TxDOT contract A00216495 bid tabulation

METAL BEAM GUARD FENCE REPAIR, IH0010 (Fayette, Lavaca, Gonzales, DeWitt, and to Colorado Counties). Let by Texas DOT on October 8, 2025, Fayette, Yoakum District. 4 bids received; low bid $946,199 by JCW Construction, LLC, -44% against the engineer's estimate of $1,689,375.

Owner
Texas DOT
Letting
08 OCT 2025
Pay items
44
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1JCW Construction, LLC$946,199Low-44%
2Ross Sa Enterprise LLC$1,257,000+33%-26%
3Roy Jorgensen Associates, Inc.$1,750,817+85%+4.0%
4Above All Contracting LLC$2,273,250+140%+35%
TxDOT contract A00216495: bids by rank

Engineer's estimate: $1,689,375.

Bid tabulation

LinePay itemUnitQuantityEstimate1. JCW Construction, LLC2. Ross Sa Enterprise LLC3. Roy Jorgensen Associates, Inc.4. Above All Contracting LLC
1Mobilization (callout) (500-7002)EACH24$1,000.00$1.00$11,000$7,000.00$500.00
2TMA (stationary) (505-7001)DAY200$150.00$1.00$2,000.00$750.00$200.00
3Metal beam guard fence trans (anchor plate) (540-7029)EACH5$750.00$250.00$100.00$1.00$600.00
4Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH100$30.00$1.00$20.00$10.00$40.00
5Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH100$35.00$1.00$1.00$10.00$40.00
6Replace rail element (W-beam) (770-7001)LF7,000$25.00$20.00$20.00$50.00$28.00
7Replace rail element (thrie-beam) (770-7002)LF100$50.00$50.00$10.00$15.00$75.00
8Repl rail elmnt(thrie-BM trans to W-BM) (770-7003)EACH40$35.00$100.00$10.00$200.00$2,500.00
9Replace timber post W/O concrete FND (770-7006)EACH500$50.00$500.00$25.00$100.00$100.00
10Replace steel post W/O concrete FND (770-7007)EACH250$50.00$1.00$25.00$125.00$100.00
11Replace timber post W/ concrete FND (770-7008)EACH100$55.00$500.00$425.00$100.00$100.00
12Replace steel post W/ concrete FND (770-7009)EACH50$55.00$1.00$100.00$125.00$100.00
13Realign posts (770-7010)EACH250$35.00$1.00$1.00$5.00$50.00
14Rem obsolete get & repl W/ SGT (770-7013)EACH100$3,000.00$2,000.00$100.00$1,000.00$3,600.00
15Repl single gdrail terminal impact head (770-7015)EACH50$1,200.00$1.00$550.00$3,000.00$1,000.00
16Replace single gdrail terminal rail (770-7016)LF2,000$30.00$25.00$30.00$65.00$40.00
17Replace single gdrail terminal post (770-7017)EACH250$65.00$50.00$40.00$1.00$125.00
18Replace blockout (770-7018)EACH700$37.00$100.00$200.00$50.00$25.00
19Reset SGT impact head (770-7020)EACH40$200.00$1.00$1.00$1.00$250.00
20Replace SGT object marker (770-7021)EACH100$45.00$1.00$1.00$1.00$25.00
21Replace SGT cable anchor (770-7022)EACH40$30.00$1.00$1.00$1.00$100.00
22Replace SGT cable assembly (770-7023)EACH50$30.00$1.00$1.00$1.00$100.00
23Replace SGT strut (770-7024)EACH50$35.00$1.00$1.00$1.00$125.00
24Repair rail element (curved rail) (770-7027)LF500$25.00$25.00$1.00$1.00$100.00
25Replace posts (TL-3)(trinity) (771-7003)EACH3,000$160.00$1.00$1.00$50.00$180.00
26Replace posts (TL-4)(gibraltar) (771-7005)EACH250$160.00$1.00$100.00$50.00$200.00
27Replace posts (TL-4)(trinity) (771-7007)EACH250$200.00$1.00$100.00$200.00$200.00
28Cable splice / turnbuckle (TL-3) (771-7009)EACH15$100.00$1.00$250.00$700.00$250.00
29Cable splice / turnbuckle (TL-4) (771-7010)EACH10$100.00$1.00$250.00$700.00$250.00
30Repair concrete foundation (TL-3) (771-7011)EACH10$100.00$1.00$1.00$1.00$500.00
31Repair concrete foundation (TL-4) (771-7012)EACH10$100.00$1.00$1.00$1.00$500.00
32Repair or replace cable barrier terminal sec(TL-3) (771-7013)EACH30$1,500.00$500.00$100.00$1,000.00$2,500.00
33Repair or replace cable barrier terminal sec(TL-4) (771-7014)EACH30$1,500.00$500.00$1.00$500.00$2,500.00
34Replace cable (TL-3) (771-7015)LF500$5.00$5.00$1.00$5.00$10.00
35Replace cable (TL-4) (771-7016)LF500$5.00$1.00$1.00$5.00$10.00
36Check / RE-tension cable (TL-3) (771-7017)EACH100$300.00$500.00$490.00$650.00$200.00
37Check / RE-tension cable (TL-4) (771-7018)EACH200$300.00$1.00$1.00$650.00$200.00
38Replace post hardware (TL-3) (771-7019)EACH1,000$11.00$0.10$0.01$1.00$80.00
39Replace post hardware (TL-4) (771-7020)EACH1,000$10.00$0.10$0.01$1.00$80.00
40Replace terminal line posts (trinity) (771-7021)EACH10$165.00$100.00$800.00$200.00$200.00
41Replace cable release post (trinity) (771-7023)EACH5$165.00$100.00$500.00$500.00$500.00
42Replace anchor post (gibralter) (771-7024)EACH10$165.00$100.00$500.00$500.00$700.00
43Replace (individual sand barrel) (774-7067)EACH200$325.00$1.00$1.00$350.00$400.00
44Lane closure(setup & rem)(typ 7) (790-7007)EACH12$4,000.00$5,000.00$500.00$1.00$5,000.00
TxDOT contract A00216495: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of October 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy