TxDOT contract A00209284 bid tabulation
Bridge Maintenance, Various (Various Locations to .). Let by Texas DOT on April 8, 2026, Lamar, Paris District. 12 bids received; low bid $734,734 by The Truesdell Corporation, -11% against the engineer's estimate of $823,730.
- Owner
- Texas DOT
- Letting
- 08 APR 2026
- Pay items
- 21
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | The Truesdell Corporation | $734,734 | Low | -11% |
| 2 | Jackson Excavation, LLC | $778,173 | +6.0% | -6.0% |
| 3 | Road Doctors LLC | $781,028 | +6.0% | -5.0% |
| 4 | Garret Shields Infrastructure | $884,940 | +20% | +7.0% |
| 5 | Built Right Construction of Oklahoma, LLC | $944,325 | +29% | +15% |
| 6 | THK Construction LLC | $960,659 | +31% | +17% |
| 7 | Icos Management, LLC | $984,245 | +34% | +19% |
| 8 | Pathfield Investments LLC | $1,041,500 | +42% | +26% |
| 9 | Tucan Contracting, LLC | $1,190,575 | +62% | +45% |
| 10 | Shalom Services Corporation | $1,198,550 | +63% | +46% |
| 11 | H. V. Caver, Inc. | $1,310,540 | +78% | +59% |
| 12 | Premier Contractors LLC | $1,576,067 | +115% | +91% |
Engineer's estimate: $823,730.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. The Truesdell Corporation | 2. Jackson Excavation, LLC | 3. Road Doctors LLC | 4. Garret Shields Infrastructure | 5. Built Right Construction of Oklahoma, LLC | 6. THK Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 8 | $500.00 | $2,000.00 | $1,000.00 | $3,000.00 | $500.00 | $1,000.00 | $1,200.00 |
| 2 | Excavation (channel) (110-7002) | CY | 557 | $20.00 | $30.00 | $20.00 | $60.00 | $40.00 | $25.00 | $18.00 |
| 3 | Excavation (special) (110-7003) | CY | 185 | $30.00 | $30.00 | $12.00 | $150.00 | $40.00 | $25.00 | $18.00 |
| 4 | Embankment (vehicle)(OC)(type B) (132-7015) | CY | 467 | $40.00 | $50.00 | $20.00 | $100.00 | $30.00 | $30.00 | $18.00 |
| 5 | Embankment (vehicle)(OC)(type D) (132-7019) | CY | 30 | $45.00 | $50.00 | $25.00 | $100.00 | $30.00 | $10.00 | $18.00 |
| 6 | Backfill (type A or B)(vehicle) (134-7009) | CY | 20 | $50.00 | $75.00 | $6.00 | $40.00 | $30.00 | $100.00 | $18.00 |
| 7 | Block sodding (162-7002) | SY | 7 | $10.00 | $200.00 | $7.00 | $20.00 | $10.00 | $20.00 | $20.00 |
| 8 | Flowable backfill (401-7001) | CY | 43 | $300.00 | $750.00 | $300.00 | $300.00 | $300.00 | $300.00 | $400.00 |
| 9 | Riprap (stone protection)(12 in) (432-7041) | CY | 145 | $150.00 | $135.00 | $150.00 | $110.00 | $150.00 | $150.00 | $155.00 |
| 10 | Riprap (stone protection)(18 in) (432-7043) | CY | 948 | $150.00 | $120.00 | $140.00 | $110.00 | $140.00 | $150.00 | $155.00 |
| 11 | Riprap (stone protection)(24 in) (432-7045) | CY | 3,649 | $130.00 | $110.00 | $140.00 | $100.00 | $140.00 | $150.00 | $155.00 |
| 12 | Gabions (3' X 3')(galvanized) (459-7010) | CY | 115 | $300.00 | $300.00 | $400.00 | $100.00 | $300.00 | $250.00 | $225.00 |
| 13 | Clean existing culverts (480-7001) | EACH | 2 | $800.00 | $5,000.00 | $500.00 | $2,500.00 | $1,000.00 | $7,500.00 | $10,000 |
| 14 | Removing structure (pipe) (496-7007) | LF | 16 | $25.00 | $500.00 | $7.00 | $30.00 | $10.00 | $50.00 | $5.00 |
| 15 | Mobilization (500-7001) | LS | 1 | $60,000 | $26,166 | $1,000.00 | $70,000 | $50,000 | $52,000 | $80,000 |
| 16 | Barricades, signs and traffic handling (502-7001) | MO | 7 | $2,000.00 | $1.00 | $1,500.00 | $3,000.00 | $5,000.00 | $7,000.00 | $3,633.15 |
| 17 | Portable changeable message sign (503-7002) | EACH | 2 | $200.00 | $3,500.00 | $1.00 | $1.00 | $1,000.00 | $3,500.00 | $5,000.00 |
| 18 | TMA (stationary) (505-7001) | DAY | 6 | $200.00 | $1.00 | $10.00 | $1.00 | $300.00 | $300.00 | $200.00 |
| 19 | TMA (mobile operation) (505-7002) | HR | 65 | $100.00 | $1.00 | $10.00 | $100.00 | $50.00 | $100.00 | $10.00 |
| 20 | Driftwood removal (735-7060) | CY | 177 | $60.00 | $65.00 | $50.00 | $100.00 | $120.00 | $75.00 | $30.00 |
| 21 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 15 | $100.00 | $300.00 | $10.00 | $1,000.00 | $500.00 | $200.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.