WisDOT contract 20250114033 bid tabulation
Galesville - Melrose; Wilson Cr & Mill Cr Br B270175,0235 (STH 054, Jackson County Galesville - Melrose). Let by Wisconsin DOT on January 14, 2025, Jackson. 4 bids received; low bid $2,794,848 by Lunda Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 14 JAN 2025
- Pay items
- 118
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lunda Construction Company | $2,794,848 | Low |
| 2 | Sheet Piling Services LLC | $2,892,259 | +3.0% |
| 3 | Kraemer North America, LLC | $3,326,710 | +19% |
| 4 | Zenith Tech., Inc. - Waukesha | $4,024,391 | +44% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lunda Construction Company | 2. Sheet Piling Services LLC | 3. Kraemer North America, LLC | 4. Zenith Tech., Inc. - Waukesha |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 9 | $450.00 | $450.00 | $450.00 | $1,521.52 |
| 2 | Grubbing (201.0205) | STA | 9 | $450.00 | $450.00 | $450.00 | $855.65 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 2 | $500.00 | $500.00 | $500.00 | $566.36 |
| 4 | Removing structure over waterway minimal debris (structure) 01. B-27- 0175 (203.0260) | EACH | 1 | $175,000 | $250,000 | $250,000 | $148,000 |
| 5 | Removing structure over waterway minimal debris (structure) 02. B-27- 0235 (203.0260) | EACH | 1 | $100,000 | $175,000 | $175,000 | $112,000 |
| 6 | Removing curb & gutter (204.0150) | LF | 236 | $7.50 | $7.50 | $7.50 | $5.67 |
| 7 | Excavation common (205.0100) | CY | 4,000 | $12.50 | $12.50 | $12.50 | $19.35 |
| 8 | Excavation for structures bridges (structure) 01. B-27-0175 (206.1001) | EACH | 1 | $50,000 | $7,500.00 | $7,500.00 | $9,779.70 |
| 9 | Excavation for structures bridges (structure) 02. B-27-0235 (206.1001) | EACH | 1 | $50,000 | $12,000 | $12,000 | $18,613 |
| 10 | Borrow (208.0100) | CY | 10,000 | $15.50 | $15.50 | $15.50 | $24.10 |
| 11 | Backfill structure type A (210.1500) | TON | 1,612 | $22.00 | $22.00 | $22.00 | $44.21 |
| 12 | Finishing roadway (project) 01. 7550-00-75 (213.0100) | EACH | 1 | $500.00 | $500.00 | $500.00 | $2,350.00 |
| 13 | Base aggregate dense 3/4-inch (305.0110) | TON | 455 | $29.00 | $29.00 | $29.00 | $32.64 |
| 14 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 3,210 | $21.50 | $21.50 | $21.50 | $19.53 |
| 15 | Concrete pavement 7-inch (415.0070) | SY | 66 | $114.44 | $114.44 | $114.44 | $114.44 |
| 16 | Concrete pavement approach slab (415.0410) | SY | 133 | $254.77 | $254.77 | $254.77 | $254.77 |
| 17 | Tack coat (455.0605) | GAL | 188 | $4.48 | $4.48 | $4.48 | $4.48 |
| 18 | Asphaltic surface (465.0105) | TON | 1,240 | $117.88 | $117.88 | $117.88 | $117.88 |
| 19 | Asphaltic surface detours (465.0115) | TON | 50 | $251.06 | $251.06 | $251.06 | $251.06 |
| 20 | Asphaltic surface temporary (465.0125) | TON | 500 | $119.27 | $119.27 | $119.27 | $119.27 |
| 21 | Concrete masonry bridges (502.0100) | CY | 675 | $600.00 | $900.00 | $1,000.00 | $1,065.00 |
| 22 | Protective surface treatment (502.3200) | SY | 841 | $3.00 | $3.00 | $3.00 | $4.00 |
| 23 | Pigmented surface sealer (502.3210) | SY | 258 | $5.00 | $3.00 | $15.00 | $12.30 |
| 24 | Prestressed girder type I 36W-inch (503.0137) | LF | 304 | $250.00 | $250.00 | $300.00 | $295.00 |
| 25 | Prestressed girder type I 72W-inch (503.0172) | LF | 484 | $300.00 | $275.00 | $400.00 | $370.00 |
| 26 | Bar steel reinforcement HS structures (505.0400) | LB | 15,500 | $1.25 | $1.00 | $1.40 | $1.20 |
| 27 | Bar steel reinforcement HS coated structures (505.0600) | LB | 80,600 | $1.45 | $1.10 | $1.55 | $1.40 |
| 28 | Bearing pads elastomeric non- laminated (506.2605) | EACH | 16 | $150.00 | $250.00 | $120.00 | $183.00 |
| 29 | Steel diaphragms (structure) 01. B- 27-0175 (506.4000) | EACH | 6 | $2,000.00 | $3,000.00 | $2,800.00 | $2,650.00 |
| 30 | Steel diaphragms (structure) 02. B- 27-0235 (506.4000) | EACH | 3 | $1,000.00 | $1,500.00 | $1,100.00 | $1,625.00 |
| 31 | Temporary shoring (structure) 01. B-27-0235 (511.1200) | SF | 300 | $25.00 | $25.00 | $50.00 | $163.50 |
| 32 | Rubberized membrane waterproofing (516.0500) | SY | 52 | $20.00 | $25.00 | $10.00 | $60.00 |
| 33 | Apron endwalls for culvert pipe 18- inch (520.1018) | EACH | 2 | $265.00 | $265.00 | $265.00 | $393.32 |
| 34 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 2 | $285.00 | $285.00 | $285.00 | $462.62 |
| 35 | Culvert pipe class III-B 18-inch (520.3518) | LF | 54 | $40.00 | $40.00 | $40.00 | $49.01 |
| 36 | Culvert pipe class III-B 24-inch (520.3524) | LF | 156 | $50.00 | $50.00 | $50.00 | $57.92 |
| 37 | Concrete collars for pipe (520.8000) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,236.04 |
| 38 | Culvert pipe liners (size) 01. 30- inch (520.9700.S) | LF | 58 | $168.00 | $168.00 | $168.00 | $231.00 |
| 39 | Cleaning culvert pipes for liner verification 01. 172+85 (520.9750.S) | EACH | 1 | $400.00 | $400.00 | $400.00 | $1,800.00 |
| 40 | Temporary structure (station) 01. 3+50 (526.0101) | EACH | 1 | $300,000 | $150,000 | $275,000 | $600,000 |
| 41 | Pre-boring rock or consolidated materials (550.0020) | LF | 230 | $175.00 | $125.00 | $200.00 | $560.00 |
| 42 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 300 | $40.00 | $45.00 | $75.00 | $80.00 |
| 43 | Piling cip concrete 10 3/4 X 0.365- inch (550.2106) | LF | 2,480 | $45.00 | $44.00 | $65.00 | $55.00 |
| 44 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 126 | $39.19 | $39.19 | $39.19 | $39.19 |
| 45 | Concrete curb & gutter 4-inch sloped 30-inch type TBT (601.0584) | LF | 181 | $39.19 | $39.19 | $39.19 | $39.19 |
| 46 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 39 | $89.08 | $89.08 | $89.08 | $89.08 |
| 47 | Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590) | LF | 12 | $89.08 | $89.08 | $89.08 | $89.08 |
| 48 | Concrete surface drains (602.3010) | CY | 4 | $1,490.66 | $1,490.66 | $1,490.66 | $1,490.66 |
| 49 | Concrete barrier temporary precast delivered (603.8000) | LF | 210 | $10.00 | $20.00 | $21.00 | $21.00 |
| 50 | Concrete barrier temporary precast installed (603.8125) | LF | 210 | $5.00 | $9.00 | $13.50 | $13.50 |
| 51 | Riprap medium (606.0200) | CY | 17 | $110.00 | $110.00 | $110.00 | $100.06 |
| 52 | Riprap heavy (606.0300) | CY | 690 | $70.00 | $70.00 | $70.00 | $80.61 |
| 53 | Reconstructing inlets (611.0430) | EACH | 1 | $1,750.00 | $1,750.00 | $1,750.00 | $1,386.20 |
| 54 | Inlet covers type H-S (611.0639) | EACH | 1 | $950.00 | $950.00 | $950.00 | $1,087.83 |
| 55 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 430 | $8.00 | $8.00 | $8.00 | $8.22 |
| 56 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 8 | $200.00 | $500.00 | $30.93 | $300.00 |
| 57 | Steel thrie beam structure approach (614.0200) | LF | 19 | $88.00 | $88.00 | $88.00 | $90.00 |
| 58 | Steel plate beam guard class A (614.0305) | LF | 47 | $25.00 | $25.00 | $25.00 | $28.00 |
| 59 | Steel plate beam guard short radius (614.0345) | LF | 32 | $30.00 | $30.00 | $30.00 | $28.00 |
| 60 | Steel plate beam guard short radius terminal (614.0390) | EACH | 1 | $2,265.00 | $2,265.00 | $2,265.00 | $1,953.00 |
| 61 | Salvaged rail (614.0920) | LF | 803 | $2.10 | $2.10 | $2.10 | $2.50 |
| 62 | MGS guardrail 3 (614.2300) | LF | 525 | $21.25 | $21.25 | $21.25 | $25.00 |
| 63 | MGS thrie beam transition (614.2500) | LF | 280 | $86.00 | $86.00 | $86.00 | $85.00 |
| 64 | MGS guardrail terminal eat (614.2610) | EACH | 6 | $3,280.00 | $3,280.00 | $3,280.00 | $3,133.00 |
| 65 | Maintenance and repair of haul roads (project) 01. 7550-00-75 (618.0100) | EACH | 1 | $0.01 | $0.01 | $1,000.00 | $3,150.00 |
| 66 | Mobilization (619.1000) | EACH | 1 | $255,553 | $279,220 | $299,700 | $535,000 |
| 67 | Water (624.0100) | MGAL | 30 | $25.00 | $25.00 | $25.00 | $42.92 |
| 68 | Salvaged topsoil (625.0500) | SY | 5,980 | $1.25 | $1.25 | $1.25 | $1.77 |
| 69 | Silt fence (628.1504) | LF | 2,150 | $1.80 | $1.80 | $1.50 | $1.75 |
| 70 | Silt fence maintenance (628.1520) | LF | 1,075 | $0.01 | $0.01 | $0.10 | $0.03 |
| 71 | Mobilizations erosion control (628.1905) | EACH | 7 | $200.00 | $200.00 | $100.00 | $153.00 |
| 72 | Mobilizations emergency erosion control (628.1910) | EACH | 7 | $100.00 | $100.00 | $100.00 | $203.00 |
| 73 | Erosion mat class II type B (628.2023) | SY | 5,980 | $1.75 | $1.75 | $1.75 | $2.25 |
| 74 | Turbidity barriers (628.6005) | SY | 250 | $41.25 | $41.25 | $35.00 | $44.00 |
| 75 | Inlet protection type A (628.7005) | EACH | 1 | $175.00 | $175.00 | $150.00 | $150.00 |
| 76 | Inlet protection type C (628.7015) | EACH | 1 | $65.00 | $65.00 | $175.00 | $75.00 |
| 77 | Temporary ditch checks (628.7504) | LF | 400 | $5.95 | $5.95 | $8.00 | $7.00 |
| 78 | Culvert pipe checks (628.7555) | EACH | 11 | $18.00 | $18.00 | $25.00 | $50.00 |
| 79 | Rock bags (628.7570) | EACH | 50 | $15.00 | $15.00 | $25.00 | $9.00 |
| 80 | Fertilizer type B (629.0210) | CWT | 4 | $85.00 | $85.00 | $120.00 | $100.00 |
| 81 | Seeding mixture no. 20 (630.0120) | LB | 160 | $8.50 | $8.50 | $6.00 | $9.00 |
| 82 | Seeding temporary (630.0200) | LB | 70 | $3.20 | $3.20 | $5.00 | $7.00 |
| 83 | Seed water (630.0500) | MGAL | 150 | $0.01 | $0.01 | $10.00 | $5.00 |
| 84 | Markers culvert end (633.5200) | EACH | 4 | $53.00 | $53.00 | $40.00 | $75.00 |
| 85 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 10 | $82.00 | $82.00 | $110.00 | $95.00 |
| 86 | Signs type II reflective H (637.2210) | SF | 34.36 | $20.00 | $20.00 | $30.00 | $30.00 |
| 87 | Field office type B (642.5001) | EACH | 1 | $6,000.00 | $3,500.00 | $10,000 | $7,000.00 |
| 88 | Traffic control drums (643.0300) | DAY | 5,000 | $0.23 | $0.23 | $0.23 | $0.23 |
| 89 | Traffic control barricades type III (643.0420) | DAY | 3,000 | $0.67 | $0.67 | $0.67 | $0.67 |
| 90 | Traffic control warning lights type A (643.0705) | DAY | 1,800 | $0.32 | $0.32 | $0.32 | $0.32 |
| 91 | Traffic control warning lights type C (643.0715) | DAY | 1,800 | $0.19 | $0.19 | $0.19 | $0.19 |
| 92 | Traffic control signs (643.0900) | DAY | 37,000 | $0.33 | $0.33 | $0.33 | $0.33 |
| 93 | Traffic control covering signs type II (643.0920) | EACH | 15 | $41.36 | $41.36 | $41.36 | $41.36 |
| 94 | Temporary marking line paint 6- inch (643.3165) | LF | 2,800 | $0.40 | $0.40 | $0.40 | $0.40 |
| 95 | Temporary marking line removable tape 6-inch (643.3180) | LF | 1,400 | $1.67 | $1.67 | $1.67 | $1.67 |
| 96 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 57 | $5.26 | $5.26 | $5.26 | $5.26 |
| 97 | Traffic control (643.5000) | EACH | 1 | $12,214 | $12,214 | $12,214 | $12,214 |
| 98 | Geotextile type DF schedule A (645.0111) | SY | 137 | $3.50 | $3.50 | $3.50 | $3.10 |
| 99 | Geotextile type HR (645.0120) | SY | 1,158 | $3.50 | $3.50 | $3.50 | $2.50 |
| 100 | Marking line epoxy 6-inch (646.2020) | LF | 1,838 | $1.50 | $0.86 | $0.86 | $0.86 |
| 101 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 2,490 | $3.25 | $2.37 | $2.37 | $2.37 |
| 102 | Marking line same day epoxy 6- inch (646.4720) | LF | 1,838 | $2.20 | $2.25 | $2.25 | $2.25 |
| 103 | Marking removal line 4-inch (646.9000) | LF | 700 | $0.44 | $0.44 | $0.44 | $0.44 |
| 104 | Construction staking subgrade (650.4500) | LF | 800 | $0.01 | $0.01 | $0.01 | $0.01 |
| 105 | Construction staking base (650.5000) | LF | 800 | $0.75 | $0.75 | $0.75 | $0.75 |
| 106 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 305 | $2.00 | $2.00 | $2.00 | $2.00 |
| 107 | Construction staking pipe culverts (650.6000) | EACH | 2 | $200.00 | $200.00 | $200.00 | $200.00 |
| 108 | Construction staking structure layout (structure) 01. B-27-0175 (650.6501) | EACH | 1 | $2,250.00 | $2,250.00 | $2,250.00 | $2,250.00 |
| 109 | Construction staking structure layout (structure) 02. B-27-0235 (650.6501) | EACH | 1 | $2,250.00 | $2,250.00 | $2,250.00 | $2,250.00 |
| 110 | Construction staking supplemental control (project) 01. 7550-00-75 (650.9911) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 111 | Construction staking slope stakes (650.9920) | LF | 1,150 | $0.75 | $0.75 | $0.75 | $0.75 |
| 112 | Temporary traffic signals for bridges (structure) 01. B-27-0235 (661.0101) | EACH | 1 | $31,395 | $31,395 | $31,395 | $31,395 |
| 113 | Sawing asphalt (690.0150) | LF | 120 | $2.95 | $2.95 | $4.00 | $2.95 |
| 114 | Incentive strength concrete structures 01. B-27-0175 (715.0502) | DOL | 2,454 | $1.00 | $1.00 | $1.00 | $1.00 |
| 115 | Incentive strength concrete structures 02. B-27-0235 (715.0502) | DOL | 1,596 | $1.00 | $1.00 | $1.00 | $1.00 |
| 116 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 117 | Installing and maintaining bird deterrent system (station) 01. 170+50 (999.2000.S) | EACH | 1 | $0.01 | $0.01 | $10,000 | $9,000.00 |
| 118 | Installing and maintaining bird deterrent system (station) 02. 210+50 (999.2000.S) | EACH | 1 | $0.01 | $0.01 | $4,000.00 | $3,750.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.