TxDOT contract A00221639 bid tabulation

METAL BEAM GUARD FENCE REPAIR, IH0020 (VARIOUS LOCATIONS IN to Palo Pinto And Parker). Let by Texas DOT on July 1, 2026, Palo Pinto, Fort Worth District. 5 bids received; low bid $974,892 by Short-Line Corporation, -43% against the engineer's estimate of $1,707,467.

Owner
Texas DOT
Letting
01 JUL 2026
Pay items
17
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Short-Line Corporation$974,892Low-43%
2T&L Cleaning Services LLC$1,031,222+6.0%-40%
3Austin Barricade Company, L.L.C.$1,124,217+15%-34%
4E.V.G. Enterprise$1,258,042+29%-26%
5Rhino Equity, LLC$1,301,462+33%-24%
TxDOT contract A00221639: bids by rank

Engineer's estimate: $1,707,467.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Short-Line Corporation2. T&L Cleaning Services LLC3. Austin Barricade Company, L.L.C.4. E.V.G. Enterprise5. Rhino Equity, LLC
1Mobilization (callout) (500-7002)EACH12$1,000.00$1.00$1.00$1.00$1.00$1.00
2Mobilization (emergency) (500-7033)EACH5$1,500.00$1.00$1,000.00$1.00$1.00$750.00
3TMA (stationary) (505-7001)DAY100$217.00$1.00$1.00$1.00$100.00$1,200.00
4Metal W-beam guard fence (timber post) (540-7001)LF9,000$27.97$15.00$28.00$28.00$46.00$25.00
5Driveway terminal anchor section (540-7014)EACH10$1,200.00$500.00$500.00$200.00$300.00$1,000.00
6Downstream anchor terminal section (540-7015)EACH10$1,450.00$1.00$1,000.00$200.00$1,000.00$1,000.00
7Guardrail end treatment (install) (544-7001)EACH32$3,349.50$3,000.00$3,000.00$4,000.00$4,500.00$3,600.00
8Replace downstream anchor terminal (770-7026)EACH10$800.00$1.00$1,000.00$200.00$1,000.00$1,500.00
9Replace rail element (thrie-beam) (770-7034)EACH10$1.00$5,000.00$1,500.00$1,000.00$500.00$200.00
10Replace W-beam rail (770-7035)LF2,500$45.00$20.00$28.00$35.00$17.00$25.00
11Replace guardrail end treatment system (770-7037)EACH100$4,228.43$2,500.00$4,000.00$4,000.00$4,500.00$3,600.00
12Replace curved rail (770-7038)LF500$50.00$10.00$25.00$30.00$30.00$27.00
13Remove rail (770-7040)LF10,000$50.00$15.00$0.01$0.01$0.00$5.00
14Replace line or terminal post (gibral) (771-7026)EACH1,000$185.00$200.00$150.00$210.00$150.00$300.00
15Replace cable release post (771-7029)EACH15$1,000.00$250.00$300.00$200.00$1.00$600.00
16Check and RE-tension cable system (771-7030)EACH10$500.00$3,000.00$1.00$1,000.00$300.00$500.00
17Splice cable (771-7033)EACH5$1,500.00$1.00$200.00$500.00$300.00$100.00
TxDOT contract A00221639: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of July 1, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy