TxDOT contract A00206947 bid tabulation
Install Illumination, US 77 (@ SH 320 to @ SH 320). Let by Texas DOT on February 4, 2026, Falls, Waco District. 4 bids received; low bid $773,917 by E-Z Bel Construction, LLC, +6.4% against the engineer's estimate of $727,175.
- Owner
- Texas DOT
- Letting
- 04 FEB 2026
- Pay items
- 65
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | E-Z Bel Construction, LLC | $773,917 | Low | +6.0% |
| 2 | Florida Traffic Control Devices, Inc. | $832,000 | +8.0% | +14% |
| 3 | Austin Traffic Signal Construction Co., Inc. | $852,690 | +10% | +17% |
| 4 | Select Maintenance, L.L.C. | $937,758 | +21% | +29% |
Engineer's estimate: $727,175.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. E-Z Bel Construction, LLC | 2. Florida Traffic Control Devices, Inc. | 3. Austin Traffic Signal Construction Co., Inc. | 4. Select Maintenance, L.L.C. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (miscellaneous) (104-7046) | SY | 57 | $33.00 | $27.00 | $415.00 | $140.00 | $85.00 |
| 2 | Remove (8"-12") TRT/untrt base & asphalt pavement (105-7008) | SY | 131 | $20.00 | $16.00 | $310.00 | $69.00 | $15.00 |
| 3 | Spec excavation work (backhoe) (158-7001) | HR | 8 | $300.00 | $172.00 | $1,175.00 | $285.00 | $120.00 |
| 4 | D-GR HMA type-B PG64-22 (exempt) (341-7003) | TON | 28 | $200.00 | $350.00 | $108.00 | $1,300.00 | $500.00 |
| 5 | Flexible pavement structure repair(10") (351-7009) | SY | 98 | $100.00 | $23.00 | $86.00 | $528.00 | $275.00 |
| 6 | Cut & restore asphalt paving (400-7008) | SY | 11 | $300.00 | $352.00 | $185.00 | $455.00 | $275.00 |
| 7 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 104 | $350.00 | $350.00 | $569.00 | $250.00 | $400.00 |
| 8 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 56 | $500.00 | $370.00 | $610.00 | $300.00 | $500.00 |
| 9 | Riprap (concrete)(4 in) (432-7001) | CY | 35 | $800.00 | $920.00 | $1,255.00 | $800.00 | $1,150.00 |
| 10 | Mobilization (500-7001) | LS | 1 | $52,531 | $79,000 | $83,000 | $75,000 | $90,000 |
| 11 | Barricades, signs and traffic handling (502-7001) | MO | 3 | $6,000.00 | $7,000.00 | $950.00 | $6,000.00 | $12,750 |
| 12 | Portable changeable message sign (503-7002) | EACH | 4 | $5,000.00 | $2,000.00 | $180.00 | $1,600.00 | $15,000 |
| 13 | TMA (stationary) (505-7001) | DAY | 69 | $300.00 | $270.00 | $180.00 | $282.00 | $225.00 |
| 14 | TMA (mobile operation) (505-7003) | DAY | 2 | $60.00 | $1.00 | $180.00 | $500.00 | $225.00 |
| 15 | Rock filter dams (install) (type 2) (506-7002) | LF | 8 | $100.00 | $26.00 | $61.70 | $155.00 | $65.00 |
| 16 | Rock filter dams (remove) (506-7011) | LF | 8 | $20.00 | $9.00 | $16.00 | $63.00 | $25.00 |
| 17 | Temporary sediment control fence (install) (506-7039) | LF | 126 | $5.00 | $4.00 | $22.20 | $5.00 | $5.00 |
| 18 | Temporary sediment control fence (remove) (506-7041) | LF | 126 | $1.00 | $2.00 | $2.50 | $1.00 | $1.00 |
| 19 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 72 | $5.00 | $6.00 | $19.75 | $15.00 | $5.00 |
| 20 | Biodegradable erosion control logs (remove) (506-7046) | LF | 72 | $2.00 | $2.00 | $2.50 | $3.00 | $1.00 |
| 21 | Concrete curb & gutter (type II) (529-7009) | LF | 169 | $65.00 | $60.00 | $100.00 | $60.00 | $65.00 |
| 22 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 13 | $6,500.00 | $5,600.00 | $5,295.00 | $5,000.00 | $7,850.00 |
| 23 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 2,180 | $22.00 | $14.00 | $17.60 | $13.00 | $25.00 |
| 24 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 2,869 | $30.00 | $35.00 | $26.00 | $46.00 | $27.00 |
| 25 | Electrical conductor (no.10) bare (620-7005) | LF | 4,954 | $1.50 | $2.00 | $1.65 | $0.90 | $2.00 |
| 26 | Electrical conductor (no.10) insulated (620-7006) | LF | 8,390 | $1.80 | $2.00 | $1.95 | $1.00 | $2.70 |
| 27 | Electrical conductor (no.8) bare (620-7007) | LF | 115 | $2.00 | $2.00 | $1.90 | $1.40 | $2.00 |
| 28 | Electrical conductor (no.8) insulated (620-7008) | LF | 230 | $2.20 | $2.00 | $2.40 | $1.50 | $2.50 |
| 29 | Ground box type D (162922)W/apron (624-7008) | EACH | 14 | $1,800.00 | $1,750.00 | $1,783.00 | $1,900.00 | $2,500.00 |
| 30 | Elc SRV type D 120/240 060(NS)SS(E)PS(U) (628-7147) | EACH | 1 | $7,250.00 | $12,600 | $9,096.60 | $8,500.00 | $25,000 |
| 31 | Aluminum signs (type A) (636-7001) | SF | 44 | $35.00 | $57.00 | $30.00 | $42.00 | $50.00 |
| 32 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 9 | $900.00 | $1,200.00 | $1,370.00 | $2,000.00 | $650.00 |
| 33 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 2 | $1,200.00 | $1,400.00 | $1,750.00 | $2,000.00 | $925.00 |
| 34 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 35 | $700.00 | $800.00 | $975.00 | $2,000.00 | $450.00 |
| 35 | Install small roadside sign support and assembly tytwt(1)WS(T) (644-7058) | EACH | 1 | $750.00 | $1,000.00 | $1,150.00 | $2,000.00 | $480.00 |
| 36 | Remove SM RD SN sup&AM (644-7073) | EACH | 50 | $110.00 | $175.00 | $222.00 | $100.00 | $100.00 |
| 37 | Relocate SM RD SN sup & AM type temporary (644-7077) | EACH | 2 | $500.00 | $1,500.00 | $961.00 | $900.00 | $850.00 |
| 38 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 146 | $7.00 | $25.00 | $54.00 | $35.00 | $20.00 |
| 39 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 2 | $250.00 | $650.00 | $555.00 | $445.00 | $400.00 |
| 40 | Eliminating existing PM & markers (6") (677-7002) | LF | 166 | $0.40 | $3.00 | $12.35 | $2.50 | $1.00 |
| 41 | Eliminating existing PM & markers (8") (677-7004) | LF | 326 | $0.75 | $4.00 | $12.35 | $5.00 | $3.00 |
| 42 | Eliminating existing PM & markers (24") (677-7008) | LF | 28 | $3.20 | $10.00 | $24.70 | $6.00 | $6.00 |
| 43 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 2 | $55.00 | $150.00 | $246.00 | $100.00 | $175.00 |
| 44 | Eliminating existing PM & markers (36")(yld tri) (677-7024) | EACH | 14 | $12.00 | $25.00 | $49.00 | $25.00 | $100.00 |
| 45 | Pavement surface preparation for marking (24") (678-7008) | LF | 146 | $1.20 | $15.00 | $6.15 | $2.00 | $1.00 |
| 46 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 2 | $25.00 | $100.00 | $31.00 | $14.00 | $100.00 |
| 47 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $25,000 | $13,000 | $14,125 | $5,000.00 | $39,500 |
| 48 | Removing traffic signals (680-7004) | EACH | 1 | $4,000.00 | $4,000.00 | $4,450.00 | $3,000.00 | $7,000.00 |
| 49 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 8 | $350.00 | $410.00 | $350.00 | $300.00 | $350.00 |
| 50 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 2 | $350.00 | $410.00 | $350.00 | $300.00 | $350.00 |
| 51 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 8 | $350.00 | $440.00 | $350.00 | $300.00 | $350.00 |
| 52 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 4 | $350.00 | $410.00 | $350.00 | $300.00 | $350.00 |
| 53 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 8 | $350.00 | $410.00 | $350.00 | $300.00 | $350.00 |
| 54 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 2 | $350.00 | $440.00 | $350.00 | $300.00 | $350.00 |
| 55 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 8 | $350.00 | $200.00 | $325.00 | $140.00 | $350.00 |
| 56 | Backplate W/reflectorized border(4 sec)aluminum (682-7040) | EACH | 2 | $350.00 | $250.00 | $335.00 | $200.00 | $350.00 |
| 57 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 384 | $4.70 | $6.00 | $5.20 | $4.00 | $5.00 |
| 58 | Traffic signal CBL (type A)(12 AWG)(16 conductor) (684-7021) | LF | 632 | $6.50 | $10.00 | $9.50 | $6.00 | $9.00 |
| 59 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 1 | $17,000 | $20,000 | $16,030 | $18,000 | $16,750 |
| 60 | Ins traffic signal PL AM(S)1 arm(48') (686-7049) | EACH | 1 | $18,000 | $19,000 | $15,920 | $17,000 | $16,750 |
| 61 | Ins traffic signal PL AM(S)1 arm(48')lum (686-7051) | EACH | 2 | $20,000 | $23,000 | $18,040 | $22,000 | $18,750 |
| 62 | Removal of concrete foundations (690-7063) | EACH | 1 | $1,700.00 | $785.00 | $1,235.00 | $1,500.00 | $2,500.00 |
| 63 | Bbu system (external battery cabinet) (6007-7001) | EACH | 1 | $10,000 | $10,500 | $7,535.00 | $8,000.00 | $15,000 |
| 64 | RVDS (presence and advance detection) (6008-7003) | EACH | 4 | $6,000.00 | $13,000 | $9,672.00 | $8,500.00 | $8,000.00 |
| 65 | Dead end roadway barricade (6012-7001) | LF | 16 | $240.00 | $44.00 | $310.00 | $200.00 | $150.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 4, 2026. Compiled by Mirage Metrics.