Tree removal (42" - 48" diameter), TxDOT 752-7011
Low bidders on TxDOT contracts carried a median of $390.00 per EACH for this item, over the 24 months to 19 NOV 2026, across 86 low bids. Half of all 564 bids fell between $345.00 and $1,000.00.
- Owner
- Texas DOT
- Item
- 752-7011
- Unit
- EACH
- Data through
- 19 NOV 2026
TxDOT prints this item as “TREE REMOVAL (42" - 48" DIA)”.
TxDOT has bid this work under more than one code: 7526011001 on lettings from 11 FEB 2020 to 02 JUN 2023 (16 bids); 7526011 on lettings from 12 FEB 2020 to 12 JUN 2024 (183 bids); 752-7011 on lettings from 07 NOV 2024 to 19 NOV 2026 (643 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 5 | 5 | $500.00 | 36 | $500.00 |
| 2021 | 18 | 14 | $425.00 | 77 | $550.00 |
| 2022 | 14 | 12 | $500.00 | 51 | $500.00 |
| 2023 | 4 | 3 | $320.00 | 13 | $450.00 |
| 2024 | 10 | 10 | $900.00 | 36 | $1,000.00 |
| 2025 | 46 | 39 | $250.00 | 288 | $500.00 |
| 2026 | 48 | 45 | $500.00 | 269 | $700.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Lufkin District | 18 | $200.00 | 113 | $400.00 |
| Dallas District | 7 | $250.00 | 63 | $700.00 |
| Atlanta District | 9 | $250.00 | 51 | $700.00 |
| Bryan District | 9 | $250.00 | 50 | $472.50 |
| Fort Worth District | 6 | $565.00 | 47 | $950.00 |
| Paris District | 7 | $400.00 | 46 | $600.00 |
| Tyler District | 4 | $700.00 | 29 | $450.00 |
| Beaumont District | 5 | $500.00 | 28 | $1,000.00 |
| San Angelo District | 3 | $500.00 | 23 | $700.00 |
| Waco District | 4 | $1,300.00 | 20 | $1,000.00 |
| Austin District | 3 | $300.00 | 19 | $1,000.00 |
| Brownwood District | 3 | $500.00 | 18 | $675.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 21 | $500.00 |
| 2 to 5 | 22 | $412.00 |
| 5 to 10 | 21 | $250.00 |
| 10 to 50 | 22 | $390.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Rhino Equity, LLC | 47 | 24 (51%) |
| K & R Contractors | 26 | 15 (58%) |
| Austin Barricade Company, L.L.C. | 35 | 8 (23%) |
| Allies Land Clearing | 21 | 8 (38%) |
| H. V. Caver, Inc. | 9 | 7 (78%) |
| Boen Landscaping & Irrigation, LLC | 13 | 6 (46%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 19 NOV 2026 | A00224894 | San Angelo District | 2 | $1,200.00 | $700.00 | $500.00 | 7 | Allies Land Clearing | TxDOT |
| 17 NOV 2026 | A00223761 | Beaumont District | 2 | $500.00 | $1,000.00 | $650.00 | 7 | Ace Contractors, Inc. | TxDOT |
| 17 NOV 2026 | A00223887 | Beaumont District | 10 | $400.00 | $1,000.00 | $650.00 | 7 | L & M Mowing Contractors, LLC | TxDOT |
| 17 NOV 2026 | A00223897 | Beaumont District | 2 | $500.00 | $1,400.00 | $650.00 | 8 | Ace Contractors, Inc. | TxDOT |
| 12 NOV 2026 | A00224261 | Amarillo District | 22 | $1,200.00 | $1,250.00 | $1,300.00 | 8 | Allies Land Clearing | TxDOT |
| 28 OCT 2026 | A00224238 | Lufkin District | 2 | $500.00 | $375.00 | $420.00 | 4 | Ace Contractors, Inc. | TxDOT |
| 14 OCT 2026 | A00221497 | Dallas District | 2 | $800.00 | $900.00 | $895.33 | 8 | GV Landscape and Construction LLC | TxDOT |
| 08 OCT 2026 | A00223995 | Yoakum District | 5 | $200.00 | $555.00 | $450.00 | 5 | ROW Contractors LLC | TxDOT |
| 23 SEP 2026 | A00222474 | Lufkin District | 15 | $650.00 | $500.00 | $400.00 | 2 | Western Certified Arborists | TxDOT |
| 17 SEP 2026 | A00222992 | Paris District | 10 | $500.00 | $500.00 | $584.49 | 7 | Catocon, Inc. | TxDOT |
| 16 SEP 2026 | A00223390 | Fort Worth District | 2 | $750.00 | $750.00 | $342.39 | 5 | Western Certified Arborists | TxDOT |
| 20 AUG 2026 | A00222783 | Fort Worth District | 10 | $380.00 | $359.44 | $295.00 | 8 | GV Landscape and Construction LLC | TxDOT |
| 12 AUG 2026 | A00222416 | Lufkin District | 2 | $50.00 | $450.00 | $420.00 | 5 | K & R Contractors | TxDOT |
| 12 AUG 2026 | A00222372 | Lufkin District | 2 | n/a | $450.00 | $425.00 | 3 | Ace Contractors, Inc. | TxDOT |
| 11 AUG 2026 | A00221492 | Childress District | 16 | $1,000.00 | $812.00 | $540.00 | 6 | Black Crown Construction LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.