$9.00$8.50
54Reflectorized pavement marking type I (Y)8"(solid)(090MIL) (666-7113)LF79$3.50$1.55$4.00$10.00$3.20$9.00$8.50
55Reflectorized pavement marking type I (W)6"(broken)(090MIL)(callout) (666-7144)LF1,276$2.00$1.55$2.00$1.00$1.70$1.00$1.00
56Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265)LF5,632$1.00$1.45$2.00$1.50$1.50$1.30$1.25
57Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269)LF6,571$1.00$1.45$2.00$1.50$1.50$1.30$1.25
58Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273)LF497$1.25$1.50$2.00$1.50$1.60$1.30$1.25
59Prefabricated PM type C (W)(arrow) (668-7091)EACH8$275.00$375.00$510.00$330.00$421.50$343.00$327.00
60Prefabricated PM type C (W)(word) (668-7103)EACH6$315.00$285.00$390.00$425.00$320.35$419.00$400.00
61Reflectorized pavement marker type I-C (672-7002)EACH8$7.50$9.00$12.00$10.00$10.15$9.00$8.50
62Reflectorized pavement marker type II-A-A (672-7004)EACH50$8.50$9.00$12.00$10.00$10.15$9.00$8.50
63Reflectorized pavement marker type II-C-R (672-7006)EACH165$7.25$6.00$8.25$10.00$6.75$9.00$8.50
64Eliminating existing PM & markers (6") (677-7002)LF4,812$1.00$0.55$0.75$0.75$0.65$0.58$0.55
65Eliminating existing PM & markers (8") (677-7004)LF137$2.00$1.00$1.25$1.25$1.15$1.20$1.10
66Eliminating existing PM & markers (24") (677-7008)LF48$5.25$3.50$4.75$2.50$3.95$2.40$2.20
67Eliminating existing PM & markers (arrow) (677-7009)EACH2$125.00$55.00$75.00$85.00$61.85$78.00$74.00
68Eliminating existing PM & markers (word) (677-7015)EACH2$125.00$55.00$75.00$85.00$61.85$78.00$74.00
69Install highway traffic signal (isolated) (680-7002)EACH1$60,000$30,397$63,000$42,000$46,700$33,775$33,000
70Vehicle signal section (12")LED(green) (682-7001)EACH7$300.00$222.57$250.00$275.00$460.00$247.00$236.00
71Vehicle signal section (12")LED(green arrow) (682-7002)EACH2$320.00$222.48$250.00$275.00$460.00$247.00$236.00
72Vehicle signal section (12")LED(yel) (682-7003)EACH13$360.00$222.54$250.00$275.00$460.00$247.00$236.00
73Vehicle signal section (12")LED(yel arrow) (682-7004)EACH2$375.00$222.48$250.00$275.00$460.00$247.00$236.00
74Vehicle signal section (12")LED(red) (682-7005)EACH7$300.00$222.57$250.00$275.00$460.00$247.00$236.00
75Vehicle signal section (12")LED(red arrow) (682-7006)EACH1$300.00$223.03$250.00$275.00$460.00$248.00$236.00
76Backplate W/ref border(3 sec)(vent)aluminum (682-7042)EACH6$200.00$146.45$180.00$200.00$250.00$163.00$155.00
77Backplate W/ref border(4 sec)(vent)aluminum (682-7043)EACH2$350.00$187.05$220.00$225.00$350.00$208.00$200.00
78Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010)LF4,441$5.00$1.93$2.50$2.25$3.00$2.14$2.05
79Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012)LF835$3.75$2.36$3.25$2.75$4.00$2.62$2.50
80Install RDSD flash beacon assembly (685-7001)EACH3$6,000.00$4,622.39$4,700.00$5,500.00$5,800.00$5,137.00$5,000.00
81Ins traffic signal PL AM (S)STR(type A) (686-7006)EACH1$8,000.00$6,086.39$11,000$7,200.00$12,000$6,763.00$6,500.00
82Ins traffic signal PL AM(S)1 arm(50')lum (686-7055)EACH1$45,000$37,268$35,000$46,000$40,000$41,410$39,000
83Ins traffic signal PL AM(S)2 arm(65-44')lum (686-7279)EACH1$60,000$44,711$46,000$56,000$51,000$49,680$47,000
84Bonding course (3007-7001)GAL406$7.00$3.50$11.00$6.00$4.00$4.50$3.00
85ITS com CBL (ethernet) (6005-7001)LF50$5.00$2.93$2.00$3.50$2.00$3.26$3.20
86Bbu system (external battery cabinet) (6007-7001)EACH1$9,700.00$10,416$9,500.00$12,000$11,000$11,575$11,000
87Installation of cellular modem (6015-7001)EACH1$1,200.00$52.09$660.00$75.00$3,000.00$58.00$55.00
88VDS prosr sys (6017-7001)EACH1$13,500$11,847$14,000$14,000$16,000$13,170$12,600
89VIVDS cam assy var LNS (6017-7003)EACH1$3,200.00$2,055.56$2,400.00$2,500.00$3,000.00$2,290.00$2,200.00
90HVDS W/var LNS (6017-7008)EACH2$7,500.00$10,630$6,100.00$12,000$7,000.00$11,800$11,300
91VDS CNTRL software (6017-7009)EACH1$520.00$361.79$1,400.00$425.00$760.00$405.00$385.00
92VDS cabling (6017-7012)LF670$2.60$2.30$3.00$3.00$1.40$2.56$2.50
93CCTV field equipment (digital) (6018-7002)EACH1$7,500.00$5,921.39$2,900.00$7,500.00$3,800.00$6,580.00$6,290.00
94CCTV mount (pole) (6018-7003)EACH1$1,500.00$403.74$480.00$600.00$1,000.00$450.00$428.00
TxDOT contract A00196756: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of May 2, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy