WisDOT contract 20250114042 bid tabulation

1130-66-80. Let by Wisconsin DOT on January 14, 2025, Outagamie. 4 bids received; low bid $6,647,514 by Vinton Construction Company.

Owner
Wisconsin DOT
Letting
14 JAN 2025
Pay items
162
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Vinton Construction Company$6,647,514Low
2Lunda Construction Company$6,704,542+1.0%
3Sheet Piling Services LLC$6,762,515+2.0%
4Zenith Tech., Inc. - Waukesha$7,807,387+17%
WisDOT contract 20250114042: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Vinton Construction Company2. Lunda Construction Company3. Sheet Piling Services LLC4. Zenith Tech., Inc. - Waukesha
1Clearing (201.0105)STA7$200.00$200.00$200.00$850.00
2Grubbing (201.0205)STA7$200.00$200.00$200.00$250.00
3Removing small pipe culverts (203.0100)EACH5$690.00$690.00$690.00$375.00
4Removing structure (structure) 01. B-44-33 (203.0220)EACH1$330,000$542,000$200,000$250,000
5Removing structure (structure) 02. C-44-19 (203.0220)EACH1$22,600$38,269$22,600$30,000
6Removing structure (structure) 03. B-44-34 (203.0220)EACH1$330,000$542,000$200,000$250,000
7Removing asphaltic surface (204.0110)SY220$10.00$10.00$10.00$17.00
8Removing asphaltic surface milling (204.0120)SY1,780$4.50$4.50$4.50$4.50
9Removing curb & gutter (204.0150)LF120$7.75$7.75$7.75$12.00
10Removing concrete barrier (204.0157)LF210$30.00$30.00$40.00$30.17
11Removing guardrail (204.0165)LF1,956$3.00$3.00$3.00$3.00
12Removing cable barrier (204.0167)LF5,625$3.00$3.00$3.75$3.00
13Removing delineators and markers (204.0180)EACH26$30.00$30.00$25.00$30.00
14Removing surface drains (204.0190)EACH8$200.00$200.00$200.00$31.00
15Removing storm sewer (size) 01. 18-inch (204.0245)LF160$13.00$13.00$13.00$16.00
16Removing (item description) 01. billboard sign (204.9060.S)EACH1$1,120.00$1,120.00$1,120.00$5,000.00
17Excavation common (205.0100)CY4,236$11.52$11.52$11.52$11.32
18Excavation for structures bridges (structure) 01. B-44-330 (206.1001)EACH1$10,600$10,600$25,000$44,000
19Excavation for structures bridges (structure) 02. B-44-331 (206.1001)EACH1$10,600$10,600$25,000$44,000
20Excavation for structures culverts (structure) 01. C-44-153 (206.2001)EACH1$83,000$83,000$83,000$63,000
21Borrow (208.0100)CY28,036$0.01$0.01$0.01$14.00
22Backfill structure type A (210.1500)TON1,850$28.91$28.91$28.91$34.50
23Backfill structure type B (210.2500)TON2,156$25.11$25.11$25.11$34.60
24Prepare foundation for asphaltic paving (project) 01. 1130-66-80 (211.0101)EACH1$5,700.00$5,700.00$5,700.00$5,700.00
25Prepare foundation for asphaltic paving (project) 02. 1130-66-81 (211.0101)EACH1$5,700.00$5,700.00$5,700.00$5,700.00
26Prepare foundation for concrete pavement (project) 01. 1130-66-80 (211.0201)EACH1$1,000.00$1,000.00$1,000.00$2,500.00
27Prepare foundation for concrete pavement (project) 02. 1130-66-81 (211.0201)EACH1$1,000.00$1,000.00$1,000.00$2,500.00
28Prepare foundation for asphaltic shoulders (211.0400)STA43$150.00$150.00$150.00$150.00
29Finishing roadway (project) 01. 1130-66-80 (213.0100)EACH1$2,500.00$2,500.00$0.01$500.00
30Finishing roadway (project) 02. 1130-66-81 (213.0100)EACH1$2,500.00$2,500.00$0.01$500.00
31Base aggregate dense 3/4-inch (305.0110)TON540$44.78$44.78$44.78$32.00
32Base aggregate dense 1 1/4-inch (305.0120)TON2,840$12.33$12.33$12.33$14.90
33Select crushed material (312.0110)TON4,955$16.65$16.65$16.65$14.90
34Concrete pavement 8-inch (415.0080)SY4,665$64.99$64.99$64.99$61.54
35Concrete pavement approach slab (415.0410)SY216$225.00$225.00$225.00$204.87
36Concrete pavement joint filling (415.4100)SY5,095$1.89$1.89$1.89$6.95
37HMA cold weather paving (450.4000)TON370$10.35$10.35$10.35$10.35
38Tack coat (455.0605)GAL168$9.75$9.75$9.75$9.75
39Incentive density HMA pavement (460.2000)DOL300$1.00$1.00$1.00$1.00
40HMA pavement 3 LT 58-28 S (460.5223)TON80$184.10$184.10$184.10$184.10
41HMA pavement 4 LT 58-28 S (460.5224)TON380$189.90$189.90$189.90$189.90
42Asphaltic flumes (465.0315)SY125$67.50$67.50$67.50$67.50
43Asphaltic rumble strips, shoulder divided roadway (465.0510)LF3,900$1.85$1.85$1.85$1.85
44Ice hot weather concreting (501.1000.S)LB8,150$0.01$0.01$0.25$0.79
45Concrete masonry bridges (502.0100)CY448$550.00$550.00$950.00$900.00
46Protective surface treatment (502.3200)SY2,238$3.00$3.00$3.00$4.00
47Pigmented surface sealer (502.3210)SY1,128$2.00$2.00$3.00$13.00
48Prestressed girder type I 45W-inch (503.0146)LF1,433$286.00$286.00$250.00$220.00
49Prestressed girder type I 54W-inch (503.0155)LF1,024$302.00$302.00$275.00$240.00
50Concrete masonry culverts (504.0100)CY15$550.00$550.00$950.00$1,800.00
51Precast concrete wingwalls (structure) 01. C-44-153 (504.1001.S)EACH4$0.01$0.01$0.01$7,000.00
52Precast concrete box culvert (FT X FT) 01. 12 FT X 5 FT (504.2000.S)LF168$1,740.00$1,740.00$1,740.00$2,150.00
53Bar steel reinforcement HS structures (505.0400)LB21,690$0.90$0.90$1.20$1.15
54Bar steel reinforcement HS coated structures (505.0600)LB257,760$1.00$1.00$1.25$1.15
55Bearing pads elastomeric non- laminated (506.2605)EACH48$150.00$150.00$125.00$170.00
56Steel diaphragms (structure) 01. B- 44-330 (506.4000)EACH24$750.00$750.00$750.00$800.00
57Steel diaphragms (structure) 02. B- 44-331 (506.4000)EACH16$1,750.00$1,750.00$1,300.00$1,500.00
58Temporary shoring (structure) 01. B-44-330 (511.1200)SF486$0.01$0.01$45.00$40.00
59Temporary shoring (structure) 02. B-44.331 (511.1200)SF486$0.01$0.01$45.00$40.00
60Temporary shoring (structure) 02. C-44-153 (511.1200)SF400$0.01$0.01$0.01$70.00
61Railing tubular screening (513.4091)LF964$224.50$224.50$215.00$250.00
62Rubberized membrane waterproofing (516.0500)SY87$25.00$25.00$18.00$65.00
63Concrete collars for pipe (520.8000)EACH4$615.00$615.00$615.00$550.00
64Culvert pipe corrugated steel 18- inch (521.3118)LF160$73.70$73.70$73.70$123.00
65Culvert pipe reinforced concrete class IV 36-inch (522.0436)LF383$227.00$227.00$227.00$197.00
66Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH10$1,130.00$1,130.00$1,130.00$1,276.00
67Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036)EACH2$3,500.00$3,500.00$3,500.00$4,160.00
68Pre-boring unconsolidated materials (550.0010)LF161$0.01$0.01$35.00$300.00
69Piling steel HP 12-inch X 53 LB (550.1120)LF5,160$42.00$42.00$40.00$45.00
70Concrete curb integral type D (601.0150)LF2,015$20.00$20.00$20.00$20.00
71Concrete sidewalk 4-inch (602.0405)SF15,604$6.45$6.45$6.45$6.25
72Concrete surface drains (602.3010)CY20$0.01$0.01$0.01$750.00
73Concrete barrier type S42 (603.1142)LF464$300.00$300.00$300.00$239.00
74Concrete barrier temporary precast delivered (603.8000)LF7,400$15.00$12.00$13.00$15.00
75Concrete barrier temporary precast installed (603.8125)LF8,600$3.00$3.00$3.00$2.00
76Anchoring concrete barrier temporary precast (603.8500)LF1,200$10.00$9.25$20.00$7.00
77Slope paving concrete (604.0400)SY708$90.00$90.00$90.00$90.00
78Slope paving select crushed material (604.0600)SY208$30.00$30.00$38.00$30.00
79Riprap medium (606.0200)CY456$79.40$79.40$79.40$84.00
80Riprap heavy (606.0300)CY34$90.00$90.00$90.00$105.00
81Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF178$91.80$91.80$91.80$72.00
82Inlet covers type H (611.0624)EACH10$725.00$725.00$725.00$770.00
83Inlets 2X3-FT (611.3230)EACH10$2,300.00$2,300.00$2,300.00$2,636.00
84Pipe underdrain wrapped 6-inch (612.0406)LF1,180$13.85$13.85$13.85$17.25
85Anchorages for steel plate beam guard type 2 (614.0115)EACH4$2,500.00$2,500.00$250.00$2,500.00
86Steel plate beam guard class A (614.0305)LF356$28.00$28.00$30.00$28.00
87Adjusting steel plate beam guard (614.0400)LF1,413$15.00$15.00$15.00$15.00
88Crash cushions temporary (614.0905)EACH8$5,500.00$3,750.00$3,750.00$7,500.00
89MGS guardrail 3 (614.2300)LF1,554$29.00$29.00$30.00$29.00
90MGS guardrail terminal eat (614.2610)EACH4$4,850.00$4,850.00$4,200.00$4,850.00
91MGS guardrail terminal type 2 (614.2620)EACH4$3,850.00$3,850.00$2,750.00$3,850.00
92Fence chain link salvaged 5-FT (616.0405)LF705$10.00$10.00$15.00$10.00
93Fence chain link salvaged 8-FT (616.0408)LF300$10.00$10.00$20.00$10.00
94Fence safety (616.0700.S)LF300$9.00$9.00$4.75$9.00
95Maintenance and repair of haul roads (project) 01. 1130-66-80 (618.0100)EACH1$0.01$0.01$0.01$250.00
96Maintenance and repair of haul roads (project) 02. 1130-66-81 (618.0100)EACH1$0.01$0.01$0.01$250.00
97Mobilization (619.1000)EACH1$1,017,000$659,621$708,850$840,000
98Water (624.0100)MGAL185$0.01$0.01$0.01$65.00
99Topsoil (625.0100)SY6,205$1.87$1.87$1.87$4.75
100Salvaged topsoil (625.0500)SY20,000$1.87$1.87$1.87$2.75
101Silt fence (628.1504)LF3,925$2.00$2.00$2.50$2.00
102Silt fence maintenance (628.1520)LF7,850$0.01$0.01$0.01$0.01
103Mobilizations erosion control (628.1905)EACH16$1.00$1.00$100.00$1.00
104Mobilizations emergency erosion control (628.1910)EACH10$1.00$1.00$100.00$1.00
105Erosion mat class I type A (628.2002)SY26,205$1.65$1.65$1.10$1.65
106Inlet protection type A (628.7005)EACH11$50.00$50.00$75.00$50.00
107Inlet protection type C (628.7015)EACH10$200.00$200.00$75.00$200.00
108Temporary ditch checks (628.7504)LF525$5.00$5.00$10.00$5.00
109Stone ditch checks (628.7515.S)CY65$80.00$80.00$80.00$80.00
110Culvert pipe checks (628.7555)EACH75$8.00$8.00$18.00$8.00
111Tracking pads (628.7560)EACH4$0.01$0.01$0.01$3,200.00
112Rock bags (628.7570)EACH280$8.00$8.00$18.00$8.00
113Fertilizer type B (629.0210)CWT17$150.00$150.00$85.00$150.00
114Seeding mixture no. 30 (630.0130)LB1,205$8.00$8.00$9.95$8.00
115Seeding borrow pit (630.0300)LB80$8.00$8.00$9.95$8.00
116Seed water (630.0500)MGAL625$0.01$0.01$20.00$0.01
117Markers culvert end (633.5200)EACH12$85.00$85.00$65.00$85.00
118Posts wood 4X6-inch X 16-FT (634.0616)EACH1$250.00$250.00$125.00$250.00
119Signs type II reflective F (637.2230)SF6.25$50.00$50.00$35.00$50.00
120Moving signs type II (638.2102)EACH6$200.00$200.00$250.00$200.00
121Removing signs type II (638.2602)EACH6$50.00$50.00$40.00$50.00
122Removing small sign supports (638.3000)EACH6$100.00$100.00$40.00$100.00
123Moving small sign supports (638.4000)EACH10$50.00$50.00$100.00$50.00
124Traffic control drums (643.0300)DAY25,220$0.20$0.20$0.20$0.20
125Traffic control barricades type III (643.0420)DAY8,456$0.60$0.60$0.60$0.60
126Traffic control warning lights type A (643.0705)DAY16,762$0.15$0.15$0.15$0.15
127Traffic control warning lights type C (643.0715)DAY2,850$0.40$0.40$0.40$0.40
128Traffic control arrow boards (643.0800)DAY1,068$8.25$8.25$8.25$8.25
129Traffic control signs (643.0900)DAY15,132$0.25$0.25$0.25$0.25
130Traffic control covering signs type II (643.0920)EACH248$25.00$25.00$25.00$25.00
131Traffic control signs PCMS (643.1050)DAY557$12.50$12.50$12.50$12.50
132Traffic control (643.5000)EACH1$95,925$95,925$95,925$95,925
133Geotextile type C (645.0105)SY859$3.00$3.00$3.00$2.75
134Geotextile type DF schedule A (645.0111)SY208$3.00$3.00$3.00$6.50
135Geotextile type HR (645.0120)SY1,407$4.00$4.00$4.00$6.55
136Geotextile type R (645.0130)SY260$8.00$8.00$3.00$5.75
137Marking line epoxy 6-inch (646.2020)LF7,000$0.95$0.95$0.95$0.95
138Marking line same day epoxy 4- inch (646.4520)LF4,600$0.70$0.70$0.70$0.70
139Cold weather marking epoxy 4-inch (646.6464)LF4,300$0.20$0.20$0.20$0.20
140Cold weather marking epoxy 6-inch (646.6466)LF3,600$0.30$0.30$0.30$0.30
141Conduit rigid metallic 2-inch (652.0125)LF48$165.00$165.00$165.00$165.00
142Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF2,138$10.00$10.00$10.00$10.00
143Pull boxes non-conductive 24X42- inch (653.0164)EACH8$1,950.00$1,950.00$1,950.00$1,950.00
144Junction boxes 18X12X6-inch (653.0222)EACH2$1,950.00$1,950.00$1,950.00$1,950.00
145Concrete bases type 5 (654.0105)EACH8$1,750.00$1,750.00$1,750.00$1,750.00
146Sawing asphalt (690.0150)LF450$2.99$2.25$1.15$1.15
147Incentive strength concrete structures (715.0502)DOL9,294$1.00$1.00$1.00$1.00
148Incentive strength concrete barrier (715.0603)DOL232$1.00$1.00$1.00$1.00
149Incentive compressive strength concrete pavement (715.0720)DOL1,465$1.00$1.00$1.00$1.00
150On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,400$5.00$5.00$5.00$5.00
151On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS2,100$5.00$5.00$5.00$5.00
152Special 01. HPC masonry structures (SPV.0035)CY1,086$550.00$550.00$950.00$1,000.00
153Special 01. existing footing opening (efo) (SPV.0060)EACH16$250.00$250.00$500.00$1,250.00
154Special 02. covering and locating storm sewer (SPV.0060)EACH2$950.00$950.00$950.00$300.00
155Special 03. emergency response to traffic involving concrete barrier temporary (SPV.0060)EACH10$0.01$325.00$2,000.00$1,950.80
156Special 04. emergency response to traffic involving crash cushion temporary (SPV.0060)EACH10$325.00$325.00$325.00$325.00
157Special 05. construction staking survey project 1130-66-80 (SPV.0060)EACH1$9,950.00$9,950.00$9,950.00$9,950.00
158Special 06. construction staking survey project 1130-66-81 (SPV.0060)EACH1$9,950.00$9,950.00$9,950.00$9,950.00
159Special 07. temporary water diversion C-44-153 (SPV.0060)EACH1$27,000$27,000$27,000$95,000
160Special 01. street sweeping (SPV.0075)HRS70$0.01$0.01$150.00$225.00
161Special 01. longitudinal grooving bridge deck (SPV.0165)SF14,868$0.77$1.37$0.77$0.74
162Special 01. external joint sealer (SPV.0180)SY168$50.00$50.00$50.00$150.00
WisDOT contract 20250114042: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy