TxDOT contract A00211965 bid tabulation
Preventive Maintenance, Various (ON IH 10 (DISTRICTWIDE) to .). Let by Texas DOT on September 5, 2025, El Paso, El Paso District. 5 bids received; low bid $4,508,216 by International Eagle Enterprises, Inc., -29% against the engineer's estimate of $6,376,066.
- Owner
- Texas DOT
- Letting
- 05 SEP 2025
- Pay items
- 51
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | International Eagle Enterprises, Inc. | $4,508,216 | Low | -29% |
| 2 | Dan Williams Company | $5,505,586 | +22% | -14% |
| 3 | Gibson & Associates, Inc. | $6,161,335 | +37% | -3.0% |
| 4 | Spartan Construction of Texas, Inc. | $6,339,711 | +41% | -1.0% |
| 5 | Southern Road & Bridge, LLC | $9,429,909 | +109% | +48% |
Engineer's estimate: $6,376,066.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. International Eagle Enterprises, Inc. | 2. Dan Williams Company | 3. Gibson & Associates, Inc. | 4. Spartan Construction of Texas, Inc. | 5. Southern Road & Bridge, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 53 | $26.00 | $200.00 | $42.00 | $27.50 | $104.64 | $25.00 |
| 2 | Embankment (final)(OC)(type A) (132-7001) | CY | 2 | $161.00 | $500.00 | $300.00 | $750.00 | $1,962.00 | $95.00 |
| 3 | Flexible pavement structure repair(2") (351-7001) | SY | 4 | $45.00 | $1,000.00 | $1,500.00 | $1,250.00 | $1,700.40 | $25.00 |
| 4 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 3,800 | $10.00 | $2.00 | $10.00 | $15.38 | $33.98 | $25.00 |
| 5 | Flowable backfill (401-7001) | CY | 10 | $275.00 | $350.00 | $1,000.00 | $467.50 | $849.60 | $1,950.00 |
| 6 | Epoxy waterproof finish (type X) (427-7005) | SF | 9,080 | $18.00 | $5.00 | $11.00 | $13.20 | $15.70 | $22.00 |
| 7 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 330 | $225.00 | $160.00 | $250.00 | $308.00 | $294.30 | $485.00 |
| 8 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 1,024 | $300.00 | $170.00 | $225.00 | $380.00 | $176.58 | $600.00 |
| 9 | Riprap (concrete)(4 in) (432-7001) | CY | 7 | $930.00 | $1,200.00 | $2,000.00 | $973.50 | $1,373.40 | $650.00 |
| 10 | Riprap (mow strip)(4 in) (432-7013) | CY | 20 | $550.00 | $850.00 | $1,700.00 | $907.50 | $1,308.00 | $500.00 |
| 11 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 15 | $145.00 | $500.00 | $300.00 | $313.50 | $654.00 | $500.00 |
| 12 | Elastomeric bearing (laminated) (434-7002) | EACH | 72 | $3,000.00 | $200.00 | $550.00 | $350.00 | $915.60 | $4,250.00 |
| 13 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 225 | $36.00 | $30.00 | $30.00 | $48.00 | $52.32 | $125.00 |
| 14 | Concrete overlay (3 in) (439-7004) | SY | 6,980 | $130.00 | $125.00 | $143.00 | $178.00 | $183.12 | $225.00 |
| 15 | Miscellaneous non-bridge (nbis) (442-7017) | LB | 336 | $25.00 | $20.00 | $15.00 | $25.00 | $23.54 | $95.00 |
| 16 | Hydro-demolition (2 1/2 in) (483-7011) | SY | 3,800 | $132.00 | $140.00 | $240.00 | $186.00 | $156.96 | $408.00 |
| 17 | Hydro-demolition (3 in) (483-7012) | SY | 3,180 | $140.00 | $140.00 | $249.00 | $162.00 | $189.66 | $525.00 |
| 18 | Raising existing struct (495-7001) | LS | 2 | $100,000 | $250,000 | $150,000 | $137,000 | $326,400 | $77,000 |
| 19 | Mobilization (500-7001) | LS | 1 | $800,000 | $400,000 | $500,000 | $736,000 | $629,016 | $600,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $12,000 | $20,000 | $30,000 | $51,000 | $19,620 | $10,000 |
| 21 | Portable changeable message sign (503-7002) | EACH | 6 | $12,000 | $14,000 | $12,000 | $25,000 | $13,080 | $22,000 |
| 22 | TMA (stationary) (505-7001) | DAY | 375 | $300.00 | $100.00 | $175.00 | $450.00 | $523.20 | $330.00 |
| 23 | TMA (mobile operation) (505-7003) | DAY | 8 | $500.00 | $300.00 | $650.00 | $1,050.00 | $4,578.00 | $300.00 |
| 24 | Metal W-beam guard fence (steel post) (540-7002) | LF | 250 | $46.00 | $40.00 | $35.00 | $53.08 | $71.94 | $39.00 |
| 25 | Remove metal beam guard fence (542-7001) | LF | 450 | $10.00 | $2.00 | $6.00 | $11.00 | $13.08 | $6.00 |
| 26 | Remove downstream anchor terminal (542-7003) | EACH | 2 | $300.00 | $800.00 | $350.00 | $1,650.00 | $1,962.00 | $1,100.00 |
| 27 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $4,500.00 | $3,000.00 | $4,000.00 | $5,340.50 | $5,886.00 | $3,988.00 |
| 28 | Guardrail end treatment (remove) (544-7003) | EACH | 2 | $325.00 | $800.00 | $350.00 | $1,650.00 | $1,308.00 | $7,500.00 |
| 29 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 4 | $2,330.00 | $2,500.00 | $2,000.00 | $5,791.50 | $3,270.00 | $250.00 |
| 30 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 12 | $22.00 | $10.00 | $55.00 | $203.50 | $91.56 | $110.00 |
| 31 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 16 | $38.00 | $10.00 | $55.00 | $203.50 | $91.56 | $110.00 |
| 32 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 12 | $20.00 | $5.00 | $55.00 | $203.50 | $91.56 | $110.00 |
| 33 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 130 | $2.30 | $4.00 | $2.25 | $10.00 | $6.54 | $1.00 |
| 34 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 130 | $2.30 | $4.00 | $2.25 | $10.00 | $6.54 | $1.00 |
| 35 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 486 | $0.20 | $1.60 | $0.80 | $0.88 | $1.11 | $1.00 |
| 36 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 1,940 | $0.49 | $0.70 | $0.35 | $0.39 | $0.52 | $2.00 |
| 37 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 1,940 | $0.49 | $0.70 | $0.35 | $0.39 | $0.52 | $2.00 |
| 38 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 1,940 | $2.25 | $4.60 | $2.30 | $2.53 | $3.14 | $3.00 |
| 39 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 1,940 | $2.25 | $4.60 | $2.30 | $2.53 | $3.14 | $3.00 |
| 40 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 486 | $1.84 | $4.80 | $2.40 | $2.64 | $3.27 | $4.00 |
| 41 | Prefabricated PM type B (W)(6")(broken) (668-7008) | LF | 834 | $13.00 | $13.00 | $6.50 | $7.15 | $8.63 | $10.00 |
| 42 | Prefabricated PM type B (W)(6")(solid) (668-7009) | LF | 1,112 | $10.00 | $12.00 | $6.00 | $6.60 | $8.11 | $9.00 |
| 43 | Prefabricated PM type B (W)(6")(broken)contrast (668-7012) | LF | 834 | $25.00 | $28.00 | $14.00 | $15.40 | $18.31 | $18.00 |
| 44 | Prefabricated PM type B (Y)(6")(solid) (668-7051) | LF | 1,112 | $10.00 | $13.00 | $6.50 | $7.15 | $8.63 | $10.00 |
| 45 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 68 | $8.05 | $18.00 | $9.00 | $9.90 | $13.08 | $12.00 |
| 46 | Pavement surface preparation for marking (6") (678-7002) | LF | 7,424 | $0.40 | $0.68 | $0.34 | $0.37 | $0.59 | $1.00 |
| 47 | Tree trimming / brush removal(channels) (752-7003) | ACRE | 0.10 | $2,750.00 | $2,000.00 | $10,000 | $20,000 | $235,440 | $25,000 |
| 48 | CNC crack repair (discrete)(inject) (780-7002) | LF | 3 | $78.00 | $15.00 | $300.00 | $500.00 | $1,308.00 | $353.00 |
| 49 | Bridge joint replacement (SEJ) (785-7011) | LF | 1,196 | $800.00 | $500.00 | $500.00 | $500.00 | $555.90 | $858.00 |
| 50 | Carbon fiber reinforced polymer strengthning (786-7002) | SF | 8,280 | $155.00 | $40.00 | $35.00 | $41.00 | $58.86 | $105.00 |
| 51 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 16 | $1,100.00 | $1,000.00 | $750.00 | $1,400.00 | $3,270.00 | $1,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 5, 2025. Compiled by Mirage Metrics.