TxDOT contract A00208822 bid tabulation
Surfacing/Roadway Restoration, FM 331 (FM 529 to 0.028 Mi E of SH 36). Let by Texas DOT on December 2, 2025, Austin, Yoakum District. 7 bids received; low bid $10,744,493 by Hunter Industries, LTD., +0.3% against the engineer's estimate of $10,709,547.
- Owner
- Texas DOT
- Letting
- 02 DEC 2025
- Pay items
- 50
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hunter Industries, LTD. | $10,744,493 | Low | 0.0% |
| 2 | Clark Construction of Texas, Inc. | $12,123,095 | +13% | +13% |
| 3 | Matagorda Construction & Materials | $12,296,187 | +14% | +15% |
| 4 | CK Newberry, LLC | $12,441,558 | +16% | +16% |
| 5 | MBN Enterprises LLC | $12,677,852 | +18% | +18% |
| 6 | Environmental Allies, Inc. | $14,403,929 | +34% | +34% |
| 7 | Forde Construction Company, Inc. | $14,822,558 | +38% | +38% |
Engineer's estimate: $10,709,547.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hunter Industries, LTD. | 2. Clark Construction of Texas, Inc. | 3. Matagorda Construction & Materials | 4. CK Newberry, LLC | 5. MBN Enterprises LLC | 6. Environmental Allies, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (driveways) (104-7011) | SY | 218 | $25.00 | $16.40 | $41.31 | $15.00 | $50.00 | $20.00 | $20.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 18,716 | $17.00 | $12.04 | $23.62 | $15.00 | $16.00 | $14.00 | $20.00 |
| 3 | Subgr widen (OC) (112-7001) | STA | 1,305.54 | $375.00 | $244.20 | $330.89 | $143.00 | $325.00 | $230.00 | $550.00 |
| 4 | Embankment (final)(OC)(type C) (132-7005) | CY | 5,259 | $25.00 | $13.12 | $18.78 | $15.00 | $25.00 | $22.00 | $40.00 |
| 5 | Blading (150-7002) | HR | 70 | $150.00 | $99.00 | $100.00 | $120.00 | $175.00 | $250.00 | $130.00 |
| 6 | Drill seed (permanent_rural_clay) (164-7010) | SY | 436,173 | $0.30 | $0.16 | $0.15 | $0.27 | $0.15 | $0.35 | $0.35 |
| 7 | Drill seed (temporary_warm) (164-7013) | SY | 109,044 | $0.20 | $0.16 | $0.15 | $0.17 | $0.15 | $0.35 | $0.23 |
| 8 | Drill seed (temporary_cool) (164-7014) | SY | 109,044 | $0.20 | $0.16 | $0.15 | $0.18 | $0.15 | $0.35 | $0.25 |
| 9 | Vegetative watering (168-7001) | TGL | 3,671.43 | $35.00 | $25.16 | $20.00 | $25.00 | $20.00 | $25.00 | $38.00 |
| 10 | FL BS (compacted in place)(tye GR1-2)(final pos) (247-7193) | CY | 20,732 | $65.00 | $89.93 | $85.22 | $120.00 | $105.00 | $100.00 | $105.00 |
| 11 | FL BS (roadway del)(type E GR 1-2)(final pos) (247-7275) | CY | 34,210 | $75.00 | $83.14 | $113.26 | $105.00 | $95.00 | $99.00 | $105.00 |
| 12 | Cement (275-7001) | TON | 3,741 | $165.00 | $205.20 | $215.00 | $200.00 | $215.00 | $175.00 | $225.00 |
| 13 | Cement TRT (existing material & new base)(8") (275-7007) | SY | 307,890 | $2.00 | $1.98 | $1.79 | $2.50 | $1.50 | $3.00 | $4.00 |
| 14 | Asphalt (RC-250) (316-7016) | GAL | 74,434 | $4.00 | $4.44 | $5.93 | $4.50 | $4.25 | $4.80 | $6.50 |
| 15 | Aggregate (type-E, GR-5)(sac-B) (316-7194) | CY | 2,659 | $145.00 | $90.09 | $124.62 | $100.00 | $175.00 | $100.00 | $195.00 |
| 16 | Aggregate (type-PE, GR-3)(sac-B) (316-7229) | CY | 4,464 | $130.00 | $139.92 | $106.44 | $120.00 | $155.00 | $100.00 | $195.00 |
| 17 | Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264) | GAL | 151,742 | $3.25 | $2.98 | $3.54 | $3.25 | $2.75 | $4.40 | $5.75 |
| 18 | Flexible pavement structure repair(12") (351-7011) | SY | 2,000 | $65.00 | $89.50 | $63.76 | $78.00 | $70.00 | $90.00 | $95.00 |
| 19 | Mobilization (500-7001) | LS | 1 | $1,115,000 | $822,915 | $634,500 | $320,000 | $1,250,000 | $1,100,000 | $245,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 33 | $6,500.00 | $4,183.57 | $4,499.70 | $15,000 | $10,000 | $5,000.00 | $4,500.00 |
| 21 | Portable changeable message sign (503-7002) | EACH | 8 | $10,000 | $4,059.37 | $7,500.00 | $10,000 | $5,000.00 | $8,000.00 | $15,250 |
| 22 | TMA (stationary) (505-7001) | DAY | 70 | $250.00 | $162.37 | $115.00 | $400.00 | $250.00 | $200.00 | $295.00 |
| 23 | TMA (mobile operation) (505-7003) | DAY | 70 | $450.00 | $216.50 | $225.00 | $550.00 | $275.00 | $300.00 | $295.00 |
| 24 | Rock filter dams (install) (type 1) (506-7001) | LF | 400 | $40.00 | $9.62 | $49.16 | $30.00 | $50.00 | $45.00 | $35.00 |
| 25 | Rock filter dams (remove) (506-7011) | LF | 400 | $4.00 | $18.71 | $17.82 | $10.00 | $18.00 | $10.00 | $10.00 |
| 26 | Sandbags for erosion control (506-7035) | EACH | 400 | $17.00 | $10.69 | $10.18 | $10.00 | $10.00 | $15.00 | $8.00 |
| 27 | Temporary sediment control fence (install) (506-7039) | LF | 400 | $5.00 | $15.16 | $14.44 | $4.00 | $15.00 | $7.00 | $3.50 |
| 28 | Temporary sediment control fence (remove) (506-7041) | LF | 400 | $4.00 | $2.81 | $2.68 | $1.00 | $3.00 | $2.00 | $1.50 |
| 29 | Driveways (concrete) (530-7006) | SY | 218 | $135.00 | $150.21 | $186.00 | $165.00 | $175.00 | $120.00 | $100.00 |
| 30 | Driveways (surface treat) (530-7016) | SY | 12,103 | $25.00 | $39.24 | $28.62 | $45.00 | $30.00 | $28.00 | $33.00 |
| 31 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 9 | $550.00 | $470.00 | $475.00 | $550.00 | $475.00 | $600.00 | $550.00 |
| 32 | Mailbox install-S (WC-post) type 3 (560-7004) | EACH | 95 | $125.00 | $225.00 | $200.00 | $250.00 | $200.00 | $400.00 | $260.00 |
| 33 | Mailbox install-D (WC-post) type 3 (560-7005) | EACH | 7 | $145.00 | $285.00 | $215.00 | $315.00 | $215.00 | $400.00 | $350.00 |
| 34 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 12 | $21.00 | $25.00 | $38.00 | $25.00 | $30.00 | $25.00 | |
| 35 | Inst delineator assembly (D-SW)SZ 1(WFLX)GNDHH(BI) (658-7108) | EACH | 33 | $55.00 | $125.00 | $185.00 | $138.00 | $185.00 | $30.00 | $175.00 |
| 36 | Install object marker assembly (OM-2Z)(yflx)GNDHH(BI) (658-7255) | EACH | 78 | $20.00 | $125.00 | $185.00 | $138.00 | $185.00 | $500.00 | $220.00 |
| 37 | Install object marker assembly (OM-2Z)(yflx)SRFHH(BI) (658-7263) | EACH | 6 | $20.00 | $125.00 | $205.00 | $138.00 | $205.00 | $500.00 | $200.00 |
| 38 | Install object marker assembly (OM-3L)(WFLX)GNDHH (658-7269) | EACH | 4 | $165.00 | $425.00 | $500.00 | $425.00 | $500.00 | $200.00 | |
| 39 | Install object marker assembly (OM-3R)(WFLX)GNDHH (658-7277) | EACH | 4 | $165.00 | $425.00 | $500.00 | $425.00 | $500.00 | $200.00 | |
| 40 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 530,748 | $0.25 | $0.19 | $0.45 | $0.20 | $0.35 | $0.53 | $0.65 |
| 41 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 59,404 | $0.30 | $0.21 | $0.45 | $0.22 | $0.30 | $0.53 | $0.70 |
| 42 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 105,162 | $0.35 | $0.21 | $0.45 | $0.22 | $0.30 | $0.55 | $0.65 |
| 43 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 23,082 | $1.50 | $1.53 | $1.75 | $1.00 | $0.55 | $2.50 | $1.00 |
| 44 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 52,581 | $0.75 | $0.73 | $0.95 | $0.75 | $0.95 | $1.20 | $1.40 |
| 45 | Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274) | LF | 29,702 | $0.75 | $0.74 | $0.95 | $0.76 | $0.95 | $1.20 | $1.40 |
| 46 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 265,374 | $0.75 | $0.57 | $0.70 | $0.59 | $0.60 | $0.95 | $0.77 |
| 47 | Prefabricated PM type B (W)(RR crossing) (668-7035) | EACH | 2 | $720.00 | $2,134.80 | $1,500.00 | $1,000.00 | $725.00 | $5,000.00 | $885.00 |
| 48 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 80 | $20.00 | $13.33 | $8.00 | $22.00 | $20.00 | $14.00 | $27.50 |
| 49 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 2,144 | $4.75 | $3.95 | $5.00 | $11.00 | $6.00 | $8.00 | $6.00 |
| 50 | TMSP radar speed control monitor (6025-7001) | EACH | 8 | $10,000 | $2,706.25 | $10,000 | $10,000 | $2,500.00 | $5,000.00 | $11,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 2, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.