End post support angles GR-8, VDOT 505SP20-0034

Low bidders on VDOT contracts carried a median of $25.00 per EACH for this item, from 26 MAR 2002 to 25 MAR 2026, across 46 low bids. Half of all 127 bids fell between $19.50 and $50.00.

Owner
Virginia DOT
Item
505SP20-0034
Unit
EACH
Data through
28 OCT 2026

VDOT prints this item as “END POST SUPPORT ANGLES GR-8”.

VDOT has bid this work under more than one code: 17383 on lettings from 26 MAR 2002 to 18 NOV 2020 (150 bids); 505SP20-0034 on lettings from 22 OCT 2025 to 25 MAR 2026 (4 bids). They are combined here into one trend.

$25.00Low bidder's median, per EACH
$25.00Median of all bids, per EACH
63Contracts in the window

By year of letting

End post support angles GR-8, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200255$25.0012$25.00
200466$24.3817$25.00
200555$25.007$20.00
200622$20.504$23.00
200711$10.003$20.00
200899$25.0021$25.00
200911$25.003$25.00
201011$40.001$40.00
201143$10.006$17.50
201221$20.005$50.00
201355$25.0011$25.00
201462$17.759$50.00
201520n/a3$10.50
201611$4.003$50.00
201711$25.003$50.00
201820n/a3$50.00
201962$6.0010$10.00
202021$60.004$175.00
202510n/a1$200.00
202610n/a1$100.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Staunton19$25.0056$25.00
Salem14$25.0037$25.00
Lynchburg3$10.0012$25.00
Northern Virginia3$25.0011$50.00
Culpeper4$10.006$10.00
End post support angles GR-8, VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 111$25.00
1 to 212$25.00
2 to 211$20.00
2 to 1012$23.00
End post support angles GR-8, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Makco, Incorporated3722 (59%)
L. S. Lee, Inc.158 (53%)
Penn Line Service, Inc.127 (58%)
Webster & Webster, Inc.55 (100%)
Lanford Brothers Company, Incorporated62 (33%)
Nickelston Industries, Inc.121 (8%)
End post support angles GR-8, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
25 MAR 2026C0000128504N01Northern Virginia2n/a$100.001L. S. Lee, Inc.VDOT
22 OCT 2025C0000127926S01Staunton1n/a$200.001Makco, IncorporatedVDOT
18 NOV 2020C0000117874S01Staunton1n/a$390.182Makco, IncorporatedVDOT
22 JUL 2020C0000116644N01Northern Virginia2$60.00$80.002Curtis Contracting, Inc.VDOT
23 OCT 2019C0000116075N01Lynchburg2n/a$80.001Makco, IncorporatedVDOT
22 MAY 2019M000114816N01Staunton1n/a$85.001Makco, IncorporatedVDOT
24 APR 2019C0000114413N01Salem2$6.00$10.003Webster & Webster, Inc.VDOT
24 APR 2019C0000114414N01Salem2n/a$6.001Makco, IncorporatedVDOT
24 APR 2019C0000114415N01Salem2$6.00$10.003Webster & Webster, Inc.VDOT
24 APR 2019C0000114416N01Salem2n/a$6.001Makco, IncorporatedVDOT
25 APR 2018C0000112251N01Lynchburg5n/a$18.001Makco, IncorporatedVDOT
25 APR 2018M000112711N01Staunton1n/a$250.002Makco, IncorporatedVDOT
21 JUN 2017CM616GR0110411Northern Virginia2$25.00$50.003L. S. Lee, Inc.VDOT
27 APR 2016C000108148N01Staunton1$4.00$50.003Makco, IncorporatedVDOT
22 APR 2015C0000106705N01Lynchburg5n/a$100.001Makco, IncorporatedVDOT
Latest VDOT contracts carrying End post support angles GR-8

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy