H. V. Caver, Inc.: TxDOT bid record
H. V. Caver, Inc. submitted 52 bids on Texas DOT contracts in the data, from 19 FEB 2020 to 05 AUG 2026, and was the low bidder on 11 of them (21%). When it was not low, its total sat a median +22% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $19,991,135
- Latest bid
- 05 AUG 2026
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 7 | 3 | 43% |
| 2021 | 4 | 1 | 25% |
| 2022 | 7 | 1 | 14% |
| 2023 | 4 | 1 | 25% |
| 2024 | 9 | 2 | 22% |
| 2025 | 10 | 2 | 20% |
| 2026 | 11 | 1 | 9% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Atlanta District | 38 | 10 | 26% |
| Paris District | 8 | 0 | 0% |
| Tyler District | 3 | 1 | 33% |
| Fort Worth District | 1 | 0 | 0% |
| Dallas District | 1 | 0 | 0% |
| Lufkin District | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| TMA (stationary) | 505-7001 | DAY | 44 | 10 (23%) | $200.00 | $230.00 |
| Riprap (mow strip)(4 in) | 432-7013 | CY | 25 | 10 (40%) | $454.13 | $643.00 |
| RC pipe (CL III)(18 in) | 464-7003 | LF | 18 | 10 (56%) | $47.56 | $82.44 |
| Temporary sediment control fence (install) | 506-7039 | LF | 22 | 9 (41%) | $3.60 | $4.00 |
| Reflectorized pavement marker type II-A-A | 672-7004 | EACH | 14 | 9 (64%) | $5.00 | $5.00 |
| Metal W-beam guard fence (timber post) | 540-7001 | LF | 12 | 9 (75%) | $21.00 | $27.00 |
| Temporary sediment control fence (remove) | 506-7041 | LF | 22 | 8 (36%) | $0.80 | $1.00 |
| Guardrail end treatment (install) | 544-7001 | EACH | 15 | 8 (53%) | $2,950.00 | $3,245.00 |
| Tree removal (30" - 36" diameter) | 752-7009 | EACH | 9 | 8 (89%) | $121.00 | $500.00 |
| Tree removal (36" - 42" diameter) | 752-7010 | EACH | 9 | 8 (89%) | $121.00 | $500.00 |
| Barricades, signs and traffic handling | 502-7001 | MO | 36 | 7 (19%) | $5,000.00 | $5,000.00 |
| Set (type II) (18 in) (RCP) (6: 1) (P) | 467-7308 | EACH | 17 | 7 (41%) | $720.00 | $1,300.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| East Texas Bridge, Inc. | 19 | 3 of 19 |
| Longview Bridge and Road, LTD. | 15 | 4 of 15 |
| H. H. Howard & Sons, Inc. | 11 | 8 of 11 |
| Cross Plus Construction, LLC | 10 | 3 of 10 |
| Highway 19 Construction LLC | 9 | 2 of 9 |
| Catocon, Inc. | 9 | 5 of 9 |
| A. K. Gillis & Sons, LLC | 8 | 4 of 8 |
| FNH Construction, LLC | 7 | 0 of 7 |
| SCR Civil Construction, LLC | 7 | 1 of 7 |
| Gratiot Construction, LTD. | 7 | 3 of 7 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 05 AUG 2026 | A00196231 | Atlanta District | Rehabilitate Existing Roadway, SH 11 (0.1 Mi. E. of US 259 to Cass C/L) | 4 of 7 | $12,165,388 | +13% |
| 02 JUL 2026 | A00188996 | Dallas District | Rehabilitate Existing Roadway, FM 2933 (CR 335 to FM 545) | 4 of 6 | $12,685,374 | +15% |
| 08 APR 2026 | A00209284 | Paris District | Bridge Maintenance, Various (Various Locations to .) | 11 of 12 | $1,310,540 | +78% |
| 07 APR 2026 | A00192909 | Atlanta District | Hazard Elimination & Safety, SH 11 (US 59 to FM 130) | 3 of 10 | $1,979,078 | +10% |
| 18 MAR 2026 | A00218937 | Atlanta District | METAL BEAM GUARD FENCE REPAIR, US0059 (VARIOUS ROADWAYS to VARIOUS ROADWAYS) | 3 of 3 | $235,139 | +31% |
| 18 MAR 2026 | A00219505 | Atlanta District | CABLE BARRIER REPAIR, IH0030 (VARIOUS ROADWAYS to VARIOUS ROADWAYS) | 1 of 2 | $634,438 | Low, 16% under the second |
| 18 MAR 2026 | A00219506 | Atlanta District | CABLE BARRIER REPAIR, IH0020 (VARIOUS ROADWAYS to VARIOUS ROADWAYS) | 2 of 3 | $734,625 | +23% |
| 05 MAR 2026 | A00218351 | Atlanta District | Rehabilitate Existing Roadway, FM 699 (At Tributary of Eight Mile Creek to .) | 6 of 10 | $740,407 | +50% |
| 04 MAR 2026 | A00193135 | Lufkin District | Hazard Elimination & Safety, US 69 (FM 1270 to JASPER COUNTY LINE) | 2 of 7 | $1,736,467 | +15% |
| 05 FEB 2026 | A00192940 | Atlanta District | Hazard Elimination & Safety, SL 281 (Gregg CL to IH 20) | 3 of 9 | $1,694,681 | +5.0% |
| 04 FEB 2026 | A00193290 | Atlanta District | Install Illumination, SH 8 (at SH 11 to .) | 3 of 7 | $1,732,109 | +33% |
| 08 OCT 2025 | A00208073 | Atlanta District | Rehabilitate Existing Roadway, SH 49 (0.1 MI. E. OF SH 155 to Marion C/L) | 2 of 9 | $12,666,989 | +15% |
| 08 OCT 2025 | A00196501 | Atlanta District | Intersection Improvements With Right And/Or Left Turn Lanes, SH 49 (At FM 2348 to .) | 1 of 5 | $1,096,365 | Low, 2.0% under the second |
| 02 JUL 2025 | A00192923 | Atlanta District | Hazard Elimination & Safety, SH 43 (Rusk CL to Harrison CL) | 1 of 11 | $2,328,377 | Low, 13% under the second |
| 01 JUL 2025 | A00207270 | Atlanta District | Landscape Development, Various (Various locations to Various locations) | 4 of 4 | $143,839 | +10% |
| 03 APR 2025 | A00187424 | Paris District | Rehabilitate Existing Roadway, FM 21 (SH 37 to Titus County Line) | 5 of 9 | $11,301,762 | +24% |
| 20 FEB 2025 | A00212917 | Atlanta District | TREE REMOVAL, US0059 (VARIOUS ROADWAYS to VARIOUS ROADWAYS) | 5 of 9 | $229,069 | +25% |
| 20 FEB 2025 | A00212916 | Atlanta District | TREE REMOVAL, SH0049 (VARIOUS ROADWAYS to VARIOUS ROADWAYS) | 4 of 8 | $235,429 | +22% |
| 20 FEB 2025 | A00212915 | Atlanta District | TREE REMOVAL, US0059 (VARIOUS ROADWAYS to VARIOUS ROADWAYS) | 5 of 7 | $317,960 | +62% |
| 20 FEB 2025 | A00212913 | Atlanta District | TREE REMOVAL, US0259 (VARIOUS ROADWAYS to VARIOUS ROADWAYS) | 5 of 6 | $551,707 | +31% |
| 08 JAN 2025 | A00187241 | Paris District | Construct Pedestrian Infrastructure, Various (On NETT from East City Limits of Annona to Bowie County Line) | 3 of 6 | $2,398,975 | +16% |
| 04 DEC 2024 | A00196488 | Atlanta District | Widen Road - Add Shoulders, FM 994 (FM 1766 to SH 77) | 1 of 6 | $1,327,254 | Low, 16% under the second |
| 21 NOV 2024 | A00212301 | Paris District | TREE REMOVAL, US0082 (Various locations in to Red River County) | 3 of 5 | $328,977 | +49% |
| 20 NOV 2024 | A00211799 | Atlanta District | TREE REMOVAL, IH0030 (IH0030 to IH0030) | 3 of 5 | $239,271 | +28% |
| 05 JUN 2024 | 06243021 | Atlanta District | FM 2796 Widen road - add shoulders from SH 155 to FM 593 | 6 of 6 | $7,259,818 | +42% |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.