TxDOT contract A00045158 bid tabulation

Rehabilitate Existing Roadway, FM 547 (US 380 to FM 6). Let by Texas DOT on May 2, 2025, Collin, Dallas District. 8 bids received; low bid $16,422,403 by A. K. Gillis & Sons, LLC, -28% against the engineer's estimate of $22,962,770.

Owner
Texas DOT
Letting
02 MAY 2025
Pay items
95
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1A. K. Gillis & Sons, LLC$16,422,403Low-28%
2D. L. Lennon Incorporated - Contractor$16,649,077+1.0%-27%
3Austin Bridge & Road Services, LP$19,180,388+17%-16%
4Foutsco Paving Company, LLC$19,476,996+19%-15%
5Highway 19 Construction LLC$20,210,714+23%-12%
6Ed Bell Construction Company$21,496,922+31%-6.0%
7Grey Sky Construction LLC$22,577,319+37%-2.0%
8Harper Brothers Construction LLC$24,363,227+48%+6.0%
TxDOT contract A00045158: bids by rank

Engineer's estimate: $22,962,770.

Bid tabulation

LinePay itemUnitQuantityEstimate1. A. K. Gillis & Sons, LLC2. D. L. Lennon Incorporated - Contractor3. Austin Bridge & Road Services, LP4. Foutsco Paving Company, LLC5. Highway 19 Construction LLC6. Ed Bell Construction Company
1Preparing row (100-7002)STA409.07$2,671.25$350.00$350.00$4,688.77$500.00$280.00$5,250.00
2Removing concrete (driveways) (104-7011)SY1,794$30.00$12.00$18.50$20.00$11.00$25.00$25.00
3Remove (6") TRT/untrt base & asphalt pavement (105-7026)SY2,412$60.00$9.24$15.00$5.25$20.00$6.00$10.50
4Excavation (roadway) (110-7001)CY24,434$25.00$22.00$16.00$11.07$9.00$15.00$1.00
5Embankment (final)(DC)(type C) (132-7006)CY26,715$30.00$22.00$19.00$21.17$14.00$30.00$27.50
6Backfill (type A or B) (134-7004)STA409.07$450.00$275.00$365.00$123.30$200.00$350.00$630.00
7Blading (150-7001)STA409.07$30.00$250.00$315.00$875.67$150.00$250.00$1,050.00
8Drill seed (permanent_rural_clay) (164-7010)SY222,501$0.30$0.18$0.18$0.29$0.18$0.36$0.25
9Drill seed (temporary_warm_cool) (164-7015)SY222,501$0.66$0.16$0.16$0.21$0.10$0.35$0.15
10Vegetative watering (168-7001)TGL66,199$10.00$0.01$0.01$0.13$0.01$1.00$1.00
11FL BS (compacted in place)(type D GR 1-2) (10") (247-7102)SY140,712$36.52$25.29$25.00$21.06$33.30$35.00$27.50
12FL BS (roadway del) (type D GR 1-2) (247-7209)TON35,182$59.00$49.77$50.00$37.27$7.00$60.00$37.50
13Rework BS metal (type C)(12")(ord comp) (251-7055)SY107,225$5.40$2.90$2.30$4.41$7.00$2.50$5.25
14Cement (275-7001)TON738$250.00$220.00$240.00$220.04$250.00$215.00$280.00
15Cement TRT (existing material & new base)(6") (275-7006)SY145,302$2.50$2.85$2.16$2.42$6.50$2.50$2.00
16Prime coat(MC-30 or AE-P) (310-7013)GAL28,145$7.30$6.17$5.00$4.66$1.00$6.85$6.35
17Asphalt (CRS-2P) (316-7012)GAL35,182$4.00$5.26$5.00$4.41$3.00$4.31$6.24
18Asphalt (AC-15P, AC-20-5TR or AC-20XP) (316-7071)GAL29,552$8.20$5.46$5.00$5.04$3.00$4.94$6.50
19Aggregate (type-B or L, GR-3)(sac-B) (316-7244)CY1,352$250.00$172.84$144.00$258.00$400.00$248.00$323.78
20SP mixes SP-C sac-B PG64-22 (344-7011)TON24,844$130.00$128.40$143.40$109.10$164.00$148.00$134.69
21Plane & text asphalt concrete pavement(0" to 6") (354-7005)SY107,225$5.00$5.57$7.62$5.25$5.60$5.00$6.30
22Cut & restoring pavement (400-7006)SY265$266.25$75.00$20.00$183.70$20.00$250.00$315.00
23Trench excavation protection (402-7001)LF172$50.00$15.00$5.00$10.83$5.00$10.00$30.00
24Temporary special shoring (403-7001)SF2,404$50.00$5.00$75.00$91.00$60.00$55.00$90.00
25Riprap (stone protection)(12 in) (432-7041)CY599$250.00$290.62$250.00$215.44$250.00$180.00$426.00
26Concrete box culvert (6 FT X 5 FT)(extend) (462-7068)LF58$1,100.00$1,200.00$1,100.00$803.52$1,100.00$650.00$1,144.00
27Concrete box culvert (9 FT X 5 FT)(extend) (462-7082)LF28$1,162.50$1,500.00$1,250.00$1,004.39$1,250.00$900.00$1,300.00
28RC pipe (CL III)(24 in) (464-7005)LF5,990$115.00$80.00$68.50$70.31$69.00$83.00$71.24
29RC pipe (CL III)(30 in) (464-7007)LF45$220.00$115.00$112.00$90.40$112.00$139.00$116.48
30RC pipe (CL III)(36 in) (464-7009)LF65$265.00$160.00$150.00$150.66$150.00$201.00$156.00
31RC pipe (CL III)(48 in) (464-7011)LF67$400.00$275.00$250.00$251.10$250.00$300.00$260.00
32RC pipe (CL V)(24 in) (464-7034)LF121$200.00$105.00$90.00$90.40$90.00$185.00$93.60
33RC pipe (CL V)(36 in) (464-7037)LF98$250.00$200.00$190.00$170.75$190.00$331.00$197.60
34Headwall (CH - FW - 0) (diameter= 24 in) (466-7005)EACH1$17,500$6,000.00$5,800.00$7,030.76$5,800.00$4,500.00$6,500.00
35Headwall (CH - PW - 0) (diameter= 24 in) (466-7101)EACH7$9,000.00$6,500.00$6,300.00$6,603.89$6,300.00$450.00$7,500.00
36Headwall (CH - PW - 0) (diameter= 30 in) (466-7103)EACH1$11,000$8,000.00$7,850.00$9,541.74$7,850.00$600.00$9,000.00
37Headwall (CH - PW - 0) (diameter= 36 in) (466-7105)EACH4$14,000$10,000$9,500.00$11,802$9,500.00$7,500.00$11,500
38Headwall (CH - PW - 0) (diameter= 48 in) (466-7107)EACH1$16,000$15,000$11,000$13,810$11,000$10,500$14,000
39Wingwall (PW - 1) (HW=6 FT) (466-7176)EACH4$15,000$22,000$28,500$17,577$28,500$18,000$30,000
40Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325)EACH5$1,700.00$1,200.00$1,000.00$1,155.05$1,000.00$1,100.00$1,500.00
41Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326)EACH8$2,000.00$1,275.00$1,100.00$1,205.27$1,100.00$1,300.00$1,575.00
42Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH332$1,200.00$1,300.00$1,100.00$1,381.04$1,100.00$1,800.00$1,000.00
43Set (type II) (30 in) (RCP) (3: 1) (C) (467-7345)EACH1$4,200.00$1,700.00$2,000.00$1,506.59$2,000.00$3,100.00$3,000.00
44Set (type II) (48 in) (RCP) (4: 1) (C) (467-7390)EACH2$6,500.00$9,000.00$8,500.00$7,784.06$8,500.00$10,500$10,000
45Clean existing culverts (480-7001)EACH11$4,000.00$1,200.00$1,000.00$2,510.99$1,000.00$2,500.00$4,000.00
46Removing structure (set) (496-7004)EACH101$250.00$125.00$148.00$175.77$148.00$500.00$350.00
47Removing structure (wingwall) (496-7005)EACH16$3,150.00$1,000.00$900.00$1,004.39$900.00$1,000.00$6,000.00
48Removing structure (headwall) (496-7006)EACH15$3,300.00$1,000.00$900.00$753.30$900.00$500.00$4,500.00
49Removing structure (pipe) (496-7007)LF3,797$21.90$8.00$5.00$15.07$5.00$50.00$17.50
50Removing structure (box culvert) (496-7008)LF13$225.50$100.00$100.00$200.88$100.00$100.00$750.00
51Mobilization (500-7001)LS1$2,114,220$905,756$871,500$2,109,843$1,900,000$2,000,000$1,825,000
52Barricades, signs and traffic handling (502-7001)MO15$20,000$10,800$6,231.00$77,252$100,000$10,000$63,000
53Portable changeable message sign (503-7002)EACH2$15,000$17,500$22,000$21,650$28,000$15,000$20,000
54TMA (stationary) (505-7001)DAY238$450.00$150.00$265.00$500.00$1.00$300.00$157.50
55TMA (mobile operation) (505-7002)HR40$150.00$150.00$175.00$200.00$65.00$100.00$157.50
56Rock filter dams (install) (type 3) (506-7003)LF750$71.18$50.00$50.00$91.00$35.00$85.00$70.29
57Rock filter dams (remove) (506-7011)LF905$11.00$12.00$12.00$15.00$7.00$10.00$13.85
58Construction exits (install) (type 1) (506-7020)SY339$28.00$30.00$30.00$40.56$15.00$36.00$38.34
59Construction exits (remove) (506-7024)SY339$10.00$10.00$10.00$12.00$5.00$11.00$11.72
60Temporary sediment control fence (install) (506-7039)LF8,042$5.00$4.50$3.89$3.53$3.00$3.55$3.78
61Temporary sediment control fence (remove) (506-7041)LF8,042$1.25$1.00$0.35$0.88$0.30$1.00$1.33
62Biodegradable erosion control logs (install) (12") (506-7044)LF1,463$6.00$5.50$5.50$4.37$4.00$6.00$5.59
63Biodegradable erosion control logs (install) (18") (506-7045)LF5,350$9.00$7.00$7.00$5.23$4.00$6.00$6.39
64Biodegradable erosion control logs (remove) (506-7046)LF6,813$2.00$0.75$0.30$0.88$0.30$1.00$1.33
65Rock filter dams (install) (type 2) 6:1 (506-7048)LF155$85.00$60.00$60.00$102.00$50.00$50.00$52.19
66Driveways (concrete) (530-7006)SY1,830$130.00$159.05$177.05$149.82$98.00$110.00$175.00
67Driveways (ACP) (530-7010)SY7,427$75.00$82.80$79.80$84.54$80.00$84.00$90.00
68Mill rumble strips (asphalt) (shoulder) (533-7001)LF78,645$1.00$0.17$1.14$0.06$0.16$0.25$0.13
69Mill rumble strips (asphalt) (centerline) (533-7002)LF38,296$0.75$0.17$1.16$0.08$0.16$0.25$0.13
70Remove metal beam guard fence (542-7001)LF104$5.41$10.00$25.00$5.00$5.00$3.00$10.65
71Guardrail end treatment (remove) (544-7003)EACH2$315.00$500.00$500.00$375.00$375.00$480.00$372.75
72Mailbox install-S (TWW-post) type 4 (560-7008)EACH74$315.00$225.00$269.00$225.00$322.00$315.00$282.23
73Mailbox install-D (TWW-post) type 4 (560-7009)EACH18$275.00$250.00$370.00$250.00$357.00$355.00$292.88
74Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH72$710.00$660.00$800.00$660.00$630.00$710.00$692.25
75Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002)EACH18$900.00$685.00$890.00$685.00$750.00$355.00$740.18
76Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH3$960.00$800.00$950.00$800.00$740.00$880.00$782.78
77Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH4$944.80$890.00$1,050.00$890.00$1,190.00$1,100.00$953.18
78Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH2$1,175.00$990.00$1,300.00$990.00$1,300.00$1,500.00$1,171.50
79Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034)EACH5$1,169.00$995.00$1,630.00$995.00$1,525.00$1,500.00$1,336.58
80Relocate SM RD SN sup&AM type S80 (644-7067)EACH1$650.00$550.00$1,500.00$550.00$755.00$800.00$639.00
81Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF81,697$0.52$0.27$0.27$0.27$0.27$0.27$0.29
82Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF81,697$0.52$0.27$0.27$0.27$0.27$0.27$0.29
83Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH41$1.50$2.45$3.00$5.00$4.00$5.00$4.82
84Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH1,043$1.40$2.45$3.00$2.00$4.00$2.00$4.89
85Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF453$1.50$1.80$1.80$1.80$1.00$1.80$1.92
86Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF38$2.00$3.00$3.00$3.00$2.00$3.00$3.20
87Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF704$2.85$1.50$1.50$1.50$7.75$1.50$1.60
88Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF219$9.25$10.00$10.00$10.00$7.75$10.00$10.65
89Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH4$200.00$195.00$195.00$195.00$160.00$195.00$207.68
90Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH4$225.00$250.00$250.00$250.00$170.00$195.00$266.25
91Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF85,497$1.00$0.57$0.57$0.57$0.55$0.57$0.61
92Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF8,840$1.00$0.60$0.60$0.60$0.59$0.60$0.64
93Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF23,753$1.00$0.57$0.57$0.57$0.57$0.57$0.61
94Reflectorized pavement marker type I-C (672-7002)EACH35$6.00$5.50$5.50$5.50$4.50$5.50$5.86
95Reflectorized pavement marker type II-A-A (672-7004)EACH741$6.00$5.50$5.50$5.50$4.00$5.50$5.86
TxDOT contract A00045158: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of May 2, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy