WSDOT contract XE3760 bid tabulation
I-90 Eb 3 Miles E Of North Bend - Emergency Seeding And Erosion Control. Let by Washington State DOT on August 12, 2026, King, SCR region. 5 bids received; low bid $233,938 by Scarsella Bros., Inc., -5.2% against the engineer's estimate of $246,879.
- Owner
- Washington State DOT
- Letting
- 12 AUG 2026
- Pay items
- 14
- Data through
- 07 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scarsella Bros., Inc. | $233,938 | Low | -5.0% |
| 2 | C & R Tractor & Landscaping, Inc. | $252,408 | +8.0% | +2.0% |
| 3 | A-1 Landscaping and Construction | $345,724 | +48% | +40% |
| 4 | N.W. Construction General Contracting, Inc. | $384,904 | +65% | +56% |
| 5 | Ceccanti, Inc. | $496,084 | +112% | +101% |
Engineer's estimate: $246,879.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Scarsella Bros., Inc. | 2. C & R Tractor & Landscaping, Inc. | 3. A-1 Landscaping and Construction | 4. N.W. Construction General Contracting, Inc. | 5. Ceccanti, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Mobilization | LS | 1 | $22,500 | $23,000 | $15,000 | $43,200 | $30,000 | $292,000 |
| 2 | Coir log | LF | 265 | $25.00 | $20.50 | $15.00 | $66.00 | $40.00 | $22.00 |
| 3 | Erosion/water pollution control | EST | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 4 | Seeding, fertilizing, and mulching | ACRE | 0.50 | $50,000 | $12,000 | $10,525 | $12,500 | $10,000 | $8,500.00 |
| 5 | Seeding and fertilizing by hand | SY | 2,400 | $10.00 | $2.50 | $0.59 | $6.00 | $2.00 | $3.00 |
| 6 | Topsoil type A | ACRE | 0.50 | $150,000 | $245,000 | $150,000 | $129,000 | $350,000 | $120,000 |
| 7 | Portable changeable message sign | HR | 150 | $25.00 | $0.01 | $45.00 | $22.00 | $30.00 | $30.00 |
| 8 | Project temporary traffic control | LS | 1 | $30,000 | $12,500 | $86,000 | $132,000 | $95,000 | $63,800 |
| 9 | Work zone safety contingency | EST | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 10 | Project partnering | CALC | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 11 | Roadside cleanup | EST | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 12 | Reimbursement for third party damage | EST | 1 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 13 | Minor change | CALC | 1 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 |
| 14 | Spill prevention, control, and countermeasures plan | LS | 1 | $2,000.00 | $500.00 | $1,000.00 | $6,580.00 | $2,000.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WSDOT's tabulation for this contract. WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
Every contract let that day: WSDOT letting of August 12, 2026. Compiled by Mirage Metrics.