TxDOT contract A00212049 bid tabulation
BRIDGE PREVENTATIVE MAINTENANCE, FM0709 (Navarro to Maintenance Section). Let by Texas DOT on January 15, 2025, Navarro, Dallas District. 7 bids received; low bid $223,095 by Rhino Equity, LLC, -22% against the engineer's estimate of $284,900.
- Owner
- Texas DOT
- Letting
- 15 JAN 2025
- Pay items
- 14
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Rhino Equity, LLC | $223,095 | Low | -22% |
| 2 | Cross Plus Construction, LLC | $257,127 | +15% | -10% |
| 3 | Garret Shields Infrastructure | $272,820 | +22% | -4.0% |
| 4 | Shalom Services Corporation | $279,451 | +25% | -2.0% |
| 5 | Beck-Reit & Sons, LTD. | $313,025 | +40% | +10% |
| 6 | Pathfield Investments LLC | $317,620 | +42% | +11% |
| 7 | Roy Jorgensen Associates, Inc. | $422,910 | +90% | +48% |
Engineer's estimate: $284,900.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Rhino Equity, LLC | 2. Cross Plus Construction, LLC | 3. Garret Shields Infrastructure | 4. Shalom Services Corporation | 5. Beck-Reit & Sons, LTD. | 6. Pathfield Investments LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 25 | $40.00 | $20.00 | $35.00 | $50.00 | $30.00 | $75.00 | $60.00 |
| 2 | Embankment (final)(OC)(type C2) (132-7009) | CY | 280 | $25.00 | $40.00 | $45.00 | $50.00 | $101.00 | $75.00 | $120.00 |
| 3 | Flowable backfill (401-7001) | CY | 8 | $500.00 | $400.00 | $500.00 | $600.00 | $400.00 | $400.00 | $400.00 |
| 4 | Temporary special shoring (403-7001) | SF | 800 | $50.00 | $12.00 | $25.00 | $50.00 | $40.00 | $26.00 | $35.00 |
| 5 | Gabions (galvanized) (459-7001) | CY | 245 | $400.00 | $350.00 | $299.00 | $270.00 | $320.00 | $377.00 | $290.00 |
| 6 | Gabion mattresses (galvanized)(12 in) (459-7007) | SY | 427 | $200.00 | $135.00 | $291.00 | $230.00 | $300.00 | $255.00 | $320.00 |
| 7 | Mobilization (500-7001) | LS | 1 | $25,900 | $45,300 | $20,000 | $20,000 | $1.00 | $44,000 | $25,000 |
| 8 | Barricades, signs and traffic handling (502-7001) | MO | 3 | $2,000.00 | $400.00 | $500.00 | $5,000.00 | $2,500.00 | $5,000.00 | $10.00 |
| 9 | Portable changeable message sign (503-7001) | DAY | 10 | $200.00 | $200.00 | $1.00 | $1.00 | $1.00 | $150.00 | $10.00 |
| 10 | TMA (stationary) (505-7001) | DAY | 10 | $400.00 | $200.00 | $1.00 | $1,000.00 | $1.00 | $100.00 | $10.00 |
| 11 | Rock filter dams (install) (type 2) (506-7002) | LF | 200 | $30.00 | $12.00 | $0.10 | $8.00 | $2.00 | $10.00 | $60.00 |
| 12 | Rock filter dams (remove) (506-7011) | LF | 200 | $20.00 | $6.00 | $1.00 | $1.00 | $2.00 | $1.00 | $20.00 |
| 13 | Temporary sediment control fence (install) (506-7039) | LF | 200 | $5.00 | $4.00 | $1.00 | $6.00 | $1.00 | $5.00 | $8.00 |
| 14 | Temporary sediment control fence (remove) (506-7041) | LF | 200 | $3.00 | $1.50 | $1.00 | $2.00 | $1.00 | $1.00 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 15, 2025. Compiled by Mirage Metrics.