Purcell P & C, LLC DBA Purcell: WSDOT bid record
Purcell P & C, LLC DBA Purcell submitted 10 bids on Washington State DOT contracts in the data, from 08 MAR 2006 to 27 APR 2022, and was the low bidder on 5 of them (50%). When it was not low, its total sat a median +9.0% above the low bid.
- Owner
- Washington State DOT
- Low bid volume
- $9,372,793
- Latest bid
- 27 APR 2022
- Data through
- 07 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2006 | 1 | 1 | 100% |
| 2009 | 1 | 1 | 100% |
| 2013 | 1 | 0 | 0% |
| 2014 | 1 | 1 | 100% |
| 2015 | 1 | 1 | 100% |
| 2017 | 1 | 0 | 0% |
| 2018 | 1 | 1 | 100% |
| 2021 | 1 | 0 | 0% |
| 2022 | 2 | 0 | 0% |
By region
| Region | Bids | Low bids | Win rate |
|---|---|---|---|
| OR region | 4 | 1 | 25% |
| NWR region | 2 | 2 | 100% |
| Region 9 | 2 | 1 | 50% |
| NCR region | 1 | 1 | 100% |
| SWR region | 1 | 0 | 0% |
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Abhe & Svoboda, Inc. | 7 | 0 of 7 |
| Long Painting Company | 6 | 0 of 6 |
| S & K Painting, Inc. | 4 | 0 of 4 |
| Southern Road & Bridge, LLC | 4 | 1 of 4 |
| F.D. Thomas, Inc. | 4 | 0 of 4 |
| Dunkin & Bush, Inc. | 3 | 0 of 3 |
| Certified Coatings Company | 3 | 0 of 3 |
| Intech Contracting LLC | 2 | 1 of 2 |
| Vimas Painting Company, Inc. | 2 | 0 of 2 |
| Geronimo Painting Co. | 2 | 0 of 2 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 27 APR 2022 | 009805 | SWR region | I- 5 dike access w br mp 22.7 & bnrr br mp 26 painting | 2 of 7 | $3,432,264 | +9.0% |
| 20 JAN 2022 | 009761 | Region 9 | Sr160 southworth ferry terminal painting preservation | 2 of 5 | $416,504 | +6.0% |
| 24 FEB 2021 | 009648 | OR region | Us 101 hoquiam river - riverside bridge bridge painting - approach spans | 2 of 9 | $489,004 | +7.0% |
| 18 APR 2018 | 009255 | Region 9 | Sr104 edmonds ferry terminal painting preservation | 1 of 3 | $552,904 | Low, 35% under the second |
| 12 APR 2017 | 009064 | OR region | Us 101 sol duc river bridges bridge painting | 2 of 7 | $2,576,743 | +12% |
| 22 JAN 2015 | 008703 | NCR region | I-90 columbia river vantage bridge painting 14b010 | 1 of 7 | $4,615,068 | Low, 45% under the second |
| 02 APR 2014 | 008594 | NWR region | I-5 nooksack river bridges painting 14a005 | 1 of 5 | $3,213,054 | Low, 5.0% under the second |
| 20 MAR 2013 | 008435 | OR region | I-5 nisqually river bridges bridge painting | 2 of 7 | $5,831,793 | +17% |
| 25 MAR 2009 | 007700 | OR region | I-5 and us 12 capitol blvd. bridge & black river bridge - painting | 1 of 6 | $794,963 | Low, 53% under the second |
| 08 MAR 2006 | 007105 | NWR region | I-90 east channel bridge 90/40n&s bridge painting | 1 of 6 | $196,804 | Low, 31% under the second |
How this record was read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Every bid counted here matched its published total to within one dollar; WSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.