| 1 | Preparing row (100-7002) | STA | 207 | $1,250.00 | $2,100.00 | $1,310.00 | $750.00 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 2,650 | $15.00 | $15.00 | $11.50 | $9.25 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 1,163 | $22.00 | $24.50 | $27.30 | $21.57 |
| 4 | Subgr widen (OC) (112-7001) | STA | 207 | $390.00 | $700.00 | $332.00 | $750.00 |
| 5 | Backfill (type A or B) (134-7004) | STA | 207 | $400.00 | $255.00 | $201.00 | $230.00 |
| 6 | Blading (150-7003) | LF | 600 | $1.45 | $1.48 | $7.50 | $5.00 |
| 7 | Spec excavation work (hyd excavator) (158-7002) | HR | 160 | $220.00 | $136.50 | $810.00 | $135.00 |
| 8 | Broadcast seed (temporary_warm) (164-7005) | SY | 26,914 | $1.25 | $0.35 | $0.15 | $1.20 |
| 9 | Broadcast seed (temporary_cool) (164-7006) | SY | 26,914 | $1.50 | $0.35 | $0.15 | $1.20 |
| 10 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 53,827 | $1.50 | $0.50 | $0.50 | $0.70 |
| 11 | Vegetative watering (168-7001) | TGL | 226 | $325.00 | $30.00 | $23.00 | $60.00 |
| 12 | Asphalt (AC-20-5TR) (316-7007) | GAL | 3,292 | $7.00 | $4.25 | $4.50 | $5.00 |
| 13 | Aggregate (type-PB or PL, GR-4)(sac-B) (316-7245) | CY | 70 | $195.00 | $195.00 | $390.00 | $446.00 |
| 14 | D-GR HMA type-B PG64-22 (exempt) (341-7003) | TON | 9,796 | $140.00 | $137.98 | $145.00 | $192.00 |
| 15 | Tack coat (341-7082) | GAL | 2,312 | $8.00 | $5.03 | $4.10 | $5.00 |
| 16 | SP mixes SP-C sac-A PG76-22 (344-7030) | TON | 7,138 | $190.00 | $160.00 | $175.00 | $228.00 |
| 17 | Tack coat (344-7077) | GAL | 6,489 | $7.00 | $4.48 | $4.10 | $5.00 |
| 18 | Flexible pavement structure repair(8") (351-7007) | SY | 250 | $110.00 | $80.31 | $120.00 | $100.00 |
| 19 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 622 | $2.50 | $3.90 | $17.00 | $5.00 |
| 20 | Cem stabil BKFL (400-7010) | CY | 36 | $150.00 | $300.00 | $275.00 | $105.00 |
| 21 | Temporary special shoring (403-7001) | SF | 980 | $15.00 | $40.00 | $110.00 | $80.00 |
| 22 | Class A concrete (collar) (420-7008) | EACH | 52 | $1,000.00 | $1,053.06 | $1,650.00 | $1,845.00 |
| 23 | CL E concrete (seal slab) (420-7069) | CY | 4 | $6.00 | $500.00 | $935.00 | $800.00 |
| 24 | Riprap (concrete)(5 in) (432-7002) | CY | 12 | $650.00 | $702.56 | $1,100.00 | $743.00 |
| 25 | Riprap (mow strip)(4 in) (432-7013) | CY | 84 | $760.00 | $650.00 | $1,250.00 | $785.00 |
| 26 | Concrete box culvert (5 FT X 3 FT)(extend) (462-7062) | LF | 8 | $750.00 | $818.90 | $1.00 | $1,138.00 |
| 27 | Concrete box culvert (6 FT X 5 FT)(extend) (462-7068) | LF | 24 | $7,000.00 | $1,300.00 | $1,595.00 | $1,205.00 |
| 28 | RC pipe (CL III)(15 in) (464-7002) | LF | 4 | $125.00 | $77.50 | $72.00 | $80.00 |
| 29 | RC pipe (CL III)(18 in) (464-7003) | LF | 549 | $135.00 | $90.70 | $90.00 | $86.10 |
| 30 | RC pipe (CL III)(24 in) (464-7005) | LF | 38 | $150.00 | $110.00 | $180.00 | $203.00 |
| 31 | Inlet(complete)(PSL)(SFG)(3FTX3FT-3FTX3FT) (465-7146) | EACH | 1 | $7,000.00 | $6,985.00 | $6,000.00 | $6,765.00 |
| 32 | Wingwall (PW - 1) (HW=8 FT) (466-7178) | EACH | 2 | $30,000 | $42,085 | $44,000 | $49,200 |
| 33 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 1 | $1,415.00 | $1,155.00 | $990.00 | $1,107.00 |
| 34 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 62 | $1,525.00 | $1,275.00 | $1,100.00 | $1,230.00 |
| 35 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 2 | $1,600.00 | $1,775.00 | $2,200.00 | $2,460.00 |
| 36 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 3 | $2,000.00 | $1,775.00 | $2,750.00 | $3,075.00 |
| 37 | Removing structure (set) (496-7004) | EACH | 70 | $720.00 | $460.00 | $950.00 | $1,046.00 |
| 38 | Removing structure (wingwall) (496-7005) | EACH | 2 | $2,250.00 | $1,876.80 | $2,750.00 | $3,075.00 |
| 39 | Removing structure (pipe) (496-7007) | LF | 252 | $40.00 | $24.19 | $66.00 | $74.00 |
| 40 | Removing structure (small) (496-7036) | EACH | 33 | $3,900.00 | $1,200.00 | $1,300.00 | $1,476.00 |
| 41 | Mobilization (500-7001) | LS | 1 | $550,000 | $253,042 | $270,000 | $550,000 |
| 42 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $7,000.00 | $5,000.00 | $2,807.00 | $5,000.00 |
| 43 | Portable changeable message sign (503-7001) | DAY | 28 | $91.00 | $88.00 | $71.50 | $100.00 |
| 44 | TMA (stationary) (505-7001) | DAY | 100 | $325.00 | $205.00 | $250.00 | $300.00 |
| 45 | TMA (mobile operation) (505-7003) | DAY | 5 | $230.00 | $205.00 | $275.00 | $300.00 |
| 46 | Rock filter dams (install) (type 2) (506-7002) | LF | 600 | $50.00 | $42.00 | $52.00 | $50.00 |
| 47 | Rock filter dams (remove) (506-7011) | LF | 600 | $19.00 | $10.45 | $11.00 | $20.00 |
| 48 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 840 | $7.50 | $5.50 | $7.25 | $10.00 |
| 49 | Biodegradable erosion control logs (remove) (506-7046) | LF | 840 | $5.00 | $2.75 | $2.20 | $5.00 |
| 50 | Driveways (concrete) (530-7006) | SY | 1,127 | $112.00 | $110.00 | $180.00 | $118.00 |
| 51 | Driveways (ACP) (530-7010) | SY | 1,165 | $80.00 | $55.00 | $87.00 | $97.00 |
| 52 | Driveways (base) (530-7015) | SY | 4,574 | $60.00 | $36.00 | $56.00 | $54.34 |
| 53 | Turnouts (ACP) (530-7018) | SY | 1,223 | $88.00 | $64.50 | $201.00 | $109.22 |
| 54 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 7,290 | $1.75 | $8.50 | $1.50 | $1.81 |
| 55 | Metal W-beam guard fence (timber post) (540-7001) | LF | 900 | $27.50 | $28.65 | $30.00 | $29.69 |
| 56 | Metal beam guard fence (long span system) (540-7027) | EACH | 3 | $380.00 | $681.06 | $1,100.00 | $1,728.00 |
| 57 | Remove metal beam guard fence (542-7001) | LF | 1,238 | $3.50 | $3.00 | $3.50 | $2.46 |
| 58 | Guardrail end treatment (install) (544-7001) | EACH | 7 | $3,250.00 | $3,200.00 | $3,100.00 | $3,592.00 |
| 59 | Guardrail end treatment (remove) (544-7003) | EACH | 7 | $375.00 | $286.68 | $400.00 | $400.00 |
| 60 | Crash cushion attenuator (remove) (545-7004) | EACH | 1 | $1,400.00 | $1,000.00 | $1,000.00 | $3,505.00 |
| 61 | Crash cushion attenuator (install)(R)(N)(TL3) (545-7010) | EACH | 1 | $31,000 | $27,404 | $30,000 | $35,117 |
| 62 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 84 | $250.00 | $300.00 | $300.00 | $381.30 |
| 63 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 16 | $250.00 | $300.00 | $320.00 | $430.50 |
| 64 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 10 | $750.00 | $625.00 | $705.00 | $1,070.00 |
| 65 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 67 | $750.00 | $720.00 | $575.00 | $781.00 |
| 66 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 11 | $850.00 | $850.00 | $730.00 | $929.00 |
| 67 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,050.00 | $1,100.00 | $1,100.00 | $1,359.00 |
| 68 | Remove SM RD SN sup&AM (644-7073) | EACH | 78 | $160.00 | $110.00 | $105.00 | $111.00 |
| 69 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 18 | $25.00 | $31.00 | $36.00 | $35.00 |
| 70 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 52 | $140.00 | $75.00 | $82.50 | $80.00 |
| 71 | Remove delin & object marker assms (658-7078) | EACH | 34 | $25.00 | $18.99 | $27.50 | $22.00 |
| 72 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 3,060 | $1.55 | $1.50 | $0.85 | $3.00 |
| 73 | Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265) | LF | 71,461 | $1.28 | $1.06 | $1.20 | $1.29 |
| 74 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 4,630 | $1.70 | $0.73 | $0.75 | $0.86 |
| 75 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 42,930 | $1.70 | $0.78 | $0.75 | $0.80 |
| 76 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 300 | $19.00 | $18.00 | $20.00 | $21.53 |
| 77 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 8 | $80.00 | $84.00 | $50.00 | $55.35 |
| 78 | Reflectorized pavement marker type I-C (672-7002) | EACH | 16 | $7.00 | $7.00 | $6.00 | $6.15 |
| 79 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 553 | $7.25 | $7.00 | $6.00 | $6.15 |
| 80 | Full - width mowing (730-7019) | CYC | 2 | $2,200.00 | $2,600.00 | $3,000.00 | $5,500.00 |
| 81 | Litter removal (734-7002) | CYC | 8 | $2,000.00 | $1,716.00 | $1,020.00 | $4,000.00 |