TxDOT letting results, October 12, 2022
10 contracts let by Texas DOT on October 12, 2022, $1,142,833 in low bids, a median of 2 bidders per contract. On the 10 with an engineer's estimate, the low bid came in under it 7 times; median low bid -6.0% against the estimate.
- Owner
- Texas DOT
- Contracts
- 10
- Low bids, total
- $1,142,833
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10221822 | FM0876 Hot mix from ELLIS to MAINTENANCE SECTION | Dallas District | 2 | Texas Materials Group, Inc. | $229,400 | $244,150 | +6.0% | -20% | TxDOT |
| 10221702 | SH0036 Hot mix from VARIOUS to VARIOUS | Bryan District | 2 | Big Creek Construction, LTD. | $227,000 | $230,000 | +1.0% | 0.0% | TxDOT |
| 10221714 | SH0006 Debris removal from VARIOUS to VARIOUS | Bryan District | 4 | Expert Maintenance & Construction Services LLC | $133,983 | $142,120 | +6.0% | -20% | TxDOT |
| 10221707 | SH0036 Raised pavement markers from VARIOUS to VARIOUS | Bryan District | 3 | Brydl Contracting, LLC | $126,085 | $160,400 | +27% | -10% | TxDOT |
| 10221706 | IH0045 Hydraulic cement from VARIOUS to VARIOUS | Bryan District | 1 | Aka-Materials | $121,868 | +3.0% | TxDOT | ||
| 10221711 | SH0036 Aggregate from VARIOUS to VARIOUS | Bryan District | 3 | Knife River Corporation - South | $117,500 | $147,000 | +25% | -24% | TxDOT |
| 10221704 | SH0036 Hydraulic cement from VARIOUS to VARIOUS | Bryan District | 1 | Aka-Materials | $91,807 | +3.0% | TxDOT | ||
| 10221820 | FM0876 Emulsion from ELLIS to MAINTENANCE SECTION | Dallas District | 2 | Wright Asphalt Products Company LLC | $56,900 | $57,700 | +1.0% | -8.0% | TxDOT |
| 10221821 | FM0876 Hydraulic cement from ELLIS to MAINTENANCE SECTION | Dallas District | 1 | KLP Commercial, L.L.C. | $28,875 | -4.0% | TxDOT | ||
| 10221709 | SH0036 Asphaltic patching material from VARIOUS to VARIOUS | Bryan District | 1 | Waller County Asphalt Inc. | $9,415 | -1.0% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.