TxDOT contract A00209917 bid tabulation
Hazard Elimination & Safety, SH 16 (1000 ft North of Rockport Rd to Leon Creek). Let by Texas DOT on November 5, 2025, Bexar, San Antonio District. 12 bids received; low bid $1,129,626 by Gratiot Construction, LTD., -35% against the engineer's estimate of $1,730,372.
- Owner
- Texas DOT
- Letting
- 05 NOV 2025
- Pay items
- 17
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Gratiot Construction, LTD. | $1,129,626 | Low | -35% |
| 2 | D&S Concrete Contractors LLC | $1,173,719 | +4.0% | -32% |
| 3 | Massana Construction Inc. | $1,199,130 | +6.0% | -31% |
| 4 | Roadway Specialties, Inc. | $1,211,106 | +7.0% | -30% |
| 5 | Dan Williams Company | $1,250,321 | +11% | -28% |
| 6 | Ross Sa Enterprise LLC | $1,326,704 | +17% | -23% |
| 7 | SCR Civil Construction, LLC | $1,353,263 | +20% | -22% |
| 8 | Scout 5 Construction LLC | $1,357,579 | +20% | -22% |
| 9 | HJC Farms, Inc. | $1,422,165 | +26% | -18% |
| 10 | STX Civil | $1,702,199 | +51% | -2.0% |
| 11 | Grey Sky Construction LLC | $1,886,014 | +67% | +9.0% |
| 12 | Salinas Construction Technologies, LTD. | $1,988,387 | +76% | +15% |
Engineer's estimate: $1,730,372.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Gratiot Construction, LTD. | 2. D&S Concrete Contractors LLC | 3. Massana Construction Inc. | 4. Roadway Specialties, Inc. | 5. Dan Williams Company | 6. Ross Sa Enterprise LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Embankment (vehicle)(OC)(type C) (132-7017) | CY | 237 | $62.14 | $45.00 | $25.00 | $52.00 | $111.45 | $2.00 | $50.00 |
| 2 | Blading (150-7002) | HR | 173 | $169.28 | $35.00 | $15.00 | $29.00 | $270.93 | $75.00 | $50.00 |
| 3 | Drill seed (permanent_rural_clay) (164-7010) | SY | 22,736 | $0.63 | $0.33 | $0.70 | $0.24 | $0.21 | $0.24 | $0.25 |
| 4 | Drill seed (temporary_warm_cool) (164-7015) | SY | 22,736 | $0.25 | $0.33 | $0.70 | $0.16 | $0.22 | $0.16 | $0.25 |
| 5 | Vegetative watering (168-7001) | TGL | 358 | $45.28 | $20.00 | $10.00 | $70.00 | $68.97 | $5.00 | $50.00 |
| 6 | Soil ret BLKT(SL_mod_clay_short) (169-7001) | SY | 22,736 | $2.00 | $1.20 | $0.53 | $1.25 | $0.85 | $1.25 | $2.00 |
| 7 | Riprap (concrete)(CL A) (432-7004) | CY | 948 | $568.77 | $460.00 | $575.00 | $385.00 | $352.57 | $415.00 | $550.00 |
| 8 | Mobilization (500-7001) | LS | 1 | $200,000 | $115,000 | $70,000 | $122,399 | $174,753 | $120,000 | $100,000 |
| 9 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $3,333.58 | $4,500.00 | $4,000.00 | $7,500.00 | $2,455.02 | $13,000 | $5,000.00 |
| 10 | Portable changeable message sign (503-7002) | EACH | 4 | $5,878.00 | $2,000.00 | $2,000.00 | $1,500.00 | $4,720.08 | $9,000.00 | $1,850.00 |
| 11 | TMA (stationary) (505-7001) | DAY | 80 | $352.21 | $25.00 | $250.00 | $122.00 | $250.00 | $140.00 | $500.00 |
| 12 | Temporary sediment control fence (install) (506-7039) | LF | 1,032 | $3.41 | $5.00 | $4.00 | $3.30 | $3.32 | $3.30 | $5.00 |
| 13 | Temporary sediment control fence (remove) (506-7041) | LF | 1,032 | $0.59 | $1.50 | $0.50 | $0.80 | $0.47 | $0.80 | $1.00 |
| 14 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 650 | $3.50 | $6.00 | $1.00 | $4.00 | $2.72 | $4.00 | $18.00 |
| 15 | Biodegradable erosion control logs (remove) (506-7046) | LF | 650 | $1.04 | $2.00 | $0.50 | $0.80 | $1.25 | $0.80 | $1.00 |
| 16 | Cable barrier system (install)(TL-4) (543-7002) | LF | 34,102 | $20.00 | $9.50 | $10.00 | $12.00 | $9.23 | $10.75 | $11.00 |
| 17 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 72 | $1,500.00 | $2,000.00 | $1,500.00 | $2,250.00 | $2,814.31 | $2,750.00 | $2,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 5, 2025. Compiled by Mirage Metrics.