VDOT's 2002 to 2021 workbooks list only the three lowest bids on each contract, so a firm's bids that ranked fourth or lower in those years are missing: bid counts are understated and win rates overstated for those years.
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2019 | 2 | 2 | 100% |
| 2020 | 1 | 0 | 0% |
| 2021 | 7 | 2 | 29% |
| 2025 | 8 | 2 | 25% |
| 2026 | 8 | 3 | 38% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Fredericksburg | 6 | 3 | 50% |
| Bristol | 4 | 1 | 25% |
| Northern Virginia | 4 | 2 | 50% |
| Staunton | 3 | 1 | 33% |
| Lynchburg | 3 | 1 | 33% |
| Culpeper | 3 | 0 | 0% |
| Richmond | 2 | 0 | 0% |
| Salem | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Type A PVMT line MRKG 4" | 704SD20-0001 | LF | 17 | 7 (41%) | $0.07 | $0.24 |
| Type A PVMT line MRKG 6" | 704SD20-0002 | LF | 13 | 5 (38%) | $0.11 | $0.27 |
| Type A PVMT line MRKG 8" | 704SD20-0003 | LF | 13 | 5 (38%) | $0.17 | $0.36 |
| NS pave. message marking "stop" TY. B, CL. I | 704SX20-0005 | EACH | 9 | 4 (44%) | $225.00 | $487.88 |
| Type A PVMT line MRKG 12" | 704SD20-0004 | LF | 5 | 3 (60%) | $0.23 | $2.10 |
| Flagger service | 512SD20-0027 | HR | 7 | 2 (29%) | $60.00 | $20.00 |
| Inlaid pavement marker asphalt | 704SD20-0032 | EACH | 5 | 2 (40%) | $28.00 | $41.09 |
| Type B class I PVMT line MRKG 6" | 704SD20-0007 | LF | 5 | 2 (40%) | $0.63 | $1.36 |
| Truck mounted attenuator | 512SD20-0023 | HR | 6 | 1 (17%) | $75.00 | $20.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| A Annandale, Inc. | 8 | 6 of 8 |
| Oglesby Construction, Inc. | 7 | 3 of 7 |
| American Road Markings, L.L.C. | 6 | 3 of 6 |
| Paynes Parking Designs, Inc. | 6 | 2 of 6 |
| Central Seal Company | 5 | 2 of 5 |
| The Aero-Mark Company LLC | 5 | 1 of 5 |
| Ces Consulting, LLC | 3 | 1 of 3 |
| Richardson-Wayland-Ferreira, LLC | 3 | 0 of 3 |
| Dura Mark Inc. | 3 | 1 of 3 |
| Creative Design Concepts, Inc. | 2 | 0 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 28 OCT 2026 | C0000125378N01 | Staunton | Safety improvements - roadway signage installations | 2 of 6 | $837,680 | +24% |
| 28 OCT 2026 | C0000125379N01 | Staunton | Rumble strips, pavement markings/markers | 1 of 3 | $2,115,045 | Low, 4.0% under the second |
| 26 AUG 2026 | C0000128880N01 | Bristol | On-call pavement marker replacement | 2 of 2 | $324,052 | +59% |
| 22 JUL 2026 | C0000128505N01 | Fredericksburg | On-call pavement marking | 2 of 3 | $1,216,480 | +12% |
| 22 JUL 2026 | C0000127491N01 | Lynchburg | Rumble strips & pims installation | 3 of 3 | $2,817,685 | +48% |
| 22 APR 2026 | C0000125595N01 | Salem | Two lane rural roads: sign installation | 1 of 4 | $1,017,452 | Low, 49% under the second |
| 25 FEB 2026 | C0000128434N01 | Culpeper | On-call pavement marking | 2 of 5 | $1,515,724 | +5.0% |
| 04 FEB 2026 | C0000126388N01 | Northern Virginia | On-call pavement markings | 1 of 2 | $2,774,578 | Low, 28% under the second |
| 17 DEC 2025 | C0000124830N01 | Bristol | Pavement marking and rumble strip installation | 1 of 4 | $1,719,307 | Low, 8.0% under the second |
| 17 DEC 2025 | C0000126849N01 | Lynchburg | Fy26 secondary pavement marking retrace | 1 of 2 | $842,996 | Low, 18% under the second |
| 17 DEC 2025 | C0000127593N01 | Culpeper | On-call pavement marking | 2 of 2 | $1,579,402 | +1.0% |
| 19 NOV 2025 | C0000124829N01 | Bristol | Signing and pavement marking improvements | 4 of 4 | $2,486,679 | +39% |
| 19 NOV 2025 | C0000127995N01 | Fredericksburg | Pavement markings | 3 of 4 | $1,175,887 | +49% |
| 19 NOV 2025 | C0000127996N01 | Richmond | Pavement markings | 3 of 4 | $1,062,836 | +24% |
| 19 NOV 2025 | C0000127997N01 | Richmond | Pavement markings | 2 of 3 | $1,849,584 | +50% |
| 22 OCT 2025 | C0000127217N01 | Staunton | Safety improvements - sign installation | 2 of 6 | $1,809,358 | +1.0% |
| 17 NOV 2021 | C0000118535N01 | Culpeper | On call sprpm / pim lens replacement & removal | 2 of 2 | $384,337 | +62% |
| 23 JUN 2021 | C0000118601N01 | Northern Virginia | On-call pavement marking replacement | 3 of 3 | $862,456 | +31% |
| 28 APR 2021 | 0000118009N01 | Fredericksburg | On-call pavement markings -northern region | 1 of 2 | $508,569 | Low, 72% under the second |
| 28 APR 2021 | C0000118007N01 | Fredericksburg | On-call pavement markings - interstate-limited access | 1 of 2 | $759,867 | Low, 26% under the second |
| 28 APR 2021 | C0000118008N01 | Fredericksburg | On-call pavement markings -southern region | 2 of 3 | $887,682 | +16% |
| 24 MAR 2021 | C0000118136N01 | Northern Virginia | Pavement marking improvements | 2 of 3 | $1,120,975 | +18% |
| 24 FEB 2021 | C0000118031N01 | Lynchburg | Pavement marking retrace | 2 of 3 | $534,675 | 0.0% |
| 24 JUN 2020 | C0000116641N01 | Bristol | On-call pavement marking and marker replacement | 3 of 3 | $1,398,742 | +19% |
| 13 NOV 2019 | C0000115002N01 | Fredericksburg | On call-pavement markings | 1 of 3 | $564,526 | Low, 16% under the second |
How this record was read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Every bid counted here matched its published total to within one dollar; VDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.