WisDOT contract 20250211011 bid tabulation
City of Onalaska, Theater Road; CTH Os to Midwest Drive (LOC STR, La Crosse County City of Onalaska, Theater Road). Let by Wisconsin DOT on February 11, 2025, La Crosse. 2 bids received; low bid $417,550 by Pember Companies, Inc..
- Owner
- Wisconsin DOT
- Letting
- 11 FEB 2025
- Pay items
- 90
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pember Companies, Inc. | $417,550 | Low |
| 2 | Chippewa Concrete Services, Inc. | $436,831 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pember Companies, Inc. | 2. Chippewa Concrete Services, Inc. |
|---|---|---|---|---|---|
| 1 | Removing asphaltic surface (204.0110) | SY | 29 | $56.00 | $56.60 |
| 2 | Removing asphaltic surface butt joints (204.0115) | SY | 47 | $48.20 | $46.47 |
| 3 | Removing asphaltic surface milling (204.0120) | SY | 4,325 | $4.80 | $4.63 |
| 4 | Removing curb & gutter (204.0150) | LF | 132 | $24.50 | $24.87 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 180 | $48.00 | $27.31 |
| 6 | Removing concrete bases (204.0195) | EACH | 1 | $1,645.00 | $467.77 |
| 7 | Removing (item description) 01. removing traffic signals (main ST & theater road) (204.9060.S) | EACH | 1 | $5,285.00 | $2,316.36 |
| 8 | Prepare foundation for asphaltic paving (project) 01. 5991-02-71 (211.0101) | EACH | 1 | $1,600.00 | $8,477.73 |
| 9 | Finishing roadway (project) 01. 5991-02-71 (213.0100) | EACH | 1 | $500.00 | $2,555.00 |
| 10 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 10 | $107.00 | $124.49 |
| 11 | Drilled tie bars (416.0610) | EACH | 16 | $7.50 | $16.38 |
| 12 | Tack coat (455.0605) | GAL | 306 | $5.20 | $5.01 |
| 13 | Incentive density HMA pavement (460.2000) | DOL | 310 | $1.00 | $1.00 |
| 14 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 490 | $111.00 | $106.90 |
| 15 | Asphaltic surface (465.0105) | TON | 8 | $306.00 | $294.60 |
| 16 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 132 | $46.00 | $118.63 |
| 17 | Concrete sidewalk 5-inch (602.0410) | SF | 1,453 | $8.10 | $24.52 |
| 18 | Curb ramp detectable warning field yellow (602.0505) | SF | 20 | $56.00 | $63.89 |
| 19 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 57 | $68.00 | $69.33 |
| 20 | Maintenance and repair of haul roads (project) 01. 5991-02-71 (618.0100) | EACH | 1 | $500.00 | $1,022.00 |
| 21 | Mobilization (619.1000) | EACH | 1 | $66,700 | $57,724 |
| 22 | Salvaged topsoil (625.0500) | SY | 180 | $35.00 | $19.82 |
| 23 | Silt fence (628.1504) | LF | 95 | $4.25 | $5.11 |
| 24 | Silt fence maintenance (628.1520) | LF | 95 | $1.00 | $0.10 |
| 25 | Mobilizations erosion control (628.1905) | EACH | 2 | $320.00 | $408.80 |
| 26 | Mobilizations emergency erosion control (628.1910) | EACH | 1 | $530.00 | $204.40 |
| 27 | Erosion mat urban class I type A (628.2006) | SY | 180 | $2.70 | $4.09 |
| 28 | Inlet protection type C (628.7015) | EACH | 8 | $80.00 | $51.10 |
| 29 | Fertilizer type A (629.0205) | CWT | 0.20 | $740.00 | $306.60 |
| 30 | Seeding mixture no. 40 (630.0140) | LB | 3.10 | $90.00 | $51.10 |
| 31 | Seeding temporary (630.0200) | LB | 4.60 | $50.00 | $5.11 |
| 32 | Seed water (630.0500) | MGAL | 3.90 | $50.00 | $255.50 |
| 33 | Field office type B (642.5001) | EACH | 1 | $10,000 | $7,665.00 |
| 34 | Traffic control drums (643.0300) | DAY | 1,468 | $0.80 | $0.41 |
| 35 | Traffic control barricades type III (643.0420) | DAY | 144 | $3.20 | $1.02 |
| 36 | Traffic control warning lights type A (643.0705) | DAY | 288 | $0.25 | $0.20 |
| 37 | Traffic control warning lights type C (643.0715) | DAY | 368 | $0.25 | $0.22 |
| 38 | Traffic control arrow boards (643.0800) | DAY | 54 | $21.00 | $10.22 |
| 39 | Traffic control signs (643.0900) | DAY | 886 | $0.70 | $0.77 |
| 40 | Traffic control covering signs type II (643.0920) | EACH | 19 | $53.00 | $86.87 |
| 41 | Traffic control signs PCMS (643.1050) | DAY | 18 | $106.00 | $25.55 |
| 42 | Temporary marking line removable tape 4-inch (643.3150) | LF | 1,274 | $1.05 | $1.48 |
| 43 | Temporary marking line removable tape 6-inch (643.3180) | LF | 1,032 | $1.60 | $2.20 |
| 44 | Temporary marking line removable tape 8-inch (643.3250) | LF | 225 | $2.10 | $3.32 |
| 45 | Temporary marking arrow removable tape (643.3550) | EACH | 24 | $80.00 | $153.30 |
| 46 | Temporary marking word removable tape (643.3650) | EACH | 1 | $80.00 | $255.50 |
| 47 | Temporary marking removable mask out tape 6-inch (643.3960) | LF | 536 | $3.20 | $3.07 |
| 48 | Temporary marking removable mask out tape 10-inch (643.3970) | LF | 156 | $5.30 | $4.60 |
| 49 | Traffic control (643.5000) | EACH | 1 | $12,000 | $6,515.25 |
| 50 | Temporary pedestrian curb ramp (644.1601) | DAY | 16 | $53.00 | $40.88 |
| 51 | Temporary pedestrian detectable warning field (644.1605) | SF | 80 | $16.00 | $7.15 |
| 52 | Temporary pedestrian barricade (644.1810) | LF | 368 | $5.25 | $5.62 |
| 53 | Marking line epoxy 4-inch (646.1020) | LF | 3,773 | $1.75 | $1.02 |
| 54 | Marking line epoxy 8-inch (646.3020) | LF | 583 | $2.00 | $2.04 |
| 55 | Marking arrow epoxy (646.5020) | EACH | 22 | $300.00 | $459.90 |
| 56 | Marking word epoxy (646.5120) | EACH | 5 | $330.00 | $529.40 |
| 57 | Marking stop line epoxy 18-inch (646.6120) | LF | 145 | $20.00 | $19.62 |
| 58 | Marking island nose epoxy (646.8220) | EACH | 4 | $260.00 | $363.27 |
| 59 | Marking removal line water blasting 10-inch (646.9112) | LF | 277 | $2.10 | $12.78 |
| 60 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 132 | $1.05 | $4.09 |
| 61 | Construction staking resurfacing reference (650.8000) | LF | 710 | $0.25 | $2.04 |
| 62 | Construction staking electrical installations (project) 01. 5991-02- 71 (650.8501) | EACH | 1 | $2,125.00 | $1,481.90 |
| 63 | Construction staking curb ramps (650.9000) | EACH | 6 | $10.50 | $122.64 |
| 64 | Construction staking sidewalk (project) 01. 5991-02-71 (650.9500) | EACH | 1 | $100.00 | $1,635.20 |
| 65 | Construction staking supplemental control (project) 01. 5991-02-71 (650.9911) | EACH | 1 | $3,500.00 | $664.30 |
| 66 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 153 | $16.25 | $15.64 |
| 67 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 410 | $14.20 | $13.66 |
| 68 | Conduit special 3-inch (652.0615) | LF | 684 | $23.30 | $22.44 |
| 69 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 11 | $2,300.00 | $2,215.52 |
| 70 | Removing pull boxes (653.0905) | EACH | 11 | $275.00 | $264.76 |
| 71 | Concrete bases type 1 (654.0101) | EACH | 6 | $915.00 | $880.18 |
| 72 | Concrete control cabinet bases type 9 special (654.0217) | EACH | 1 | $1,500.00 | $1,440.95 |
| 73 | Cable traffic signal 5-14 AWG (655.0230) | LF | 90 | $3.25 | $3.09 |
| 74 | Cable traffic signal 7-14 AWG (655.0240) | LF | 3,167 | $1.90 | $1.84 |
| 75 | Cable traffic signal 12-14 AWG (655.0260) | LF | 960 | $3.15 | $3.03 |
| 76 | Cable type UF 2-12 AWG grounded (655.0305) | LF | 864 | $1.65 | $1.55 |
| 77 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 1,648 | $0.90 | $0.88 |
| 78 | Traffic signal evp detector cable (655.0900) | LF | 229 | $1.75 | $1.70 |
| 79 | Electrical service meter breaker pedestal (location) 01. east main street & theater road (656.0201) | EACH | 1 | $2,615.00 | $2,517.51 |
| 80 | Pedestal bases (657.0100) | EACH | 7 | $375.00 | $360.31 |
| 81 | Traffic signal standards aluminum 15-FT (657.0425) | EACH | 1 | $960.00 | $921.32 |
| 82 | Traffic signal standards aluminum 10-FT (657.0430) | EACH | 6 | $850.00 | $818.62 |
| 83 | Traffic signal face 5S 12-inch (658.0175) | EACH | 2 | $1,500.00 | $1,437.13 |
| 84 | Pedestrian signal face 16-inch (658.0416) | EACH | 6 | $705.00 | $678.22 |
| 85 | Signal mounting hardware (location) 01. east main street & theater road (658.5070) | EACH | 1 | $5,135.00 | $4,946.20 |
| 86 | Sawing asphalt (690.0150) | LF | 381 | $2.55 | $1.99 |
| 87 | Sawing concrete (690.0250) | LF | 53 | $3.65 | $3.01 |
| 88 | Special 01. APS push button (SPV.0060) | EACH | 6 | $1,425.00 | $1,373.61 |
| 89 | Special 02. furnish & install traffic signal cabinet & controller (main ST & theater RD) (SPV.0060) | EACH | 1 | $32,000 | $30,841 |
| 90 | Special 01. marking crosswalk epoxy transverse line 12-inch (SPV.0090) | LF | 485 | $15.10 | $26.37 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.