TxDOT contract A00195603 bid tabulation
Rehabilitate Existing Roadway, US 77 (SH 71 to BU 71E). Let by Texas DOT on January 6, 2026, Fayette, Yoakum District. 6 bids received; low bid $4,335,114 by Hunter Industries, LTD., +4.1% against the engineer's estimate of $4,163,925.
- Owner
- Texas DOT
- Letting
- 06 JAN 2026
- Pay items
- 63
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hunter Industries, LTD. | $4,335,114 | Low | +4.0% |
| 2 | STX Civil | $4,735,906 | +9.0% | +14% |
| 3 | D & D Contractors, Inc. | $4,776,510 | +10% | +15% |
| 4 | Big Creek Construction, LTD. | $4,987,996 | +15% | +20% |
| 5 | Acme Bridge Company, Inc. | $5,046,119 | +16% | +21% |
| 6 | Texas Materials Group, Inc. | $5,081,903 | +17% | +22% |
Engineer's estimate: $4,163,925.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hunter Industries, LTD. | 2. STX Civil | 3. D & D Contractors, Inc. | 4. Big Creek Construction, LTD. | 5. Acme Bridge Company, Inc. | 6. Texas Materials Group, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 35 | $2,500.00 | $2,076.80 | $500.00 | $616.88 | $3,000.00 | $4,500.00 | $1,085.00 |
| 2 | Remove (12"-16") TRT/untrt base & asphalt pavement (105-7012) | SY | 25,129 | $6.50 | $14.45 | $5.00 | $12.50 | $12.00 | $12.50 | $16.75 |
| 3 | Embankment (final)(OC)(type A) (132-7001) | CY | 100 | $40.00 | $88.00 | $45.00 | $115.11 | $35.00 | $159.00 | $115.00 |
| 4 | Block sodding (162-7002) | SY | 124 | $7.00 | $15.75 | $10.00 | $77.27 | $17.00 | $23.20 | $11.00 |
| 5 | Vegetative watering (168-7001) | TGL | 1.20 | $25.00 | $35.75 | $1.00 | $6,852.49 | $95.00 | $121.00 | $995.00 |
| 6 | Lime (com or QK)(slurry) (260-7005) | TON | 112 | $325.00 | $385.00 | $425.00 | $470.02 | $350.00 | $400.00 | $371.00 |
| 7 | Lime TRT (existing material)(8") (260-7007) | SY | 5,611 | $5.00 | $8.80 | $5.00 | $3.94 | $5.50 | $8.70 | $11.00 |
| 8 | Cement (275-7001) | TON | 68 | $325.00 | $242.00 | $235.00 | $348.15 | $300.00 | $352.00 | $218.00 |
| 9 | Cement TRT (existing material)(8") (275-7003) | SY | 5,610 | $5.00 | $4.40 | $5.00 | $3.78 | $5.50 | $6.20 | $5.50 |
| 10 | Asphalt (RC-250) (316-7016) | GAL | 267 | $6.05 | $20.00 | $6.72 | $7.00 | $17.80 | $10.00 | |
| 11 | Aggregate (type-E, GR-5)(sac-B) (316-7194) | CY | 10 | $374.00 | $1,000.00 | $659.90 | $700.00 | $915.00 | $1,237.00 | |
| 12 | Aggregate (type-PE, GR-4)(sac-B) (316-7232) | CY | 779 | $130.00 | $149.68 | $300.00 | $353.81 | $160.00 | $232.00 | $223.00 |
| 13 | Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264) | GAL | 22,462 | $4.25 | $3.74 | $5.00 | $5.15 | $3.50 | $4.05 | $3.25 |
| 14 | D-GR HMA type-B sac-B PG70-22 (341-7007) | TON | 13,950 | $95.00 | $101.20 | $125.00 | $107.78 | $128.00 | $106.00 | $120.00 |
| 15 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 5,488 | $100.00 | $102.30 | $146.00 | $112.49 | $138.00 | $135.00 | $138.00 |
| 16 | Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009) | TON | 1,677 | $161.70 | $191.00 | $166.00 | $152.00 | $178.00 | $174.00 | |
| 17 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 39,566 | $5.00 | $2.53 | $1.10 | $2.69 | $3.00 | $2.15 | $2.50 |
| 18 | Riprap (mow strip)(4 in) (432-7013) | CY | 63 | $682.48 | $700.00 | $993.81 | $950.00 | $1,000.00 | $1,000.00 | |
| 19 | Cleaning and sealing existing joints (438-7001) | LF | 264 | $46.80 | $50.00 | $74.17 | $42.00 | $40.00 | $24.00 | |
| 20 | RC pipe (CL III)(18 in) (464-7003) | LF | 50 | $220.49 | $110.00 | $243.31 | $350.00 | $150.00 | $234.00 | |
| 21 | Adjusting manholes (479-7001) | EACH | 5 | $1,500.00 | $1,650.00 | $1,650.00 | $3,528.64 | $850.00 | $2,000.00 | $2,350.00 |
| 22 | Remove STR (bollard) (496-7028) | EACH | 4 | $400.00 | $150.00 | $435.00 | $2,214.80 | $725.00 | $264.00 | $290.00 |
| 23 | Mobilization (500-7001) | LS | 1 | $395,000 | $334,640 | $330,500 | $157,045 | $450,000 | $462,000 | $346,500 |
| 24 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $6,000.00 | $5,382.77 | $3,500.00 | $5,910.44 | $5,000.00 | $15,000 | $2,150.00 |
| 25 | Portable changeable message sign (503-7002) | EACH | 2 | $8,000.00 | $5,000.00 | $7,500.00 | $25,379 | $17,000 | $17,000 | $5,875.00 |
| 26 | TMA (stationary) (505-7001) | DAY | 134 | $150.00 | $125.00 | $285.61 | $200.00 | $200.00 | $460.00 | |
| 27 | TMA (mobile operation) (505-7003) | DAY | 10 | $250.00 | $150.00 | $1,415.20 | $950.00 | $556.00 | $460.00 | |
| 28 | Sandbags for erosion control (506-7035) | EACH | 200 | $20.00 | $8.40 | $1.00 | $56.29 | $9.00 | $17.90 | $27.00 |
| 29 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 335 | $11.00 | $11.09 | $8.00 | $32.97 | $12.00 | $10.00 | $8.00 |
| 30 | Biodegradable erosion control logs (remove) (506-7046) | LF | 335 | $2.00 | $3.70 | $2.00 | $26.16 | $4.25 | $2.00 | $2.00 |
| 31 | Concrete curb & gutter (type II) (529-7009) | LF | 699 | $50.00 | $42.00 | $28.00 | $52.31 | $65.00 | $70.60 | $123.42 |
| 32 | Driveways (concrete) (type 1) (530-7008) | SY | 204 | $111.30 | $115.00 | $188.85 | $210.00 | $209.00 | $126.00 | |
| 33 | Driveways (concrete) (type 2) (530-7009) | SY | 1,022 | $125.00 | $120.75 | $135.00 | $133.34 | $115.00 | $170.00 | $94.00 |
| 34 | Driveways (surface treat) (530-7016) | SY | 4,498 | $35.00 | $48.40 | $35.00 | $30.27 | $20.00 | $14.60 | $55.00 |
| 35 | Concrete sidewalks (5") (531-7002) | SY | 1,118 | $105.00 | $94.50 | $90.00 | $99.27 | $100.00 | $137.00 | $118.00 |
| 36 | Curb ramps (type 1) (531-7005) | EACH | 20 | $2,500.00 | $2,624.93 | $2,500.00 | $3,814.78 | $1,200.00 | $2,900.00 | $1,782.00 |
| 37 | Curb ramps (type 21) (531-7013) | EACH | 1 | $2,624.93 | $2,500.00 | $11,598 | $1,750.00 | $3,240.00 | $2,650.00 | |
| 38 | Concrete median (536-7002) | SY | 11 | $250.00 | $199.49 | $2,500.00 | $1,068.30 | $200.00 | $345.00 | $405.00 |
| 39 | Metal W-beam guard fence (timber post) (540-7001) | LF | 600 | $25.20 | $32.00 | $40.90 | $35.00 | $27.70 | $32.00 | |
| 40 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 6 | $2,572.43 | $2,270.00 | $3,357.51 | $2,500.00 | $2,700.00 | $3,183.00 | |
| 41 | Connector plate for thrie beam (540-7030) | EACH | 6 | $997.47 | $1,510.00 | $2,597.03 | $900.00 | $1,100.00 | $1,060.00 | |
| 42 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,149.91 | $3,600.00 | $4,429.25 | $4,000.00 | $3,460.00 | $4,075.00 | |
| 43 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 5 | $803.23 | $980.00 | $2,506.91 | $900.00 | $796.00 | $837.00 | |
| 44 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 4 | $900.00 | $986.97 | $1,205.00 | $3,115.20 | $1,000.00 | $1,410.00 | $970.00 |
| 45 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 5 | $593.23 | $725.00 | $2,279.91 | $850.00 | $455.00 | $765.00 | |
| 46 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 1 | $682.48 | $835.00 | $8,930.80 | $900.00 | $550.00 | $870.00 | |
| 47 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 36,092 | $0.38 | $0.24 | $0.55 | $0.49 | $0.50 | $0.46 | $0.40 |
| 48 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 46,394 | $0.38 | $0.24 | $0.55 | $0.44 | $0.50 | $0.46 | $0.40 |
| 49 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 921 | $3.50 | $1.72 | $0.51 | $11.79 | $2.00 | $2.20 | $1.10 |
| 50 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 900 | $3.00 | $1.72 | $0.51 | $12.00 | $2.00 | $2.20 | $1.10 |
| 51 | Type I high perf PM (W)4"(solid)(100MIL) (666-7287) | LF | 126 | $4.00 | $1.05 | $2.05 | $66.16 | $1.15 | $1.70 | $1.10 |
| 52 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 27,407 | $0.75 | $0.57 | $0.90 | $0.91 | $1.00 | $0.74 | $0.70 |
| 53 | Type I high perf PM (Y)6"(broken)(100MIL) (666-7302) | LF | 617 | $0.75 | $0.60 | $0.90 | $13.93 | $1.00 | $0.74 | $0.70 |
| 54 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 28,051 | $0.75 | $0.57 | $0.90 | $0.90 | $1.00 | $0.74 | $0.70 |
| 55 | Prefabricated PM type C (W)(8")(broken) (668-7081) | LF | 45 | $4.41 | $5.51 | $186.83 | $9.00 | $4.55 | $7.80 | |
| 56 | Prefabricated PM type C (W)(8")(solid) (668-7084) | LF | 540 | $4.41 | $4.36 | $19.94 | $9.00 | $3.60 | $7.80 | |
| 57 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 528 | $26.00 | $11.97 | $16.22 | $28.46 | $18.00 | $13.40 | $16.75 |
| 58 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 4 | $209.99 | $320.60 | $2,275.27 | $275.00 | $265.00 | $251.00 | |
| 59 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 3 | $288.74 | $320.60 | $3,043.14 | $350.00 | $265.00 | $335.00 | |
| 60 | Prefabricated PM type C (W)(RR crossing) (668-7108) | EACH | 2 | $500.00 | $419.99 | $782.27 | $4,550.53 | $700.00 | $646.00 | $698.00 |
| 61 | Reflectorized pavement marker type I-C (672-7002) | EACH | 43 | $6.00 | $4.20 | $8.98 | $195.07 | $7.00 | $7.40 | $6.70 |
| 62 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 331 | $6.00 | $4.20 | $8.98 | $29.29 | $7.00 | $7.40 | $6.70 |
| 63 | Drain inlet cleaning (764-7001) | EACH | 8 | $700.00 | $500.00 | $350.00 | $1,195.05 | $1,000.00 | $1,060.00 | $1,710.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.