TxDOT contract A00192940 bid tabulation
Hazard Elimination & Safety, SL 281 (Gregg CL to IH 20). Let by Texas DOT on February 5, 2026, Harrison, Atlanta District. 9 bids received; low bid $1,619,890 by Gratiot Construction, LTD., +0.3% against the engineer's estimate of $1,614,403.
- Owner
- Texas DOT
- Letting
- 05 FEB 2026
- Pay items
- 37
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Gratiot Construction, LTD. | $1,619,890 | Low | 0.0% |
| 2 | Massana Construction Inc. | $1,649,288 | +2.0% | +2.0% |
| 3 | H. V. Caver, Inc. | $1,694,681 | +5.0% | +5.0% |
| 4 | Scout 5 Construction LLC | $1,798,274 | +11% | +11% |
| 5 | W. M. Miller Construction Company, Inc. | $1,807,260 | +12% | +12% |
| 6 | Garret Shields Infrastructure | $1,843,720 | +14% | +14% |
| 7 | Roadway Specialties, Inc. | $1,923,296 | +19% | +19% |
| 8 | SCR Civil Construction, LLC | $1,991,745 | +23% | +23% |
| 9 | East Texas Bridge, Inc. | $2,274,346 | +40% | +41% |
Engineer's estimate: $1,614,403.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Gratiot Construction, LTD. | 2. Massana Construction Inc. | 3. H. V. Caver, Inc. | 4. Scout 5 Construction LLC | 5. W. M. Miller Construction Company, Inc. | 6. Garret Shields Infrastructure |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 233 | $1,500.00 | $1,000.00 | $1,700.00 | $1,775.00 | $1,870.00 | $1,000.00 | $1,400.00 |
| 2 | Removing concrete (mowstrip) (104-7003) | SY | 515 | $15.00 | $20.00 | $25.00 | $24.50 | $22.53 | $16.56 | $50.00 |
| 3 | Embankment (vehicle)(OC)(type C) (132-7017) | CY | 34 | $37.00 | $160.00 | $105.00 | $50.00 | $8.80 | $140.00 | $30.00 |
| 4 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 41,882 | $0.10 | $0.10 | $0.01 | $0.11 | $0.23 | $0.01 | $0.12 |
| 5 | Bond fiber MTRX seed (permanent)(rural)(sand) (164-7073) | SY | 83,763 | $0.56 | $0.25 | $0.01 | $0.53 | $0.61 | $0.01 | $0.60 |
| 6 | Vegetative watering (168-7001) | TGL | 1,340 | $8.00 | $10.00 | $0.01 | $0.01 | $15.00 | $0.01 | $10.00 |
| 7 | Riprap (concrete)(4 in) (432-7001) | CY | 955 | $375.00 | $505.00 | $375.00 | $423.16 | $550.00 | $700.00 | $600.00 |
| 8 | Riprap (mow strip)(4 in) (432-7013) | CY | 101 | $375.00 | $725.00 | $395.00 | $577.85 | $500.00 | $700.00 | $600.00 |
| 9 | Mobilization (500-7001) | LS | 1 | $145,000 | $165,000 | $233,295 | $128,300 | $75,000 | $105,000 | $100,000 |
| 10 | Barricades, signs and traffic handling (502-7001) | MO | 7 | $4,000.00 | $7,500.00 | $5,500.00 | $3,500.00 | $2,170.54 | $6,215.00 | $5,000.00 |
| 11 | TMA (stationary) (505-7001) | DAY | 200 | $160.00 | $50.00 | $65.00 | $100.00 | $1.00 | $402.00 | $300.00 |
| 12 | Rock filter dams (install) (type 2) (506-7002) | LF | 100 | $50.00 | $40.00 | $40.00 | $23.00 | $53.90 | $50.00 | $20.00 |
| 13 | Rock filter dams (remove) (506-7011) | LF | 100 | $13.00 | $8.00 | $8.00 | $5.00 | $19.80 | $10.00 | $10.00 |
| 14 | Temporary sediment control fence (install) (506-7039) | LF | 1,000 | $3.60 | $4.00 | $4.00 | $2.20 | $4.29 | $27.00 | $4.00 |
| 15 | Temporary sediment control fence (remove) (506-7041) | LF | 1,000 | $0.80 | $0.90 | $1.00 | $0.50 | $0.66 | $1.00 | $1.00 |
| 16 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,400 | $25.00 | $25.00 | $20.00 | $24.22 | $25.30 | $23.00 | $30.00 |
| 17 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 10 | $1,900.00 | $1,800.00 | $1,475.00 | $1,488.57 | $1,760.00 | $1,700.00 | $1,500.00 |
| 18 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,300.00 | $1,500.00 | $1,075.00 | $1,084.89 | $1,210.00 | $1,350.00 | $1,000.00 |
| 19 | Remove metal beam guard fence (542-7001) | LF | 1,325 | $2.00 | $3.00 | $2.00 | $2.02 | $1.10 | $2.50 | $1.00 |
| 20 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 10 | $100.00 | $220.00 | $200.00 | $201.84 | $165.00 | $200.00 | $500.00 |
| 21 | Cable barrier system (install)(TL-4) (543-7002) | LF | 24,943 | $12.00 | $10.50 | $12.00 | $11.83 | $13.64 | $10.72 | $12.00 |
| 22 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 40 | $2,500.00 | $2,240.00 | $2,500.00 | $2,869.70 | $1,694.00 | $2,280.38 | $2,500.00 |
| 23 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $2,900.00 | $3,000.00 | $2,870.00 | $2,896.40 | $3,520.00 | $2,800.00 | $3,500.00 |
| 24 | Guardrail end treatment (remove) (544-7003) | EACH | 10 | $185.00 | $250.00 | $200.00 | $201.84 | $165.00 | $215.00 | $100.00 |
| 25 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 10 | $650.00 | $800.00 | $515.00 | $672.27 | $756.80 | $920.00 | $800.00 |
| 26 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 2 | $500.00 | $950.00 | $600.00 | $775.18 | $863.50 | $1,000.00 | $800.00 |
| 27 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 33 | $1,200.00 | $1,100.00 | $700.00 | $881.86 | $797.50 | $1,220.00 | $800.00 |
| 28 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 2 | $850.00 | $1,000.00 | $700.00 | $872.33 | $946.00 | $185.00 | $800.00 |
| 29 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 5 | $1,100.00 | $1,000.00 | $700.00 | $880.01 | $990.00 | $1,205.00 | $800.00 |
| 30 | Install small roadside sign support and assembly TYS80(2)SA(P) (644-7048) | EACH | 1 | $1,000.00 | $1,500.00 | $1,200.00 | $1,296.21 | $1,650.00 | $1,925.00 | $800.00 |
| 31 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 68 | $400.00 | $400.00 | $275.00 | $371.33 | $550.00 | $535.00 | $500.00 |
| 32 | Install small roadside sign support and assembly tytwt(1)WS(T) (644-7058) | EACH | 1 | $400.00 | $450.00 | $400.00 | $472.58 | $616.00 | $650.00 | $500.00 |
| 33 | Remove SM RD SN sup&AM (644-7073) | EACH | 134 | $100.00 | $110.00 | $90.00 | $100.00 | $77.00 | $125.00 | $100.00 |
| 34 | Install delineator assembly (D-SW)SZ 1(WFLX)GF2 (658-7001) | EACH | 21 | $25.00 | $35.00 | $42.00 | $42.39 | $44.00 | $30.00 | $25.00 |
| 35 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 12 | $22.00 | $50.00 | $32.00 | $32.29 | $41.80 | $100.00 | $25.00 |
| 36 | Install delineator assembly (D-SY)SZ 1(yflx)GF2 (658-7021) | EACH | 16 | $28.00 | $45.00 | $42.00 | $42.39 | $44.00 | $40.00 | $25.00 |
| 37 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 12 | $21.00 | $50.00 | $32.00 | $32.29 | $38.50 | $100.00 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 5, 2026. Compiled by Mirage Metrics.