TxDOT contract A00208090 bid tabulation
Bridge Maintenance, US 85 (0.246 MI E OF SPUR 1966 to COLDWELL STREET). Let by Texas DOT on May 1, 2025, El Paso, El Paso District. 5 bids received; low bid $967,190 by Structural Integrity Group LLC, -31% against the engineer's estimate of $1,411,458.
- Owner
- Texas DOT
- Letting
- 01 MAY 2025
- Pay items
- 27
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Structural Integrity Group LLC | $967,190 | Low | -31% |
| 2 | Dan Williams Company | $1,181,240 | +22% | -16% |
| 3 | Gibson & Associates, Inc. | $1,200,397 | +24% | -15% |
| 4 | International Eagle Enterprises, Inc. | $1,652,094 | +71% | +17% |
| 5 | Synergy Project Contractors, Inc. | $1,770,499 | +83% | +25% |
Engineer's estimate: $1,411,458.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Structural Integrity Group LLC | 2. Dan Williams Company | 3. Gibson & Associates, Inc. | 4. International Eagle Enterprises, Inc. | 5. Synergy Project Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (pile encasement) (104-7033) | CY | 27 | $2,500.00 | $315.00 | $600.00 | $100.00 | $2,000.00 | $62.00 |
| 2 | Planing asphalt concrete pavement(0" to 0.5" micro) (354-7044) | SY | 8,974 | $12.00 | $6.70 | $3.25 | $4.38 | $10.00 | $1.24 |
| 3 | Flowable backfill (401-7001) | CY | 10 | $250.00 | $730.00 | $550.00 | $400.00 | $800.00 | $372.00 |
| 4 | Class C concrete (pile encasement) (420-7060) | CY | 27 | $650.00 | $2,100.00 | $2,000.00 | $500.00 | $1,500.00 | $465.00 |
| 5 | Penetrating concrete surface treatment (428-7001) | SY | 1,895 | $13.00 | $35.00 | $16.00 | $27.50 | $30.00 | $55.80 |
| 6 | Concrete structure repair (epoxy mortar) (429-7002) | SF | 12 | $200.00 | $515.00 | $850.00 | $725.00 | $600.00 | $372.00 |
| 7 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 82 | $500.00 | $225.00 | $350.00 | $300.00 | $280.00 | $558.00 |
| 8 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 12 | $300.00 | $570.00 | $900.00 | $725.00 | $600.00 | $372.00 |
| 9 | Concrete structure repair (standard) (429-7009) | SF | 10 | $350.00 | $480.00 | $650.00 | $750.00 | $600.00 | $310.00 |
| 10 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 630 | $50.00 | $36.00 | $52.00 | $72.00 | $40.00 | $74.40 |
| 11 | Multi-layer polymer overlay (439-7014) | SY | 8,974 | $50.00 | $39.50 | $42.00 | $50.00 | $60.00 | $59.52 |
| 12 | Shot blasting (483-7016) | SY | 8,974 | $10.00 | $4.00 | $4.00 | $5.00 | $15.00 | $37.20 |
| 13 | Mobilization (500-7001) | LS | 1 | $128,314 | $77,000 | $115,000 | $228,500 | $150,000 | $186,000 |
| 14 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $30,000 | $11,000 | $30,000 | $26,000 | $18,000 | $7,812.00 |
| 15 | TMA (stationary) (505-7001) | DAY | 24 | $300.00 | $400.00 | $300.00 | $450.00 | $320.00 | $372.00 |
| 16 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 528 | $6.00 | $1.00 | $8.50 | $7.50 | $20.00 | $7.44 |
| 17 | Biodegradable erosion control logs (remove) (506-7046) | LF | 528 | $6.00 | $1.00 | $1.50 | $2.50 | $1.00 | $2.48 |
| 18 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 3,016 | $0.40 | $2.50 | $1.91 | $2.10 | $12.00 | $0.81 |
| 19 | All-wther PM type I (W)6"(broken)(100MIL) (666-7310) | LF | 3,016 | $0.40 | $2.60 | $1.99 | $2.19 | $12.00 | $1.24 |
| 20 | All-wther PM type I (Y)6"(solid)(100MIL) (666-7315) | LF | 3,016 | $0.40 | $2.50 | $1.91 | $2.10 | $12.00 | $1.24 |
| 21 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 75 | $10.00 | $11.50 | $8.50 | $9.35 | $25.00 | $7.44 |
| 22 | Drain inlet cleaning (764-7001) | EACH | 5 | $100.00 | $400.00 | $1,500.00 | $1,100.00 | $500.00 | $372.00 |
| 23 | CNC crack repair (discrete)(inject) (780-7002) | LF | 105 | $125.00 | $55.00 | $110.00 | $169.00 | $35.00 | $186.00 |
| 24 | Rep steel bridge member (beam) (784-7002) | EACH | 8 | $3,000.00 | $5,400.00 | $3,500.00 | $2,600.00 | $11,000 | $37,200 |
| 25 | Rep steel bridge member (piling) (784-7007) | EACH | 10 | $1,600.00 | $7,750.00 | $8,000.00 | $5,500.00 | $17,000 | $8,680.00 |
| 26 | Remove lead-containing coating (other) (5011-7002) | LS | 1 | $250,000 | $33,000 | $150,000 | $28,750 | $40,000 | $12,400 |
| 27 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 2 | $650.00 | $1,000.00 | $800.00 | $2,000.00 | $3,000.00 | $1,488.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 1, 2025. Compiled by Mirage Metrics.