WisDOT contract 20250114029 bid tabulation
CTH J - STH 17; Prairie River Bridge, B-34-0064 (CTH H, Langlade County CTH J - STH 17). Let by Wisconsin DOT on January 14, 2025, Langlade. 6 bids received; low bid $814,508 by Zenith Tech., Inc. - Waukesha.
- Owner
- Wisconsin DOT
- Letting
- 14 JAN 2025
- Pay items
- 70
- Data through
- 10 NOV 2026
5 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Zenith Tech., Inc. - Waukesha | $814,508 | Low |
| 2 | Sheet Piling Services LLC | $817,191 | 0.0% |
| 3 | Larson Construction Co., Inc. | $836,050 | +3.0% |
| 5 | Lunda Construction Company | $865,026 | +6.0% |
| 6 | Radtke Contractors Inc. | $921,839 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Zenith Tech., Inc. - Waukesha | 2. Sheet Piling Services LLC | 3. Larson Construction Co., Inc. | 4. Lunda Construction Company | 5. Radtke Contractors Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0110) | SY | 58 | $50.00 | $7.54 | $7.54 | $7.54 | $7.54 |
| 2 | Grubbing (201.0210) | SY | 58 | $65.00 | $17.24 | $17.54 | $17.24 | $17.24 |
| 3 | Removing structure over waterway debris capture (structure) 01. B-34- 0006 (203.0270) | EACH | 1 | $49,000 | $120,000 | $102,167 | $240,500 | $129,347 |
| 4 | Removing guardrail (204.0165) | LF | 160 | $5.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 5 | Excavation common (205.0100) | CY | 675 | $20.00 | $22.03 | $22.03 | $22.03 | $22.03 |
| 6 | Excavation for structures bridges (structure) 01. B-34-0064 (206.1001) | EACH | 1 | $7,500.00 | $60,000 | $27,960 | $14,250 | $11,980 |
| 7 | Backfill structure type A (210.1500) | TON | 490 | $25.00 | $27.85 | $27.85 | $27.85 | $27.85 |
| 8 | Finishing roadway (project) 01. 9371-00-70 (213.0100) | EACH | 1 | $1,400.00 | $500.00 | $500.00 | $500.00 | $500.00 |
| 9 | Base aggregate dense 3/4-inch (305.0110) | TON | 30 | $50.00 | $28.25 | $28.25 | $28.25 | $28.25 |
| 10 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,026 | $20.00 | $24.28 | $24.28 | $24.28 | $24.28 |
| 11 | Tack coat (455.0605) | GAL | 70 | $8.72 | $8.72 | $8.72 | $8.72 | $8.72 |
| 12 | Asphaltic surface (465.0105) | TON | 223 | $133.34 | $133.34 | $133.34 | $133.34 | $133.34 |
| 13 | Concrete masonry bridges (502.0100) | CY | 227 | $1,022.00 | $820.00 | $827.00 | $550.00 | $1,011.32 |
| 14 | Protective surface treatment (502.3200) | SY | 320 | $4.00 | $5.00 | $3.25 | $3.00 | $3.75 |
| 15 | Pigmented surface sealer (502.3210) | SY | 148 | $13.00 | $5.00 | $3.25 | $2.00 | $8.34 |
| 16 | Prestressed girder type I 36W-inch (503.0137) | LF | 335 | $226.00 | $240.00 | $295.00 | $275.00 | $279.92 |
| 17 | Bar steel reinforcement HS structures (505.0400) | LB | 5,300 | $1.32 | $1.30 | $2.00 | $1.18 | $1.31 |
| 18 | Bar steel reinforcement HS coated structures (505.0600) | LB | 26,070 | $1.49 | $1.40 | $1.50 | $1.35 | $1.42 |
| 19 | Bearing pads elastomeric non- laminated (506.2605) | EACH | 10 | $152.00 | $200.00 | $125.00 | $200.00 | $216.65 |
| 20 | Steel diaphragms (structure) 01. B- 34-0064 (506.4000) | EACH | 4 | $914.00 | $1,500.00 | $979.00 | $1,000.00 | $1,010.80 |
| 21 | Railing tubular type H (513.4056) | LF | 96 | $226.00 | $280.00 | $209.00 | $235.00 | $290.14 |
| 22 | Rubberized membrane waterproofing (516.0500) | SY | 22 | $28.00 | $30.00 | $38.44 | $25.00 | $74.42 |
| 23 | Pile points (550.0500) | EACH | 18 | $112.00 | $200.00 | $180.00 | $150.00 | $115.00 |
| 24 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 360 | $65.00 | $55.00 | $65.00 | $58.17 | $37.11 |
| 25 | Riprap heavy (606.0300) | CY | 310 | $95.00 | $140.91 | $140.91 | $140.91 | $140.91 |
| 26 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 240 | $9.00 | $6.50 | $6.50 | $6.50 | $6.50 |
| 27 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $444.00 | $250.00 | $250.00 | $150.00 | $236.20 |
| 28 | MGS guardrail 3 (614.2300) | LF | 53.10 | $30.00 | $31.50 | $31.50 | $31.50 | $31.50 |
| 29 | MGS guardrail short radius (614.2350) | LF | 12.50 | $45.00 | $50.10 | $50.10 | $50.10 | $50.10 |
| 30 | MGS thrie beam transition (614.2500) | LF | 157.60 | $99.00 | $95.10 | $95.10 | $95.10 | $95.10 |
| 31 | MGS guardrail terminal eat (614.2610) | EACH | 3 | $5,000.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 32 | MGS guardrail short radius terminal (614.2630) | EACH | 1 | $3,000.00 | $2,700.00 | $2,700.00 | $2,700.00 | $2,700.00 |
| 33 | Fence chain link 5-FT (616.0205) | LF | 64 | $75.00 | $106.48 | $106.48 | $106.48 | $140.00 |
| 34 | Maintenance and repair of haul roads (project) 01. 9371-00-70 (618.0100) | EACH | 1 | $1,750.00 | $0.01 | $1.00 | $0.01 | $500.00 |
| 35 | Mobilization (619.1000) | EACH | 1 | $126,000 | $54,072 | $98,498 | $83,644 | $143,651 |
| 36 | Water (624.0100) | MGAL | 16 | $50.00 | $20.00 | $20.00 | $20.00 | $20.00 |
| 37 | Topsoil (625.0100) | SY | 500 | $11.00 | $8.10 | $8.10 | $8.10 | $8.10 |
| 38 | Silt fence (628.1504) | LF | 755 | $2.00 | $2.75 | $2.75 | $2.75 | $2.75 |
| 39 | Silt fence maintenance (628.1520) | LF | 755 | $0.01 | $0.10 | $0.10 | $0.10 | $0.10 |
| 40 | Mobilizations erosion control (628.1905) | EACH | 3 | $1,000.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 41 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $1.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 42 | Erosion mat urban class I type B (628.2008) | SY | 500 | $4.00 | $1.90 | $1.90 | $1.90 | $1.90 |
| 43 | Turbidity barriers (628.6005) | SY | 160 | $65.00 | $48.50 | $48.50 | $48.50 | $48.50 |
| 44 | Rock bags (628.7570) | EACH | 51 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 45 | Fertilizer type B (629.0210) | CWT | 0.90 | $250.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 46 | Seeding mixture no. 20 (630.0120) | LB | 23 | $15.00 | $7.15 | $7.15 | $7.15 | $7.15 |
| 47 | Seed water (630.0500) | MGAL | 15 | $10.00 | $20.00 | $20.00 | $20.00 | $20.00 |
| 48 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 6 | $150.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 49 | Signs type II reflective H (637.2210) | SF | 8 | $50.00 | $30.00 | $30.00 | $30.00 | $30.00 |
| 50 | Signs type II reflective F (637.2230) | SF | 12 | $50.00 | $30.00 | $30.00 | $30.00 | $30.00 |
| 51 | Removing signs type II (638.2602) | EACH | 10 | $50.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 52 | Removing small sign supports (638.3000) | EACH | 10 | $100.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 53 | Field office type B (642.5001) | EACH | 1 | $6,000.00 | $1,000.00 | $2,000.00 | $2,000.00 | $2,489.56 |
| 54 | Traffic control barricades type III (643.0420) | DAY | 480 | $0.40 | $0.40 | $0.40 | $2.25 | $0.40 |
| 55 | Traffic control warning lights type A (643.0705) | DAY | 960 | $0.10 | $0.10 | $0.10 | $0.25 | $0.10 |
| 56 | Traffic control signs (643.0900) | DAY | 720 | $0.40 | $0.40 | $0.40 | $2.50 | $0.40 |
| 57 | Traffic control signs fixed message (643.1000) | SF | 36 | $10.70 | $10.70 | $10.70 | $25.00 | $10.70 |
| 58 | Traffic control (643.5000) | EACH | 1 | $2,456.00 | $2,456.00 | $2,456.00 | $1,650.00 | $2,456.00 |
| 59 | Geotextile type DF schedule A (645.0111) | SY | 60 | $6.00 | $7.00 | $7.00 | $7.00 | $7.00 |
| 60 | Geotextile type HR (645.0120) | SY | 530 | $6.00 | $6.00 | $6.00 | $6.00 | $6.00 |
| 61 | Construction staking subgrade (650.4500) | LF | 394 | $0.01 | $1.44 | $1.44 | $0.01 | $1.44 |
| 62 | Construction staking base (650.5000) | LF | 394 | $1.44 | $1.44 | $1.44 | $1.44 | $1.44 |
| 63 | Construction staking structure layout (structure) 01. B-34-0064 (650.6501) | EACH | 1 | $1,750.00 | $1,750.00 | $1,750.00 | $1,750.00 | $1,750.00 |
| 64 | Construction staking supplemental control (project) 01. 9371-00-70 (650.9911) | EACH | 1 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 65 | Construction staking slope stakes (650.9920) | LF | 394 | $3.44 | $3.44 | $3.44 | $3.44 | $3.44 |
| 66 | Sawing asphalt (690.0150) | LF | 44 | $2.95 | $3.50 | $3.50 | $3.50 | $3.50 |
| 67 | Incentive strength concrete structures (715.0502) | DOL | 1,362 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 68 | Installing and maintaining bird deterrent system (station) 01. 10+00 (999.2000.S) | EACH | 1 | $4,500.00 | $0.01 | $4,000.00 | $0.01 | $0.01 |
| 69 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,200 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 70 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.