WisDOT contract 20250114028 bid tabulation

CTH J - CTH Y; Plover River Bridge, B-37-0468 (CTH C, Marathon County CTH J - CTH Y). Let by Wisconsin DOT on January 14, 2025, Marathon. 6 bids received; low bid $846,890 by Larson Construction Co., Inc..

Owner
Wisconsin DOT
Letting
14 JAN 2025
Pay items
79
Data through
10 NOV 2026

5 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Larson Construction Co., Inc.$846,890Low
3Sheet Piling Services LLC$916,595+8.0%
4Janke General Contractors, Inc.$921,142+9.0%
5Lunda Construction Company$982,481+16%
6Radtke Contractors Inc.$1,027,017+21%
WisDOT contract 20250114028: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Larson Construction Co., Inc.2. Sheet Piling Services LLC3. Janke General Contractors, Inc.4. Lunda Construction Company5. Radtke Contractors Inc.
1Removing small pipe culverts (203.0100)EACH1$500.00$500.00$885.00$500.00$500.00
2Abatement of asbestos containing material (structure) 01. B-37-016 (203.0211.S)EACH1$4,625.80$4,580.00$4,580.00$5,000.00$4,580.00
3Removing structure over waterway remove debris (structure) 01. B-37- 016 (203.0250)EACH1$58,419$85,000$45,825$242,500$118,142
4Removing asphaltic surface (204.0110)SY653$4.65$4.65$9.00$4.65$4.65
5Excavation common (205.0100)CY641$9.58$9.58$23.00$9.58$9.58
6Excavation for structures bridges (structure) 01. B-37-468 (206.1001)EACH1$19,241$55,000$41,400$12,500$24,296
7Cofferdams (structure) 01. B-37-468 (206.5001)EACH1$39,140$40,000$38,600$20,000$39,605
8Backfill structure type A (210.1500)TON274$23.60$23.60$31.00$23.60$53.13
9Prepare foundation for asphaltic paving (project) 01. 6653-00-72 (211.0101)EACH1$1,500.00$1,500.00$2,345.00$1,500.00$1,500.00
10Finishing roadway (project) 01. 6653-00-72 (213.0100)EACH1$500.00$500.00$200.00$500.00$500.00
11Base aggregate dense 3/4-inch (305.0110)TON94$23.48$23.48$29.00$23.48$23.48
12Base aggregate dense 1 1/4-inch (305.0120)TON883$20.73$20.73$20.00$20.73$20.73
13Concrete pavement 6-inch (415.0060)SY29$105.00$105.00$190.00$105.00$105.00
14Concrete pavement approach slab (415.0410)SY114$320.00$320.00$255.00$320.00$320.00
15Tack coat (455.0605)GAL96$8.14$8.14$8.14$8.14$8.14
16Asphaltic surface (465.0105)TON306$142.90$142.90$142.90$142.90$142.90
17Concrete masonry bridges (502.0100)CY334.80$595.00$810.00$795.00$550.00$746.91
18Protective surface treatment (502.3200)SY316$3.50$5.00$6.00$3.00$3.60
19Pigmented surface sealer (502.3210)SY142$6.00$5.00$8.00$2.00$8.42
20Underwater substructure inspection (structure) 01. B-37-468 (502.9000.S)EACH1$4,000.00$5,100.00$1,000.00$7,500.00$5,100.00
21Bar steel reinforcement HS structures (505.0400)LB5,750$1.25$1.15$1.85$0.96$1.28
22Bar steel reinforcement HS coated structures (505.0600)LB64,800$1.25$1.20$1.43$1.10$1.16
23Rubberized membrane waterproofing (516.0500)SY40$24.00$30.00$35.00$25.00$74.42
24Culvert pipe reinforced concrete horizontal elliptical class HE-III 14X23-inch (522.2314)LF24$192.50$192.50$200.00$192.50$192.50
25Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 14X23-inch (522.2614)EACH2$1,425.00$1,425.00$1,600.00$1,425.00$1,425.00
26Pile points (550.0500)EACH22$175.00$200.00$190.00$150.00$125.00
27Piling steel HP 10-inch X 42 LB (550.1100)LF1,540$50.00$40.00$53.50$40.95$34.43
28Concrete curb & gutter 4-inch sloped 30-inch type TBT (601.0584)LF101$62.00$62.00$86.50$62.00$62.00
29Concrete surface drains (602.3010)CY4$1,200.00$1,200.00$1,450.00$1,200.00$1,200.00
30Riprap medium (606.0200)CY6$105.30$105.30$176.00$105.30$105.30
31Riprap heavy (606.0300)CY260$78.99$86.00$80.00$78.99$88.28
32Pipe underdrain wrapped 6-inch (612.0406)LF120$6.50$6.50$15.00$6.50$4.20
33Anchor assemblies for steel plate beam guard (614.0150)EACH4$200.00$250.00$500.00$175.00$225.08
34MGS guardrail 3 (614.2300)LF175$28.50$28.50$26.00$28.50$28.50
35MGS thrie beam transition (614.2500)LF157.60$95.00$95.00$92.00$95.00$95.00
36MGS guardrail terminal eat (614.2610)EACH4$3,600.00$3,600.00$4,142.88$3,600.00$3,600.00
37Maintenance and repair of haul roads (project) 01. 6653-00-72 (618.0100)EACH1$1.00$0.01$200.00$0.01$500.00
38Mobilization (619.1000)EACH1$74,068$28,230$40,000$83,386$158,250
39Water (624.0100)MGAL15$20.00$20.00$19.99$20.00$20.00
40Topsoil (625.0100)SY1,600$2.92$2.92$5.25$2.92$2.92
41Silt fence (628.1504)LF1,250$2.50$2.50$2.25$2.50$2.50
42Silt fence maintenance (628.1520)LF1,250$0.10$0.10$0.03$0.10$0.10
43Mobilizations erosion control (628.1905)EACH5$200.00$200.00$173.00$200.00$200.00
44Mobilizations emergency erosion control (628.1910)EACH3$200.00$200.00$203.00$200.00$200.00
45Erosion mat urban class I type A (628.2006)SY1,600$1.90$1.90$2.50$1.90$1.90
46Turbidity barriers (628.6005)SY451$48.50$48.50$30.00$48.50$48.50
47Rock bags (628.7570)EACH85$12.50$12.50$12.00$12.50$12.50
48Fertilizer type B (629.0210)CWT1$100.00$100.00$95.00$100.00$100.00
49Seeding mixture no. 20 (630.0120)LB43$6.00$6.00$12.00$6.00$6.00
50Seeding temporary (630.0200)LB43$3.00$3.00$8.00$3.00$3.00
51Seed water (630.0500)MGAL36$20.00$20.00$20.00$20.00$20.00
52Posts wood 4X6-inch X 14-FT (634.0614)EACH4$120.00$120.00$95.00$120.00$120.00
53Posts wood 4X6-inch X 16-FT (634.0616)EACH2$125.00$125.00$100.00$125.00$125.00
54Signs type II reflective F (637.2230)SF12$30.00$30.00$50.00$30.00$30.00
55Moving signs type II (638.2102)EACH2$15.00$15.00$150.00$15.00$15.00
56Removing signs type II (638.2602)EACH6$10.00$10.00$50.00$10.00$10.00
57Removing small sign supports (638.3000)EACH6$10.00$10.00$50.00$10.00$10.00
58Field office type B (642.5001)EACH1$3,300.00$1,000.00$1,000.00$3,000.00$2,142.17
59Traffic control barricades type III (643.0420)DAY1,566$0.30$0.30$0.30$1.00$0.30
60Traffic control warning lights type A (643.0705)DAY2,436$0.10$0.10$0.10$0.15$0.10
61Traffic control signs (643.0900)DAY21,896$0.28$0.28$0.28$0.25$0.28
62Traffic control covering signs type I (643.0910)EACH3$40.00$40.00$40.00$200.00$40.00
63Traffic control (643.5000)EACH1$1,915.00$1,915.00$4,371.82$5,700.00$1,915.00
64Geotextile type DF schedule A (645.0111)SY50$8.00$8.00$3.50$8.00$5.05
65Geotextile type HR (645.0120)SY481$6.50$5.00$4.50$6.50$5.44
66Marking line epoxy 6-inch (646.2020)LF1,873$2.90$2.90$2.90$2.90$2.75
67Construction staking subgrade (650.4500)LF609$0.01$0.01$0.01$0.01$0.01
68Construction staking base (650.5000)LF609$0.75$0.75$0.75$0.75$0.75
69Construction staking curb gutter and curb & gutter (650.5500)LF101$5.00$5.00$5.00$5.00$5.00
70Construction staking pipe culverts (650.6000)EACH1$300.00$300.00$300.00$300.00$300.00
71Construction staking structure layout (structure) 01. B-37-468 (650.6501)EACH1$2,700.00$2,700.00$2,700.00$2,700.00$2,700.00
72Construction staking supplemental control (project) 01. 6653-00-72 (650.9911)EACH1$750.00$750.00$750.00$750.00$750.00
73Construction staking slope stakes (650.9920)LF609$0.75$0.75$0.75$0.75$0.75
74Sawing asphalt (690.0150)LF58$4.10$4.10$2.00$4.10$4.10
75Incentive strength concrete structures (715.0502)DOL2,009$1.00$1.00$1.00$1.00$1.00
76Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00$1.00$1.00
77Installing and maintaining bird deterrent system (station) 01. 13+61 (999.2000.S)EACH1$1,600.00$0.01$1,000.00$3,000.00$0.01
78On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,200$5.00$5.00$5.00$5.00$5.00
79On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00$5.00$5.00
WisDOT contract 20250114028: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way