TxDOT contract A00196688 bid tabulation
Install/Upgrade Roadway Lighting, IH 35E (Commerce St to IH 635). Let by Texas DOT on March 4, 2025, Dallas, Dallas District. 3 bids received; low bid $12,555,491 by Sice, Inc., -2.2% against the engineer's estimate of $12,837,003.
- Owner
- Texas DOT
- Letting
- 04 MAR 2025
- Pay items
- 89
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sice, Inc. | $12,555,491 | Low | -2.0% |
| 2 | Elecnor Belco Electric, Inc. | $12,690,888 | +1.0% | -1.0% |
| 3 | Mica Corporation | $18,084,331 | +44% | +41% |
Engineer's estimate: $12,837,003.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Sice, Inc. | 2. Elecnor Belco Electric, Inc. | 3. Mica Corporation |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 80 | $22.50 | $87.14 | $22.00 | $66.00 |
| 2 | Drilled shaft (42 in) (416-7007) | LF | 19 | $719.55 | $520.00 | $750.00 | |
| 3 | Drilled shaft (high mast pole) (48 in) (416-7035) | LF | 948 | $825.00 | $1,084.26 | $560.00 | $921.00 |
| 4 | Drilled shaft (high mast pole) (54 in) (416-7036) | LF | 100 | $850.00 | $1,206.81 | $1,000.00 | $980.00 |
| 5 | Drilled shaft (high mast pole) (60 in) (416-7037) | LF | 172 | $875.00 | $1,097.09 | $1,500.00 | $965.00 |
| 6 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 456 | $340.00 | $412.47 | $378.00 | $300.00 |
| 7 | Riprap (concrete)(4 in) (432-7001) | CY | 122.25 | $600.00 | $1,756.83 | $648.00 | $840.00 |
| 8 | Riprap (concrete)(CL B) (432-7005) | CY | 15 | $550.00 | $1,757.78 | $544.00 | $960.00 |
| 9 | Riprap (mow strip)(4 in) (432-7013) | CY | 113 | $680.00 | $1,756.65 | $655.00 | $855.00 |
| 10 | Mobilization (500-7001) | LS | 1 | $500,000 | $946,505 | $1,046,099 | $1,562,200 |
| 11 | Barricades, signs and traffic handling (502-7001) | MO | 15 | $35,000 | $6,566.50 | $6,000.00 | $113,700 |
| 12 | Portable changeable message sign (503-7001) | DAY | 130 | $190.00 | $332.87 | $300.00 | $405.00 |
| 13 | TMA (stationary) (505-7001) | DAY | 130 | $525.00 | $668.88 | $425.00 | $810.00 |
| 14 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 1,100 | $10.00 | $3.35 | $12.00 | $19.50 |
| 15 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,100 | $2.00 | $1.31 | $7.00 | $7.50 |
| 16 | Concrete sidewalks (4") (531-7001) | SY | 70 | $275.00 | $122.18 | $97.00 | $145.00 |
| 17 | Metal W-beam guard fence (timber post) (540-7001) | LF | 2,525 | $25.00 | $31.53 | $31.00 | $39.50 |
| 18 | Downstream anchor terminal section (540-7015) | EACH | 14 | $1,400.00 | $1,462.93 | $1,571.00 | $2,000.00 |
| 19 | Remove downstream anchor terminal (542-7003) | EACH | 10 | $250.00 | $276.61 | $303.00 | $625.00 |
| 20 | Guardrail end treatment (install) (544-7001) | EACH | 5 | $3,200.00 | $3,565.13 | $3,480.00 | $4,000.00 |
| 21 | Guardrail end treatment (move & reset) (544-7002) | EACH | 3 | $1,100.00 | $1,383.03 | $1,813.00 | $1,440.00 |
| 22 | Guardrail end treatment (remove) (544-7003) | EACH | 1 | $325.00 | $399.54 | $363.00 | $700.00 |
| 23 | Remove RD IL asm (bridge mount) (610-7006) | EACH | 17 | $425.00 | $751.19 | $1,500.00 | $810.00 |
| 24 | Remove RD IL asm (shoe-base) (610-7007) | EACH | 6 | $1,000.00 | $751.19 | $1,500.00 | $810.00 |
| 25 | Remove RD IL asm (CTB mount) (610-7008) | EACH | 208 | $800.00 | $500.79 | $1,500.00 | $810.00 |
| 26 | Remove RD IL asm (trans-base) (610-7009) | EACH | 50 | $1,000.00 | $751.19 | $1,500.00 | $810.00 |
| 27 | Remove RD IL asm (U/P) (610-7010) | EACH | 125 | $430.00 | $791.21 | $1,500.00 | $1,220.00 |
| 28 | In RD IL (U/P) (type 1) (150W EQ) LED (610-7014) | EACH | 317 | $1,800.00 | $2,050.95 | $926.00 | $2,250.00 |
| 29 | In RD IL (type SA) 40B-4-4 (250W EQ) LED (610-7107) | EACH | 11 | $5,000.00 | $5,331.82 | $6,800.00 | $6,825.00 |
| 30 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 2 | $5,000.00 | $4,317.97 | $6,120.00 | $4,930.00 |
| 31 | In RD IL (type SP) 48S-8-8 (400W EQ) LED (610-7173) | EACH | 8 | $8,900.00 | $5,970.07 | $8,135.00 | $8,076.00 |
| 32 | In RD IL (type SA) 50T-8 (400W EQ) LED (610-7196) | EACH | 36 | $5,400.00 | $4,649.06 | $6,400.00 | $5,225.00 |
| 33 | HI MST IL pole (100 FT)( 80 MPH) (613-7001) | EACH | 42 | $45,000 | $35,340 | $34,000 | $42,710 |
| 34 | HI MST IL pole (125 FT)( 80 MPH) (613-7003) | EACH | 4 | $49,000 | $43,057 | $41,000 | $48,850 |
| 35 | HI MST IL pole (150 FT)( 80 MPH) (613-7005) | EACH | 5 | $55,000 | $48,767 | $47,000 | $54,950 |
| 36 | LED HI MST IL asm (6 fixt) (type S) (614-7001) | EACH | 6 | $41,500 | $34,826 | $41,300 | $40,660 |
| 37 | LED HI MST IL asm (6 fixt) (type A) (614-7002) | EACH | 42 | $39,500 | $34,754 | $40,200 | $40,915 |
| 38 | LED HI MST IL asm (6 fixt) (type C) (614-7004) | EACH | 3 | $41,500 | $34,608 | $40,600 | $40,445 |
| 39 | Replace LED HI MST IL(6 fixt) (type S) (614-7005) | EACH | 2 | $8,000.00 | $6,097.42 | $75,600 | $26,880 |
| 40 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 44,590 | $13.00 | $18.05 | $14.00 | $28.70 |
| 41 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 11,430 | $31.50 | $19.73 | $18.00 | $46.65 |
| 42 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 25 | $27.08 | $15.00 | $30.00 | |
| 43 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 8,565 | $20.82 | $20.00 | $29.55 | |
| 44 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 6,886 | $18.99 | $26.00 | $40.00 | |
| 45 | Conduit (RM) (1") (618-7072) | LF | 15,015 | $30.50 | $22.19 | $36.00 | $56.25 |
| 46 | Conduit (RM) (2") (618-7078) | LF | 1,145 | $54.00 | $33.58 | $43.00 | $65.05 |
| 47 | Conduit (prepare) (618-7090) | LF | 20,428 | $3.00 | $7.03 | $9.00 | $4.60 |
| 48 | ITS multi-duct CND (RMC) (619-7008) | LF | 435 | $277.56 | $95.00 | $205.00 | |
| 49 | Electrical conductor (no.12) bare (620-7003) | LF | 14,210 | $1.40 | $0.87 | $1.70 | $2.30 |
| 50 | Electrical conductor (no.12) insulated (620-7004) | LF | 29,790 | $1.45 | $1.19 | $1.80 | $2.35 |
| 51 | Electrical conductor (no.8) bare (620-7007) | LF | 11,130 | $1.85 | $1.07 | $2.40 | $3.15 |
| 52 | Electrical conductor (no.8) insulated (620-7008) | LF | 40,332 | $1.90 | $1.26 | $2.50 | $3.26 |
| 53 | Electrical conductor (no.6) bare (620-7009) | LF | 36,048 | $2.05 | $1.38 | $1.50 | $3.36 |
| 54 | Electrical conductor (no.6) insulated (620-7010) | LF | 79,476 | $2.25 | $1.65 | $3.00 | $3.64 |
| 55 | Electrical conductor (no.4) bare (620-7011) | LF | 20,019 | $3.90 | $1.91 | $3.00 | $3.86 |
| 56 | Electrical conductor (no.4) insulated (620-7012) | LF | 40,698 | $4.10 | $2.18 | $3.50 | $4.22 |
| 57 | Electrical conductor (no.2) bare (620-7015) | LF | 4,010 | $2.68 | $4.60 | $5.17 | |
| 58 | Electrical conductor (no.2) insulated (620-7016) | LF | 8,020 | $3.05 | $5.30 | $5.67 | |
| 59 | Electrical conductor (no.1) bare (620-7017) | LF | 6,364 | $4.82 | $6.00 | $5.87 | |
| 60 | Electrical conductor (no.1) insulated (620-7018) | LF | 12,548 | $4.60 | $6.00 | $6.05 | |
| 61 | Ground box type A (122311) (624-7001) | EACH | 51 | $1,025.00 | $907.86 | $1,375.00 | $1,743.00 |
| 62 | Ground box type A (122311)W/apron (624-7002) | EACH | 158 | $1,300.00 | $1,397.29 | $1,232.00 | $2,847.00 |
| 63 | Ground box type D (162922) (624-7007) | EACH | 2 | $1,154.21 | $1,632.00 | $1,905.00 | |
| 64 | Ground box type D (162922)W/apron (624-7008) | EACH | 23 | $1,722.34 | $1,314.00 | $3,120.00 | |
| 65 | Remove electrical services (628-7002) | EACH | 13 | $1,000.00 | $1,723.59 | $1,116.00 | $912.00 |
| 66 | Elc SRV type A 240/480 060(NS)SS(E)GC(O) (628-7044) | EACH | 17 | $10,000 | $5,282.03 | $9,525.00 | $13,500 |
| 67 | Elc SRV type D 120/240 060(NS)GS(N)EX(O) (628-7131) | EACH | 1 | $3,140.68 | $7,855.00 | $5,425.00 | |
| 68 | Elc SRV type D 120/240 060(NS)SS(N)PS(U) (628-7154) | EACH | 1 | $8,625.63 | $8,943.00 | $13,550 | |
| 69 | Elc SRV type D 120/240 070(NS)GS(N)EX(O) (628-7177) | EACH | 1 | $1,931.81 | $3,625.00 | $5,425.00 | |
| 70 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 4 | $853.03 | $1,813.00 | $1,900.00 | |
| 71 | Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012) | EACH | 7 | $754.56 | $1,571.00 | $1,820.00 | |
| 72 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 7 | $716.91 | $1,571.00 | $1,625.00 | |
| 73 | Install small roadside sign support and assembly TYS80(1)SB(T) (644-7040) | EACH | 7 | $527.81 | $1,813.00 | $1,585.00 | |
| 74 | Install small roadside sign support and assembly (inst sign only) (644-7064) | EACH | 1 | $450.88 | $605.00 | $825.00 | |
| 75 | Remove SM RD SN sup&AM (644-7073) | EACH | 23 | $121.39 | $182.00 | $920.00 | |
| 76 | Remove SM RD SN sup&AM (sign only) (644-7075) | EACH | 15 | $121.39 | $182.00 | $350.00 | |
| 77 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 224 | $32.16 | $68.00 | $25.00 | |
| 78 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 224 | $6.15 | $4.00 | $20.00 | |
| 79 | Pedestrian pole assembly (687-7001) | EACH | 27 | $2,556.00 | $3,286.00 | $5,650.00 | |
| 80 | Install circuit breaker (690-7304) | EACH | 10 | $800.81 | $300.00 | $320.00 | |
| 81 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 4 | $1,821.87 | $5,000.00 | $1,200.00 | |
| 82 | ITS pole (50 FT) (90 MPH) (6011-7005) | EACH | 1 | $22,069 | $42,713 | $23,200 | |
| 83 | Ground box (prepare) (6013-7006) | EACH | 60 | $750.00 | $261.59 | $265.00 | $990.00 |
| 84 | Fiber optic CBL (single-mode)(6 fiber) (6027-7011) | LF | 27,242 | $1.94 | $3.50 | $6.85 | |
| 85 | Fiber optic patch panel (6 position) (6027-7012) | EACH | 26 | $1,200.70 | $2,510.00 | $1,570.00 | |
| 86 | Wireless WWD system (6028-7001) | EACH | 15 | $71,903 | $51,000 | $56,000 | |
| 87 | WWD LED sign (6028-7002) | EACH | 30 | $2,256.01 | $3,420.00 | $4,040.00 | |
| 88 | WWD solar power system (6028-7004) | EACH | 17 | $2,355.09 | $1,602.00 | $6,500.00 | |
| 89 | Ethernet switch (install only) (6036-7001) | EACH | 21 | $176.42 | $4,472.00 | $3,105.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 4, 2025. Compiled by Mirage Metrics.