TxDOT contract A00196924 bid tabulation
Resurface Roadway, US 69 (US 69 to Red River Bridge). Let by Texas DOT on January 7, 2025, Grayson, Paris District. 4 bids received; low bid $14,667,932 by RK Hall, LLC, -8.0% against the engineer's estimate of $15,941,259.
- Owner
- Texas DOT
- Letting
- 07 JAN 2025
- Pay items
- 75
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | RK Hall, LLC | $14,667,932 | Low | -8.0% |
| 2 | Overland Corporation | $15,344,505 | +5.0% | -4.0% |
| 3 | Jagoe-Public Company | $17,739,252 | +21% | +11% |
| 4 | FNH Construction, LLC | $19,883,911 | +36% | +25% |
Engineer's estimate: $15,941,259.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. RK Hall, LLC | 2. Overland Corporation | 3. Jagoe-Public Company | 4. FNH Construction, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 267 | $2,000.00 | $750.00 | $175.00 | $250.00 | $5,000.00 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 2,000 | $40.00 | $38.00 | $50.00 | $20.00 | |
| 3 | Removing concrete (mowstrip) (104-7005) | LF | 3,000 | $8.00 | $19.00 | $7.00 | $10.00 | $20.00 |
| 4 | Remove (3") TRT/untrt base & asphalt pavement (105-7023) | SY | 2,000 | $27.00 | $9.00 | $10.00 | $20.00 | |
| 5 | Embankment (vehicle)(OC)(type B) (132-7015) | CY | 66 | $42.00 | $75.00 | $100.00 | $110.00 | $100.00 |
| 6 | Backfill (type A) (134-7001) | STA | 656 | $325.00 | $475.00 | $1,200.00 | $650.00 | $250.00 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 89,120 | $0.32 | $0.13 | $0.12 | $0.10 | $0.30 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 89,120 | $0.32 | $0.13 | $0.12 | $0.10 | $0.30 |
| 9 | Straw/hay mulch seed (permanent_urban_clay) (164-7028) | SY | 178,239 | $0.47 | $0.43 | $0.40 | $0.40 | $0.50 |
| 10 | Vegetative watering (168-7001) | TGL | 1,059 | $45.00 | $65.04 | $55.00 | $100.00 | $30.00 |
| 11 | D-GR HMA type-B sac-B PG64-22 (341-7002) | TON | 44,078 | $115.00 | $117.10 | $114.00 | $120.00 | $150.00 |
| 12 | SP mixes SP-C sac-A PG64-22 (344-7010) | TON | 42,648 | $123.00 | $122.00 | $119.00 | $145.00 | $165.00 |
| 13 | Tack coat (344-7077) | GAL | 25,250 | $4.80 | $5.48 | $3.00 | $1.00 | $5.00 |
| 14 | Flexible pavement structure repair(12") (351-7011) | SY | 450 | $140.00 | $166.32 | $300.00 | $200.00 | $120.00 |
| 15 | Planing asphalt concrete pavement(0" to 6") (354-7035) | SY | 7,335 | $15.00 | $9.32 | $7.00 | $8.00 | $10.00 |
| 16 | Plane concrete pavement(0" to 2") (354-7066) | SY | 8,861 | $10.00 | $6.91 | $4.50 | $5.00 | $10.00 |
| 17 | Full-depth repair CRCP (var depth) (361-7044) | CY | 275 | $1,225.00 | $1,890.00 | $1,800.00 | $2,000.00 | $1,650.00 |
| 18 | Full-depth repair CPCD (var depth) (361-7045) | CY | 100 | $1,880.28 | $1,800.00 | $2,000.00 | $2,000.00 | |
| 19 | Drilled shaft (non - reinforced) (12 in) (416-7024) | LF | 70 | $185.00 | $140.40 | $200.00 | $150.00 | $200.00 |
| 20 | Riprap (mow strip)(4 in) (432-7013) | CY | 303 | $725.00 | $783.00 | $600.00 | $775.00 | $500.00 |
| 21 | Mobilization (500-7001) | LS | 1 | $1,449,205 | $300,000 | $1,340,000 | $1,965,000 | $1,900,000 |
| 22 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $10,000 | $33,750 | $5,000.00 | $77,500 | $8,500.00 |
| 23 | Portable changeable message sign (503-7002) | EACH | 6 | $12,000 | $9,629.57 | $6,500.00 | $13,000 | $16,500 |
| 24 | TMA (stationary) (505-7001) | DAY | 128 | $260.00 | $568.29 | $300.00 | $500.00 | $250.00 |
| 25 | TMA (mobile operation) (505-7003) | DAY | 128 | $350.00 | $1,078.81 | $925.00 | $500.00 | $550.00 |
| 26 | Temporary sediment control fence (install) (506-7039) | LF | 450 | $5.00 | $4.32 | $4.00 | $4.00 | $4.00 |
| 27 | Temporary sediment control fence (remove) (506-7041) | LF | 450 | $1.75 | $1.08 | $1.00 | $2.50 | $2.00 |
| 28 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 100 | $7.50 | $5.40 | $5.00 | $12.00 | $18.00 |
| 29 | Biodegradable erosion control logs (remove) (506-7046) | LF | 100 | $5.00 | $1.08 | $1.00 | $6.00 | $8.00 |
| 30 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 100,022 | $0.58 | $0.13 | $0.11 | $0.20 | $0.20 |
| 31 | Metal W-beam guard fence (steel post) (540-7002) | LF | 3,525 | $29.00 | $28.08 | $31.00 | $30.00 | $30.00 |
| 32 | Metal thrie-beam guard fence (steel post) (540-7004) | LF | 24 | $2,300.00 | $2,257.20 | $3,000.00 | $2,700.00 | $1,000.00 |
| 33 | Downstream anchor terminal section (540-7015) | EACH | 12 | $1,860.00 | $1,404.00 | $1,400.00 | $1,700.00 | $1,850.00 |
| 34 | Metal beam guard fence trans (anchor plate) (540-7029) | EACH | 24 | $750.00 | $1,188.00 | $850.00 | $1,400.00 | $850.00 |
| 35 | Remove metal beam guard fence (542-7001) | LF | 3,000 | $3.00 | $3.24 | $2.00 | $3.50 | $3.00 |
| 36 | Remove terminal anchor section (542-7002) | EACH | 8 | $324.00 | $200.00 | $350.00 | $500.00 | |
| 37 | Guardrail end treatment (install) (544-7001) | EACH | 12 | $3,120.00 | $3,267.00 | $3,200.00 | $3,500.00 | $3,250.00 |
| 38 | Guardrail end treatment (remove) (544-7003) | EACH | 12 | $270.00 | $324.00 | $200.00 | $410.00 | $1,500.00 |
| 39 | Aluminum signs (type G) (636-7002) | SF | 37.50 | $32.40 | $35.00 | $38.00 | $50.00 | |
| 40 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 72 | $680.00 | $529.20 | $685.00 | $725.00 | $1,100.00 |
| 41 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 9 | $750.00 | $637.20 | $850.00 | $850.00 | $1,100.00 |
| 42 | Install LRSS (struct steel) (647-7001) | LB | 202 | $7.56 | $8.00 | $28.00 | $30.00 | |
| 43 | Relocate lrsa (647-7002) | EACH | 9 | $3,500.00 | $1,620.00 | $6,000.00 | $4,300.00 | $5,000.00 |
| 44 | Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003) | EACH | 215 | $65.00 | $63.72 | $125.00 | $60.00 | $100.00 |
| 45 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 76 | $24.00 | $29.16 | $20.00 | $23.00 | $100.00 |
| 46 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 41 | $45.00 | $33.48 | $35.00 | $35.00 | $100.00 |
| 47 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 76 | $41.00 | $29.16 | $20.00 | $23.00 | $100.00 |
| 48 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 60 | $45.00 | $33.48 | $35.00 | $35.00 | $100.00 |
| 49 | Install delineator assembly (D-DW)SZ 1(WFLX)GND (658-7045) | EACH | 152 | $70.00 | $63.72 | $125.00 | $60.00 | $100.00 |
| 50 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 13,350 | $0.50 | $0.43 | $0.40 | $0.45 | $0.50 |
| 51 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 53,400 | $0.55 | $0.22 | $0.20 | $0.25 | $0.50 |
| 52 | Work zone pavement marking non-removing (W)12"(DOT) (662-7013) | LF | 176 | $10.00 | $2.70 | $0.25 | $3.00 | $12.00 |
| 53 | Work zone pavement marking non-removing (W)(entr gore) (662-7020) | EACH | 10 | $800.00 | $324.00 | $300.00 | $350.00 | $500.00 |
| 54 | Work zone pavement marking non-removing (W)(exit gore) (662-7021) | EACH | 11 | $800.00 | $324.00 | $300.00 | $350.00 | $500.00 |
| 55 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 53,400 | $0.52 | $0.22 | $0.20 | $0.25 | $0.50 |
| 56 | Work zone pavement marking removing (W)6"(DOT) (662-7066) | LF | 2,690 | $1.00 | $2.70 | $2.50 | $3.00 | $2.00 |
| 57 | Work zone pavement marking removing (W)12"(solid) (662-7075) | LF | 1,200 | $3.50 | $4.32 | $4.00 | $4.75 | $2.00 |
| 58 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 16,304 | $1.15 | $2.64 | $1.50 | $3.00 | $3.00 |
| 59 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 5,803 | $1.15 | $2.64 | $1.50 | $3.00 | $3.00 |
| 60 | Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008) | LF | 2,690 | $1.08 | $2.16 | $2.00 | $2.25 | $3.00 |
| 61 | Reflectorized pavement marking type I (W)12"(solid)(090MIL) (666-7029) | LF | 1,200 | $3.75 | $4.32 | $4.00 | $4.75 | $6.00 |
| 62 | Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041) | EACH | 2 | $250.00 | $216.00 | $200.00 | $230.00 | $250.00 |
| 63 | Reflectorized pavement marking type I (W)(number)(090MIL) (666-7062) | EACH | 10 | $155.00 | $270.00 | $250.00 | $290.00 | $250.00 |
| 64 | Reflectorized pavement marking type I (W)(word)(090MIL) (666-7065) | EACH | 2 | $250.00 | $216.00 | $200.00 | $230.00 | $250.00 |
| 65 | Reflectorized pavement marking type I(W)(entr gore)(090MIL) (666-7068) | EACH | 10 | $895.00 | $594.00 | $550.00 | $625.00 | $500.00 |
| 66 | Reflectorized pavement marking type I(W)(exit gore)(090MIL) (666-7071) | EACH | 11 | $800.00 | $972.00 | $900.00 | $1,000.00 | $500.00 |
| 67 | Pavement sler 6" (666-7347) | LF | 7,136 | $0.35 | $0.54 | $0.50 | $0.60 | $0.75 |
| 68 | Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407) | LF | 13,350 | $0.60 | $0.76 | $0.70 | $0.80 | $0.75 |
| 69 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 67,829 | $0.75 | $0.67 | $0.62 | $0.70 | $0.75 |
| 70 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 62,097 | $0.78 | $0.67 | $0.62 | $0.70 | $0.78 |
| 71 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 1,773 | $5.00 | $6.48 | $6.00 | $7.00 | $6.00 |
| 72 | Eliminating existing PM & markers (6") (677-7002) | LF | 7,136 | $0.80 | $0.54 | $0.50 | $0.60 | $2.00 |
| 73 | Pavement surface preparation for marking (6") (678-7002) | LF | 7,136 | $0.34 | $0.22 | $0.20 | $0.25 | $2.00 |
| 74 | Composite geogrid for asphalt overlay (3019-7001) | SY | 156,275 | $6.50 | $3.52 | $3.95 | $3.60 | $1.25 |
| 75 | Tack coat (3019-7002) | GAL | 21,881 | $5.30 | $5.56 | $5.00 | $6.00 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2025. Compiled by Mirage Metrics.