TxDOT contract A00215515 bid tabulation
Rehabilitate Existing Roadway, SS 380 (THREADNEEDLE ROAD, SOUTH to JIM GILLIGAN WAY). Let by Texas DOT on June 3, 2026, Jefferson, Beaumont District. 4 bids received; low bid $4,771,697 by Texas Materials Group, Inc., +1.8% against the engineer's estimate of $4,685,457.
- Owner
- Texas DOT
- Letting
- 03 JUN 2026
- Pay items
- 59
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Texas Materials Group, Inc. | $4,771,697 | Low | +2.0% |
| 2 | Select Maintenance, L.L.C. | $5,689,672 | +19% | +21% |
| 3 | Hayden Paving, Inc. | $6,076,524 | +27% | +30% |
| 4 | Durwood Greene Construction Co. | $7,678,257 | +61% | +64% |
Engineer's estimate: $4,685,457.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Texas Materials Group, Inc. | 2. Select Maintenance, L.L.C. | 3. Hayden Paving, Inc. | 4. Durwood Greene Construction Co. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (curb) (104-7016) | LF | 50 | $30.00 | $32.00 | $26.00 | $75.00 | $40.00 |
| 2 | Asphalt (AC-20-5TR or AC-20XP) (316-7067) | GAL | 29,881 | $4.00 | $5.00 | $5.00 | $6.00 | $6.00 |
| 3 | Aggregate (type-PB or PL, GR-4)(sac-A) (316-7241) | CY | 639 | $195.00 | $245.00 | $266.00 | $405.00 | $300.00 |
| 4 | Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009) | TON | 6,848 | $210.00 | $244.75 | $295.00 | $369.00 | $340.00 |
| 5 | Tack coat (346-7028) | GAL | 3,320 | $3.75 | $5.00 | $5.00 | $5.00 | $4.00 |
| 6 | Plane concrete pavement(0" to 0.5") (354-7062) | SY | 8,962 | $5.00 | $6.00 | $12.02 | $4.00 | $17.00 |
| 7 | Planing asphalt concrete pavement(0" to 2.25") (354-7075) | SY | 83,002 | $5.00 | $2.75 | $2.60 | $2.30 | $6.75 |
| 8 | Full - depth repair CRCP (8") (361-7003) | CY | 180 | $1,100.00 | $1,250.00 | $1,100.00 | $1,850.00 | $1,800.00 |
| 9 | Full - depth repair CPJR (10") (361-7038) | CY | 100 | $1,300.00 | $1,250.00 | $1,100.00 | $2,250.00 | $2,200.00 |
| 10 | Cleaning and sealing existing joints (438-7001) | LF | 65,635 | $5.00 | $4.50 | $4.00 | $7.00 | $5.50 |
| 11 | Mobilization (500-7001) | LS | 1 | $400,000 | $360,000 | $570,000 | $180,000 | $600,000 |
| 12 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $5,000.00 | $1,000.00 | $28,500 | $7,000.00 | $12,000 |
| 13 | Portable changeable message sign (503-7002) | EACH | 2 | $4,750.00 | $1,705.00 | $40,000 | $19,000 | $20,000 |
| 14 | TMA (stationary) (505-7001) | DAY | 150 | $125.00 | $341.00 | $50.00 | $700.00 | $400.00 |
| 15 | TMA (mobile operation) (505-7003) | DAY | 25 | $126.00 | $786.00 | $350.00 | $1,100.00 | $400.00 |
| 16 | Temporary SDMT cont fence (inlet protection) (506-7040) | LF | 400 | $3.00 | $13.50 | $8.00 | $21.00 | $20.00 |
| 17 | Temporary sediment control fence (remove) (506-7041) | LF | 400 | $1.00 | $5.75 | $0.10 | $6.00 | $6.00 |
| 18 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 6,420 | $80.00 | $93.00 | $144.00 | $110.00 | $140.00 |
| 19 | Permanent CTB (single slope) (type 3) (42 ) (514-7002) | LF | 1,650 | $200.00 | $203.25 | $18.00 | $121.00 | $430.00 |
| 20 | Concrete curb (type II) (529-7002) | LF | 160 | $38.00 | $28.50 | $25.00 | $105.00 | $100.00 |
| 21 | Remove metal beam guard fence (542-7001) | LF | 14,475 | $3.00 | $3.00 | $5.00 | $4.00 | $18.00 |
| 22 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,038.00 | $1,023.00 | $2,500.00 | $1,300.00 | $5,000.00 |
| 23 | Crash cushion attenuator (install)(R)(N)(TL3) (545-7010) | EACH | 4 | $25,000 | $34,000 | $50,000 | $39,000 | $42,000 |
| 24 | Replace existing aluminum signs (type A) (636-7008) | EACH | 34 | $350.00 | $182.00 | $400.00 | $220.00 | $120.00 |
| 25 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 18 | $700.00 | $597.00 | $650.00 | $950.00 | $1,000.00 |
| 26 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 6 | $800.00 | $722.00 | $650.00 | $950.00 | $1,100.00 |
| 27 | Install small roadside sign support and assembly TYS80(1)SB(T) (644-7040) | EACH | 8 | $900.00 | $966.50 | $650.00 | $1,100.00 | $1,400.00 |
| 28 | Install small roadside sign support and assembly TYS80(2)SA(P-exal) (644-7049) | EACH | 2 | $2,000.00 | $2,746.00 | $2,500.00 | $245.00 | $3,800.00 |
| 29 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 92 | $26.00 | $22.75 | $16.63 | $79.00 | $50.00 |
| 30 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 6,520 | $1.00 | $0.55 | $0.50 | $0.45 | $0.70 |
| 31 | Work zone pavement marking non-removing (W)6"(DOT) (662-7006) | LF | 65 | $1.00 | $0.75 | $0.60 | $0.45 | $5.00 |
| 32 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 7,722 | $1.00 | $0.55 | $0.50 | $0.45 | $0.70 |
| 33 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 3,525 | $1.00 | $0.75 | $0.65 | $0.69 | $1.50 |
| 34 | Work zone pavement marking non-removing (W)12"(DOT) (662-7013) | LF | 50 | $2.00 | $2.25 | $2.10 | $2.45 | $6.00 |
| 35 | Work zone pavement marking non-removing (W)12"(solid) (662-7015) | LF | 2,339 | $2.00 | $2.00 | $1.85 | $2.45 | $3.00 |
| 36 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 230 | $4.00 | $10.00 | $8.50 | $4.25 | $6.00 |
| 37 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 8 | $212.00 | $142.00 | $125.00 | $104.00 | $130.00 |
| 38 | Work zone pavement marking non-removing (W)(RR crossing) (662-7024) | EACH | 6 | $200.00 | $341.00 | $300.00 | $190.00 | $700.00 |
| 39 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 18 | $218.00 | $188.00 | $165.00 | $104.00 | $140.00 |
| 40 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 140 | $1.00 | $0.55 | $0.50 | $0.43 | $0.70 |
| 41 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 16,012 | $1.00 | $0.55 | $0.50 | $0.43 | $0.70 |
| 42 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 10,290 | $1.00 | $0.25 | $0.50 | $1.22 | $2.50 |
| 43 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 2,700 | $1.00 | $1.50 | $0.50 | $1.22 | $2.50 |
| 44 | Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008) | LF | 65 | $1.00 | $1.25 | $1.10 | $1.20 | $6.00 |
| 45 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 3,525 | $2.00 | $1.25 | $1.00 | $1.55 | $2.00 |
| 46 | Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265) | LF | 7,722 | $2.00 | $1.25 | $1.10 | $1.52 | $5.00 |
| 47 | Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407) | LF | 6,520 | $1.00 | $1.00 | $0.80 | $1.05 | $1.20 |
| 48 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 140 | $1.00 | $1.25 | $1.00 | $1.05 | $1.20 |
| 49 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 16,012 | $1.00 | $1.00 | $0.75 | $1.05 | $1.20 |
| 50 | Prefabricated PM type C (W)(12")(DOT) (668-7085) | LF | 50 | $6.00 | $4.00 | $3.25 | $9.70 | $20.00 |
| 51 | Prefabricated PM type C (W)(12")(solid) (668-7087) | LF | 2,339 | $7.00 | $6.50 | $5.75 | $9.70 | $14.00 |
| 52 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 230 | $20.00 | $20.00 | $17.50 | $19.35 | $25.00 |
| 53 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 8 | $200.00 | $284.00 | $250.00 | $306.00 | $350.00 |
| 54 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 18 | $354.00 | $341.00 | $300.00 | $306.00 | $400.00 |
| 55 | Prefabricated PM type C (W)(RR crossing) (668-7108) | EACH | 6 | $586.00 | $1,222.00 | $1,075.00 | $505.00 | $1,200.00 |
| 56 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 15 | $7.00 | $6.75 | $6.00 | $8.50 | $11.00 |
| 57 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 663 | $7.00 | $6.75 | $6.00 | $8.50 | $11.00 |
| 58 | Spalling repair (hydraulic cement) (720-7001) | CF | 500 | $350.00 | $210.00 | $185.00 | $162.00 | $300.00 |
| 59 | Spalling repair (polymeric) (semirigid) (720-7003) | GAL | 100 | $350.00 | $153.00 | $135.00 | $209.00 | $275.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 3, 2026. Compiled by Mirage Metrics.