TxDOT contract A00213281 bid tabulation
TRAFFIC SIGNAL MAINTENANCE, US0084 (Various locations to Across the Waco District). Let by Texas DOT on April 4, 2025, McLennan, Waco District. 4 bids received; low bid $1,538,098 by E-Z Bel Construction, LLC, -4.4% against the engineer's estimate of $1,609,077.
- Owner
- Texas DOT
- Letting
- 04 APR 2025
- Pay items
- 71
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | E-Z Bel Construction, LLC | $1,538,098 | Low | -4.0% |
| 2 | WG Engineering & Construction, LLC | $1,799,782 | +17% | +12% |
| 3 | Austin Traffic Signal Construction Co., Inc. | $1,913,201 | +24% | +19% |
| 4 | Yunex LLC | $2,541,851 | +65% | +58% |
Engineer's estimate: $1,609,077.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. E-Z Bel Construction, LLC | 2. WG Engineering & Construction, LLC | 3. Austin Traffic Signal Construction Co., Inc. | 4. Yunex LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Drilled shaft (42 in) (416-7007) | LF | 20 | $356.26 | $650.00 | $563.60 | $1,500.00 | $592.00 |
| 2 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 40 | $500.00 | $500.00 | $420.90 | $600.00 | $695.00 |
| 3 | Riprap (concrete)(4 in) (432-7001) | CY | 1.25 | $1,000.00 | $3,000.00 | $4,291.60 | $2,000.00 | $1,046.00 |
| 4 | Riprap (concrete)(CL A) (432-7004) | CY | 1 | $1,000.00 | $1,250.00 | $5,364.50 | $2,000.00 | $1,129.00 |
| 5 | Mobilization (callout 1) (500-7003) | EACH | 1 | $5,000.00 | $3,750.00 | $10,672 | $24,000 | $10,105 |
| 6 | Mobilization (callout 2) (500-7004) | EACH | 1 | $5,000.00 | $9,000.00 | $13,582 | $8,000.00 | $13,568 |
| 7 | Mobilization (callout 3) (500-7005) | EACH | 1 | $5,000.00 | $1,000.00 | $13,582 | $8,000.00 | $13,568 |
| 8 | Mobilization (callout 4) (500-7006) | EACH | 1 | $2,500.00 | $1,000.00 | $5,821.00 | $6,000.00 | $5,370.00 |
| 9 | Mobilization (callout 5) (500-7007) | EACH | 1 | $5,000.00 | $5,000.00 | $14,553 | $6,000.00 | $14,203 |
| 10 | Mobilization (callout 6) (500-7008) | EACH | 1 | $2,500.00 | $4,250.00 | $6,791.20 | $14,000 | $8,037.00 |
| 11 | Mobilization (callout 7) (500-7009) | EACH | 1 | $5,000.00 | $4,500.00 | $12,612 | $16,000 | $9,478.00 |
| 12 | Mobilization (callout 8) (500-7010) | EACH | 1 | $25,000 | $2,250.00 | $107,574 | $85,000 | $20,080 |
| 13 | Mobilization (callout 9) (500-7011) | EACH | 1 | $20,000 | $1,000.00 | $35,896 | $35,000 | $26,774 |
| 14 | Mobilization (callout 10) (500-7012) | EACH | 1 | $5,000.00 | $10,500 | $11,642 | $45,000 | $7,437.00 |
| 15 | Mobilization (callout 11) (500-7013) | EACH | 1 | $5,000.00 | $18,000 | $18,433 | $9,500.00 | $14,511 |
| 16 | Portable changeable message sign (503-7001) | DAY | 40 | $90.00 | $95.00 | $148.70 | $300.00 | $268.00 |
| 17 | TMA (stationary) (505-7001) | DAY | 180 | $206.87 | $300.00 | $322.20 | $300.00 | $1,230.00 |
| 18 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 20 | $4,974.66 | $7,900.00 | $4,997.10 | $4,400.00 | $4,955.00 |
| 19 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 272 | $34.25 | $25.00 | $18.20 | $44.00 | $40.00 |
| 20 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 1,831 | $22.00 | $25.00 | $23.70 | $45.00 | $26.00 |
| 21 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 76 | $65.00 | $30.00 | $28.70 | $68.00 | $44.00 |
| 22 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 1,044 | $50.00 | $33.50 | $37.70 | $75.00 | $48.00 |
| 23 | Conduit (RM) (1 1/2") (618-7076) | LF | 742 | $16.00 | $35.00 | $30.80 | $30.00 | $77.00 |
| 24 | Conduit (prepare) (618-7090) | LF | 5,347 | $11.00 | $4.50 | $2.00 | $15.00 | $6.00 |
| 25 | Electrical conductor (no.14) insulated (620-7002) | LF | 450 | $1.08 | $8.00 | $2.00 | $4.00 | $3.00 |
| 26 | Electrical conductor (no.8) bare (620-7007) | LF | 18,436 | $3.00 | $3.35 | $2.60 | $2.00 | $4.00 |
| 27 | Electrical conductor (no.8) insulated (620-7008) | LF | 36,689 | $3.25 | $3.35 | $2.60 | $3.00 | $4.00 |
| 28 | Electrical conductor (no.6) bare (620-7009) | LF | 2,163 | $4.00 | $4.75 | $2.90 | $4.00 | $4.00 |
| 29 | Electrical conductor (no.6) insulated (620-7010) | LF | 4,291 | $4.25 | $4.75 | $2.90 | $4.00 | $4.00 |
| 30 | Ground box type A (122311)W/apron (624-7002) | EACH | 12 | $2,000.00 | $2,250.00 | $1,785.80 | $1,500.00 | $4,830.00 |
| 31 | Ground box type D (162922)W/apron (624-7008) | EACH | 3 | $2,500.00 | $3,000.00 | $1,845.30 | $2,900.00 | $4,919.00 |
| 32 | Retro ground box (W/secure lid) (624-7015) | EACH | 496 | $500.00 | $100.00 | $897.70 | $500.00 | $571.00 |
| 33 | Remove electrical services (628-7002) | EACH | 9 | $960.00 | $500.00 | $970.20 | $3,800.00 | $1,806.00 |
| 34 | Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048) | EACH | 1 | $8,050.00 | $12,000 | $9,820.60 | $8,500.00 | $9,576.00 |
| 35 | Elc SRV type A 240/480 060(NS)SS(E)SP(U) (628-7049) | EACH | 1 | $6,540.00 | $12,000 | $8,964.60 | $8,000.00 | $9,225.00 |
| 36 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 1 | $7,250.00 | $12,000 | $9,083.50 | $7,000.00 | $8,993.00 |
| 37 | Elc SRV type D 120/240 060(NS)SS(N)SP(O) (628-7156) | EACH | 1 | $7,250.00 | $12,000 | $8,726.80 | $7,000.00 | $8,560.00 |
| 38 | Elc SRV type D 120/240 100(NS)SS(N)PS(U) (628-7257) | EACH | 5 | $8,000.00 | $10,000 | $7,514.10 | $8,000.00 | $7,963.00 |
| 39 | Aluminum signs (type A) (636-7001) | SF | 42 | $145.00 | $45.00 | $42.60 | $71.00 | $62.00 |
| 40 | Replace existing aluminum signs(type O) (636-7006) | SF | 204 | $45.00 | $50.00 | $49.40 | $75.00 | $64.00 |
| 41 | Remove sign walkway (654-7007) | EACH | 2 | $3,000.00 | $1,000.00 | $1,617.00 | $1,500.00 | $2,709.00 |
| 42 | Install highway traffic signal (upgrade) (680-7011) | EACH | 1 | $5,000.00 | $15,000 | $22,768 | $18,000 | $14,423 |
| 43 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 8 | $265.00 | $475.00 | $399.50 | $500.00 | $434.00 |
| 44 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 4 | $265.00 | $475.00 | $399.50 | $500.00 | $434.00 |
| 45 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 8 | $265.00 | $475.00 | $399.50 | $500.00 | $434.00 |
| 46 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 8 | $265.00 | $475.00 | $399.50 | $500.00 | $434.00 |
| 47 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 8 | $265.00 | $475.00 | $399.50 | $500.00 | $434.00 |
| 48 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 4 | $265.00 | $475.00 | $399.50 | $500.00 | $434.00 |
| 49 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 8 | $150.00 | $275.00 | $217.60 | $150.00 | $166.00 |
| 50 | Backplate W/reflectorized border(4 sec)aluminum (682-7040) | EACH | 4 | $240.00 | $350.00 | $253.30 | $200.00 | $234.00 |
| 51 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 6,583 | $3.94 | $4.50 | $3.40 | $4.00 | $4.95 |
| 52 | Traffic signal CBL (type A)(12 AWG)(16 conductor) (684-7021) | LF | 5,548 | $4.97 | $9.00 | $6.80 | $8.00 | $7.90 |
| 53 | Traffic signal CBL (type A)(16 AWG)(3 conductor) (684-7049) | LF | 5,511 | $2.25 | $2.50 | $2.30 | $6.00 | $3.04 |
| 54 | Traffic signal CBL (type C)(14 AWG)(2 conductor) (684-7080) | LF | 106 | $2.10 | $2.75 | $2.50 | $3.00 | $4.00 |
| 55 | Pedestrian pole assembly (687-7001) | EACH | 1 | $3,500.00 | $3,000.00 | $3,918.80 | $5,500.00 | $5,139.00 |
| 56 | Pedestrian detect push button (APS) (688-7001) | EACH | 2 | $927.97 | $1,750.00 | $1,234.20 | $1,500.00 | $1,533.00 |
| 57 | Removal of cables (690-7009) | LF | 47,823 | $2.88 | $1.90 | $0.90 | $1.00 | $12.00 |
| 58 | Removal of signal head assembly (690-7024) | EACH | 12 | $75.00 | $140.00 | $242.60 | $200.00 | $68.00 |
| 59 | Removal of signal related signs (690-7027) | EACH | 4 | $125.00 | $140.00 | $161.70 | $100.00 | $226.00 |
| 60 | Removal of pedestrian push buttons (690-7030) | EACH | 2 | $300.00 | $140.00 | $80.90 | $100.00 | $226.00 |
| 61 | Remove vid image vehicle det sys (VIVDS) (690-7086) | EACH | 10 | $513.21 | $140.00 | $323.40 | $250.00 | $1,355.00 |
| 62 | VIVDS cabling (remove) (6006-7020) | LF | 2,384 | $0.50 | $0.75 | $1.30 | $7.00 | $6.00 |
| 63 | Bbu system (external battery cabinet) (6007-7001) | EACH | 1 | $8,500.00 | $10,000 | $8,519.90 | $9,000.00 | $10,936 |
| 64 | RVDS (presence and advance detection) (6008-7003) | EACH | 14 | $10,000 | $10,000 | $9,140.40 | $7,500.00 | $8,813.00 |
| 65 | Radar presence detector comm cable (6008-7009) | LF | 769 | $3.00 | $4.00 | $5.50 | $3.00 | $5.00 |
| 66 | ITS pole (55 FT)(relocate) (6011-7021) | EACH | 1 | $6,000.00 | $9,000.00 | $4,244.50 | $7,600.00 | $8,729.00 |
| 67 | Ground box (prepare) (6013-7006) | EACH | 36 | $450.00 | $350.00 | $261.60 | $2,200.00 | $369.00 |
| 68 | Loop installation (6041-7001) | LF | 450 | $13.87 | $6.00 | $18.70 | $35.00 | $29.00 |
| 69 | Sensor installation (6041-7002) | EACH | 2 | $2,485.71 | $1,750.00 | $2,211.50 | $4,000.00 | $2,887.00 |
| 70 | Remove and replace DMS (6054-7001) | EACH | 5 | $35,000 | $49,500 | $29,223 | $26,000 | $37,275 |
| 71 | Maintenance speed limit signing (7010-7001) | EACH | 4 | $500.00 | $100.00 | $485.10 | $2,300.00 | $511.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.