TxDOT contract A00217905 bid tabulation
METAL BEAM GUARD FENCE REPAIR, US0090 (VARIOUS LOCATIONS to VARIOUS LOCATIONS). Let by Texas DOT on January 7, 2026, Presidio, El Paso District. 4 bids received; low bid $1,198,026 by E.V.G. Enterprise, -32% against the engineer's estimate of $1,760,250.
- Owner
- Texas DOT
- Letting
- 07 JAN 2026
- Pay items
- 29
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | E.V.G. Enterprise | $1,198,026 | Low | -32% |
| 2 | Apache Barricade & Sign | $1,199,359 | 0.0% | -32% |
| 3 | Blacksmith Ventures LLC | $1,287,650 | +7.0% | -27% |
| 4 | Dan Williams Company | $2,053,905 | +71% | +17% |
Engineer's estimate: $1,760,250.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. E.V.G. Enterprise | 2. Apache Barricade & Sign | 3. Blacksmith Ventures LLC | 4. Dan Williams Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (curb) (104-7016) | LF | 100 | $8.00 | $17.00 | $49.00 | $50.00 | $30.00 |
| 2 | Riprap (concrete)(CL B) (432-7005) | CY | 170 | $800.00 | $728.00 | $725.00 | $800.00 | $2,200.00 |
| 3 | Mobilization (500-7001) | LS | 1 | $250,000 | $1.00 | $300,000 | $100,000 | $200,000 |
| 4 | TMA (stationary) (505-7001) | DAY | 160 | $1,800.00 | $3,000.00 | $1,300.00 | $4,400.00 | $650.00 |
| 5 | Concrete curb (type II) (529-7002) | LF | 100 | $150.00 | $45.00 | $375.00 | $100.00 | $120.00 |
| 6 | Concrete sidewalks (4") (531-7001) | SY | 90 | $300.00 | $98.00 | $525.00 | $200.00 | $325.00 |
| 7 | Remove metal beam guard fence (542-7001) | LF | 3,300 | $35.00 | $1.00 | $35.00 | $1.00 | $15.00 |
| 8 | Remove terminal anchor section (542-7002) | EACH | 5 | $900.00 | $1.00 | $375.00 | $500.00 | $600.00 |
| 9 | Remove downstream anchor terminal (542-7003) | EACH | 10 | $1,000.00 | $1.00 | $275.00 | $500.00 | $600.00 |
| 10 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 50 | $75.00 | $100.00 | $10.00 | $100.00 | $75.00 |
| 11 | Replace rail element (W-beam) (770-7001) | LF | 2,100 | $100.00 | $25.00 | $29.00 | $30.00 | $65.00 |
| 12 | Replace rail element (thrie-beam) (770-7002) | LF | 35 | $90.00 | $28.00 | $38.00 | $100.00 | $135.00 |
| 13 | Repl rail elmnt(thrie-BM trans to W-BM) (770-7003) | EACH | 60 | $75.00 | $30.00 | $265.00 | $200.00 | $950.00 |
| 14 | Replace timber post W/O concrete FND (770-7006) | EACH | 220 | $250.00 | $250.00 | $49.00 | $50.00 | $350.00 |
| 15 | Replace steel post W/O concrete FND (770-7007) | EACH | 120 | $300.00 | $250.00 | $89.00 | $100.00 | $420.00 |
| 16 | Realign posts (770-7010) | EACH | 90 | $100.00 | $100.00 | $28.00 | $50.00 | $225.00 |
| 17 | Repair of terminal anchors posts (770-7011) | EACH | 2 | $1,500.00 | $200.00 | $175.00 | $500.00 | $1,750.00 |
| 18 | Rem obsolete get & repl W/ SGT (770-7013) | EACH | 35 | $7,500.00 | $5,000.00 | $3,400.00 | $2,500.00 | $12,500 |
| 19 | Repl single gdrail terminal impact head (770-7015) | EACH | 2 | $3,000.00 | $1,000.00 | $1,300.00 | $1,300.00 | $3,500.00 |
| 20 | Replace single gdrail terminal rail (770-7016) | LF | 1,900 | $100.00 | $35.00 | $39.00 | $30.00 | $70.00 |
| 21 | Replace single gdrail terminal post (770-7017) | EACH | 325 | $175.00 | $300.00 | $59.00 | $50.00 | $725.00 |
| 22 | Replace blockout (770-7018) | EACH | 500 | $70.00 | $100.00 | $24.00 | $25.00 | $80.00 |
| 23 | Reset SGT impact head (770-7020) | EACH | 5 | $3,000.00 | $1,000.00 | $190.00 | $100.00 | $3,400.00 |
| 24 | Replace SGT object marker (770-7021) | EACH | 35 | $75.00 | $100.00 | $34.00 | $50.00 | $95.00 |
| 25 | Replace SGT cable anchor (770-7022) | EACH | 36 | $300.00 | $250.00 | $244.00 | $100.00 | $330.00 |
| 26 | Replace SGT cable assembly (770-7023) | EACH | 20 | $150.00 | $250.00 | $245.00 | $150.00 | $380.00 |
| 27 | Replace SGT strut (770-7024) | EACH | 20 | $100.00 | $250.00 | $125.00 | $150.00 | $340.00 |
| 28 | Replace downstream anchor terminal (770-7026) | EACH | 2 | $1,500.00 | $1,000.00 | $1,400.00 | $1,450.00 | $8,900.00 |
| 29 | Repair rail element (curved rail) (770-7027) | LF | 25 | $90.00 | $30.00 | $295.00 | $50.00 | $100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2026. Compiled by Mirage Metrics.