WisDOT contract 20250114032 bid tabulation
1198-03-73. Let by Wisconsin DOT on January 14, 2025, Douglas. 2 bids received; low bid $3,977,872 by Chippewa Concrete Services, Inc..
- Owner
- Wisconsin DOT
- Letting
- 14 JAN 2025
- Pay items
- 151
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Chippewa Concrete Services, Inc. | $3,977,872 | Low |
| 2 | Northland Constructors of Duluth, Mathy | $4,145,800 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Chippewa Concrete Services, Inc. | 2. Northland Constructors of Duluth, Mathy |
|---|---|---|---|---|---|
| 1 | Grubbing (201.0210) | SY | 72 | $13.37 | $15.00 |
| 2 | Removing concrete pavement (204.0100) | SY | 1,970 | $11.67 | $30.00 |
| 3 | Removing concrete pavement butt joints (204.0105) | SY | 28 | $21.77 | $21.77 |
| 4 | Removing asphaltic surface (204.0110) | SY | 790 | $5.56 | $9.00 |
| 5 | Removing asphaltic surface butt joints (204.0115) | SY | 540 | $14.29 | $14.29 |
| 6 | Removing asphaltic surface milling (204.0120) | SY | 58,400 | $3.32 | $3.32 |
| 7 | Removing curb & gutter (204.0150) | LF | 1,220 | $5.88 | $6.00 |
| 8 | Removing concrete sidewalk (204.0155) | SY | 87 | $29.19 | $25.00 |
| 9 | Removing catch basins (204.0215) | EACH | 2 | $474.09 | $735.00 |
| 10 | Removing storm sewer (size) 01. 15-inch (204.0245) | LF | 30 | $46.88 | $40.00 |
| 11 | Removing (item description) 01. storm sewer bulkhead (204.9060.S) | EACH | 1 | $393.30 | $650.00 |
| 12 | Removing (item description) 02. bollards (204.9060.S) | EACH | 3 | $233.45 | $250.00 |
| 13 | Removing (item description) 01. concrete median (204.9180.S) | SY | 13 | $98.46 | $60.00 |
| 14 | Excavation common (205.0100) | CY | 5,140 | $15.93 | $19.00 |
| 15 | Select borrow (208.1100) | CY | 2,260 | $24.00 | $33.00 |
| 16 | Prepare foundation for asphaltic paving (project) 01. 1198-03-73 (211.0101) | EACH | 1 | $106,145 | $106,145 |
| 17 | Prepare foundation for asphaltic paving (project) 02. 1198-03-80 (211.0101) | EACH | 1 | $18,763 | $18,763 |
| 18 | Finishing roadway (project) 01. 1198-03-73 (213.0100) | EACH | 1 | $5,000.00 | $15,000 |
| 19 | Finishing roadway (project) 02. 1198-03-80 (213.0100) | EACH | 1 | $2,500.00 | $15,000 |
| 20 | Base aggregate dense 3/4-inch (305.0110) | TON | 340 | $67.75 | $30.00 |
| 21 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 4,140 | $30.00 | $30.00 |
| 22 | Shaping shoulders (305.0500) | STA | 8 | $95.00 | $650.00 |
| 23 | Concrete pavement 8-inch (415.0080) | SY | 1,700 | $83.09 | $111.00 |
| 24 | Drilled tie bars (416.0610) | EACH | 1,160 | $20.59 | $11.00 |
| 25 | Drilled dowel bars (416.0620) | EACH | 2,930 | $16.03 | $19.00 |
| 26 | Concrete pavement repair (416.1710) | SY | 1,470 | $163.83 | $150.00 |
| 27 | Concrete pavement replacement (416.1720) | SY | 1,930 | $141.54 | $150.00 |
| 28 | Tack coat (455.0605) | GAL | 6,100 | $3.30 | $3.30 |
| 29 | Incentive density HMA pavement (460.2000) | DOL | 5,460 | $1.00 | $1.00 |
| 30 | HMA pavement 5 MT 58-34 V (460.6645) | TON | 8,520 | $111.57 | $111.57 |
| 31 | Material transfer vehicle (460.9000.S) | EACH | 1 | $21,300 | $21,300 |
| 32 | Asphaltic surface (465.0105) | TON | 50 | $125.00 | $125.00 |
| 33 | Asphaltic surface patching (465.0110) | TON | 325 | $125.00 | $125.00 |
| 34 | Asphaltic surface driveways and field entrances (465.0120) | TON | 110 | $125.00 | $125.00 |
| 35 | Concrete collars for pipe (520.8000) | EACH | 3 | $1,103.43 | $1,050.00 |
| 36 | Culvert pipe reinforced concrete horizontal elliptical class HE-III 14X23-inch (522.2314) | LF | 46 | $219.00 | $140.00 |
| 37 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 14X23-inch (522.2614) | EACH | 2 | $1,872.20 | $1,600.00 |
| 38 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 280 | $60.10 | $45.00 |
| 39 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 2,430 | $23.33 | $24.00 |
| 40 | Concrete curb pedestrian (601.0600) | LF | 30 | $52.47 | $70.00 |
| 41 | Concrete sidewalk 6-inch (602.0415) | SF | 1,220 | $13.55 | $15.00 |
| 42 | Curb ramp detectable warning field natural patina (602.0515) | SF | 40 | $60.38 | $70.00 |
| 43 | Curb ramp detectable warning field radial natural patina (602.0615) | SF | 37 | $68.90 | $70.00 |
| 44 | Concrete driveway 6-inch (602.0810) | SY | 312 | $85.90 | $95.00 |
| 45 | Concrete barrier temporary precast delivered (603.8000) | LF | 175 | $55.93 | $50.00 |
| 46 | Concrete barrier temporary precast installed (603.8125) | LF | 175 | $7.71 | $15.00 |
| 47 | Anchoring concrete barrier temporary precast (603.8500) | LF | 175 | $14.93 | $10.00 |
| 48 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 305 | $147.89 | $85.00 |
| 49 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 32 | $144.12 | $85.00 |
| 50 | Storm sewer pipe reinforced concrete class IV 30-inch (608.0430) | LF | 452 | $158.63 | $175.00 |
| 51 | Reconstructing catch basins (611.0410) | EACH | 1 | $2,131.53 | $4,040.00 |
| 52 | Reconstructing manholes (611.0420) | EACH | 8 | $2,390.85 | $4,040.00 |
| 53 | Inlet covers type A (611.0600) | EACH | 1 | $907.64 | $1,280.00 |
| 54 | Inlet covers type A-S (611.0603) | EACH | 1 | $907.64 | $1,280.00 |
| 55 | Inlet covers type H (611.0624) | EACH | 7 | $881.93 | $1,300.00 |
| 56 | Inlet covers type H-S (611.0639) | EACH | 6 | $883.06 | $1,300.00 |
| 57 | Inlet covers type MS (611.0642) | EACH | 1 | $690.29 | $1,050.00 |
| 58 | Inlet covers type V (611.0654) | EACH | 1 | $857.04 | $1,250.00 |
| 59 | Catch basins 4-FT diameter (611.1004) | EACH | 11 | $3,827.83 | $3,150.00 |
| 60 | Catch basins 5-FT diameter (611.1005) | EACH | 2 | $5,990.35 | $5,730.00 |
| 61 | Manholes 8-FT diameter (611.2008) | EACH | 1 | $13,694 | $13,450 |
| 62 | Inlets median 1 grate (611.3901) | EACH | 1 | $3,032.55 | $3,025.00 |
| 63 | Adjusting catch basin covers (611.8105) | EACH | 53 | $1,500.00 | $950.00 |
| 64 | Adjusting manhole covers (611.8110) | EACH | 14 | $1,500.00 | $850.00 |
| 65 | Cover plates temporary (611.8120.S) | EACH | 92 | $500.00 | $490.00 |
| 66 | Salvaged manhole covers (611.9705) | EACH | 1 | $543.95 | $350.00 |
| 67 | Pipe underdrain unperforated 6- inch (612.0206) | LF | 30 | $25.43 | $30.00 |
| 68 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 3,160 | $24.22 | $11.00 |
| 69 | Maintenance and repair of haul roads (project) 01. 1198-03-73 (618.0100) | EACH | 1 | $1,000.00 | $1.00 |
| 70 | Mobilization (619.1000) | EACH | 1 | $375,724 | $433,140 |
| 71 | Water (624.0100) | MGAL | 0.20 | $1,000.00 | $750.00 |
| 72 | Topsoil (625.0100) | SY | 1,820 | $7.49 | $10.00 |
| 73 | Salvaged topsoil (625.0500) | SY | 2,710 | $3.39 | $4.00 |
| 74 | Silt fence (628.1504) | LF | 200 | $5.00 | $2.70 |
| 75 | Silt fence maintenance (628.1520) | LF | 200 | $0.03 | $0.17 |
| 76 | Mobilizations erosion control (628.1905) | EACH | 2 | $393.00 | $300.00 |
| 77 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $593.00 | $325.00 |
| 78 | Erosion mat urban class I type A (628.2006) | SY | 4,530 | $2.75 | $2.30 |
| 79 | Inlet protection type C (628.7015) | EACH | 71 | $70.00 | $74.00 |
| 80 | Fertilizer type B (629.0210) | CWT | 4 | $100.00 | $80.00 |
| 81 | Seeding mixture no. 30 (630.0130) | LB | 83 | $15.00 | $8.80 |
| 82 | Seed water (630.0500) | MGAL | 102 | $5.00 | $2.00 |
| 83 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 21 | $100.00 | $80.00 |
| 84 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 2 | $125.00 | $90.00 |
| 85 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 1 | $300.00 | $170.00 |
| 86 | Signs type II reflective H (637.2210) | SF | 178.78 | $25.00 | $21.00 |
| 87 | Signs type II reflective F (637.2230) | SF | 36 | $30.00 | $24.80 |
| 88 | Moving signs type II (638.2102) | EACH | 8 | $100.00 | $120.00 |
| 89 | Removing signs type I (638.2601) | EACH | 10 | $300.00 | $580.00 |
| 90 | Removing signs type II (638.2602) | EACH | 19 | $30.00 | $32.00 |
| 91 | Removing small sign supports (638.3000) | EACH | 6 | $30.00 | $32.00 |
| 92 | Moving small sign supports (638.4000) | EACH | 6 | $100.00 | $100.00 |
| 93 | Field office type B (642.5001) | EACH | 1 | $10,000 | $7,000.00 |
| 94 | Traffic control drums (643.0300) | DAY | 24,800 | $0.22 | $0.22 |
| 95 | Traffic control barricades type III (643.0420) | DAY | 3,500 | $0.67 | $0.67 |
| 96 | Traffic control warning lights type A (643.0705) | DAY | 6,670 | $0.11 | $0.11 |
| 97 | Traffic control warning lights type C (643.0715) | DAY | 4,420 | $0.11 | $0.11 |
| 98 | Traffic control arrow boards (643.0800) | DAY | 200 | $10.00 | $10.00 |
| 99 | Traffic control signs (643.0900) | DAY | 11,360 | $0.35 | $0.35 |
| 100 | Traffic control covering signs type II (643.0920) | EACH | 10 | $40.00 | $40.00 |
| 101 | Traffic control signs fixed message (643.1000) | SF | 75 | $20.00 | $20.00 |
| 102 | Traffic control signs PCMS (643.1050) | DAY | 250 | $20.00 | $20.00 |
| 103 | Traffic control cones 42-inch (643.1070) | DAY | 46,800 | $0.15 | $0.15 |
| 104 | Temporary marking line paint 6- inch (643.3165) | LF | 545 | $5.83 | $5.83 |
| 105 | Temporary marking line removable tape 6-inch (643.3180) | LF | 2,100 | $2.15 | $2.15 |
| 106 | Traffic control (643.5000) | EACH | 1 | $57,000 | $157,000 |
| 107 | Temporary pedestrian surface plate (644.1430) | SF | 355 | $8.00 | $8.00 |
| 108 | Temporary pedestrian curb ramp (644.1601) | DAY | 60 | $10.00 | $10.00 |
| 109 | Temporary pedestrian barricade (644.1810) | LF | 1,000 | $5.00 | $5.00 |
| 110 | Geotextile type sas (645.0140) | SY | 32 | $26.02 | $10.00 |
| 111 | Marking line epoxy 6-inch (646.2020) | LF | 29,700 | $0.89 | $0.89 |
| 112 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 22,000 | $1.90 | $1.90 |
| 113 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 3,480 | $2.75 | $2.75 |
| 114 | Marking arrow epoxy (646.5020) | EACH | 22 | $295.00 | $295.00 |
| 115 | Marking word epoxy (646.5120) | EACH | 6 | $350.00 | $350.00 |
| 116 | Marking stop line epoxy 18-inch (646.6120) | LF | 480 | $14.00 | $14.00 |
| 117 | Marking diagonal epoxy 12-inch (646.7120) | LF | 198 | $10.00 | $10.00 |
| 118 | Marking chevron epoxy 24-inch (646.7220) | LF | 50 | $16.00 | $16.00 |
| 119 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 334 | $14.00 | $14.00 |
| 120 | Marking curb epoxy (646.8120) | LF | 665 | $9.00 | $9.00 |
| 121 | Marking island nose epoxy (646.8220) | EACH | 16 | $300.00 | $300.00 |
| 122 | Marking removal line 4-inch (646.9000) | LF | 1,870 | $1.35 | $1.35 |
| 123 | Marking removal line 8-inch (646.9100) | LF | 216 | $1.47 | $1.47 |
| 124 | Marking removal special marking (646.9300) | EACH | 1 | $313.93 | $313.93 |
| 125 | Construction staking storm sewer (650.4000) | EACH | 17 | $65.00 | $65.00 |
| 126 | Construction staking subgrade (650.4500) | LF | 2,810 | $0.30 | $0.30 |
| 127 | Construction staking base (650.5000) | LF | 2,910 | $0.35 | $0.35 |
| 128 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 3,050 | $0.75 | $0.75 |
| 129 | Construction staking resurfacing reference (650.8000) | LF | 16,000 | $0.13 | $0.13 |
| 130 | Construction staking curb ramps (650.9000) | EACH | 5 | $250.00 | $250.00 |
| 131 | Construction staking sidewalk (project) 01. 1198-03-73 (650.9500) | EACH | 1 | $2,500.00 | $2,500.00 |
| 132 | Construction staking supplemental control (project) 01. 1198-03-73 (650.9911) | EACH | 1 | $2,500.00 | $1,000.00 |
| 133 | Construction staking supplemental control (project) 02. 1198-03-80 (650.9911) | EACH | 1 | $1,000.00 | $2,500.00 |
| 134 | Construction staking slope stakes (650.9920) | LF | 1,280 | $0.40 | $0.40 |
| 135 | Sawing asphalt (690.0150) | LF | 2,960 | $1.95 | $1.95 |
| 136 | Sawing concrete (690.0250) | LF | 16,600 | $2.55 | $2.55 |
| 137 | Incentive compressive strength concrete pavement (715.0720) | DOL | 510 | $1.00 | $1.00 |
| 138 | Incentive iri ride (740.0440) | DOL | 12,050 | $1.00 | $1.00 |
| 139 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 800 | $5.00 | $5.00 |
| 140 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 |
| 141 | Special 01. elastomeric waterproofing sealer (SPV.0060) | EACH | 98 | $205.90 | $220.00 |
| 142 | Special 02. manhole covers special (SPV.0060) | EACH | 4 | $996.48 | $1,175.00 |
| 143 | Special 03. move and reset landscaping boulders (SPV.0060) | EACH | 26 | $42.82 | $100.00 |
| 144 | Special 01. concrete curb & gutter 6-inch sloped 18-inch type G (SPV.0090) | LF | 240 | $42.68 | $50.00 |
| 145 | Special 02. cure & seal treatment, concrete curb & gutter (SPV.0090) | LF | 2,940 | $0.36 | $1.00 |
| 146 | Special 03. fence chain link 5-FT repair (SPV.0090) | LF | 70 | $50.00 | $62.54 |
| 147 | Special 01. cure & seal treatment, concrete sidewalk (SPV.0165) | SF | 1,220 | $0.08 | $1.00 |
| 148 | Special 01. cure & seal treatment, concrete driveway (SPV.0180) | SY | 312 | $0.64 | $6.00 |
| 149 | Special 02. salvage and reset landscaping rock (SPV.0180) | SY | 300 | $11.86 | $35.00 |
| 150 | Special 01. excavation, hauling, and disposal of contaminated soil (direct landfill) (SPV.0195) | TON | 2,280 | $59.13 | $35.00 |
| 151 | Special 02. landscaping rock (SPV.0195) | TON | 12 | $55.00 | $150.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.