WisDOT contract 20250211051 bid tabulation

Spooner - STH 77; USH 63 to Sunset Lane (CTH K, Washburn County Spooner - STH 77). Let by Wisconsin DOT on February 11, 2025, Washburn. 4 bids received; low bid $2,013,697 by James Peterson Sons, Inc..

Owner
Wisconsin DOT
Letting
11 FEB 2025
Pay items
87
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1James Peterson Sons, Inc.$2,013,697Low
2McCabe Construction, Inc.$2,086,135+4.0%
3A-1 Excavating LLC$2,089,676+4.0%
4Haas Sons, Inc.$2,099,009+4.0%
WisDOT contract 20250211051: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. James Peterson Sons, Inc.2. McCabe Construction, Inc.3. A-1 Excavating LLC4. Haas Sons, Inc.
1Removing concrete pavement (204.0100)SY324$5.95$10.00$12.00$18.00
2Removing asphaltic surface butt joints (204.0115)SY577$10.50$8.50$10.00$7.50
3Removing curb & gutter (204.0150)LF3,454$2.00$5.00$3.00$3.25
4Removing concrete sidewalk (204.0155)SY126$8.58$9.00$12.00$10.00
5Removing inlets (204.0220)EACH10$799.00$300.00$400.00$850.00
6Excavation common (205.0100)CY5,215$13.29$17.00$18.00$14.99
7Finishing roadway (project) 01. 8800-00-70 (213.0100)EACH1$2,000.00$2,500.00$300.00$1.00
8Base aggregate dense 3/4-inch (305.0110)TON1,726$23.21$26.00$25.00$20.39
9Base aggregate dense 1 1/4-inch (305.0120)TON6,527$21.12$18.00$20.00$16.39
10Pulverize and relay (325.0100)SY35,474$1.47$1.93$2.50$1.20
11QMP pulverize and relay compaction (374.1020.S)SY35,474$0.20$0.21$0.30$0.17
12Tack coat (455.0605)GAL3,363$3.38$3.55$3.45$3.38
13HMA pavement 3 LT 58-28 S (460.5223)TON6,627$86.42$91.00$88.15$91.70
14HMA pavement 4 LT 58-34 S (460.5244)TON4,639$95.16$100.00$97.06$95.16
15Asphaltic surface driveways and field entrances (465.0120)TON76$174.68$184.00$194.00$174.68
16Asphaltic flumes (465.0315)SY32$131.11$112.00$126.00$106.11
17Asphaltic rumble strips, centerline (465.0560)LF6,465$0.65$0.70$1.00$0.65
18Apron endwalls for culvert pipe 12- inch (520.1012)EACH1$689.00$1,150.00$1,504.00$1,450.00
19Concrete collars for pipe (520.8000)EACH2$2,500.00$1,400.00$1,000.00$850.00
20Concrete curb & gutter 30-inch type D (601.0411)LF4,197$20.00$21.00$20.60$15.90
21Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF303$28.00$29.40$28.80$20.80
22Concrete sidewalk 4-inch (602.0405)SF2,879$8.50$8.95$8.80$5.70
23Curb ramp detectable warning field yellow (602.0505)SF210$65.00$68.30$67.00$46.00
24Concrete driveway 6-inch (602.0810)SY324$81.00$85.10$83.00$72.20
25Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF174$224.93$116.00$118.00$133.00
26Storm sewer pipe reinforced concrete class III 15-inch (608.0315)LF213$121.94$125.00$111.00$105.00
27Inlet covers type H (611.0624)EACH7$1,213.00$900.00$1,156.00$1,250.00
28Inlet covers type H-S (611.0639)EACH4$1,213.00$900.00$1,156.00$1,250.00
29Inlets 2X3-FT (611.3230)EACH11$2,772.00$2,500.00$2,873.00$3,800.00
30Adjusting manhole covers (611.8110)EACH14$1,089.00$530.00$200.00$850.00
31Cover plates temporary (611.8120.S)EACH12$250.00$285.00$200.00$350.00
32Insulation board polystyrene (inch) 01. 2-inch (612.0902.S)SY16$50.00$40.00$26.00$21.25
33Maintenance and repair of haul roads (project) 01. 8800-00-70 (618.0100)EACH1$150.00$1.00$300.00$1.00
34Mobilization (619.1000)EACH1$133,050$155,503$148,420$167,730
35Water (624.0100)MGAL122$45.00$43.00$30.00$60.00
36Topsoil (625.0100)SY2,265$9.87$10.50$6.00$8.40
37Silt fence (628.1504)LF70$2.25$2.35$2.36$4.00
38Silt fence maintenance (628.1520)LF70$0.01$0.01$0.01$0.01
39Mobilizations erosion control (628.1905)EACH1$990.00$1,040.00$1,040.00$125.00
40Mobilizations emergency erosion control (628.1910)EACH1$10.00$10.50$10.50$175.00
41Erosion mat urban class I type A (628.2006)SY2,265$1.86$1.95$1.95$3.00
42Inlet protection type C (628.7015)EACH18$65.00$59.00$68.00$50.00
43Culvert pipe checks (628.7555)EACH1$50.00$52.50$53.00$100.00
44Fertilizer type B (629.0210)CWT1.40$360.00$378.00$378.00$170.00
45Seeding mixture no. 40 (630.0140)LB102$24.60$25.85$26.00$35.00
46Seed water (630.0500)MGAL25$100.00$105.00$105.00$0.01
47Posts wood 4X6-inch X 14-FT (634.0614)EACH53$66.50$70.00$70.00$90.00
48Posts wood 4X6-inch X 16-FT (634.0616)EACH25$72.50$76.00$76.00$100.00
49Signs type II reflective H (637.2210)SF455.70$13.45$14.00$14.00$19.50
50Signs type II reflective F (637.2230)SF115.50$16.80$17.65$18.00$22.00
51Removing signs type II (638.2602)EACH108$17.25$18.00$18.00$25.00
52Removing small sign supports (638.3000)EACH71$13.80$14.50$15.00$25.00
53Field office type B (642.5001)EACH1$10,000$8,000.00$9,000.00$28,500
54Traffic control drums (643.0300)DAY3,000$0.50$0.53$0.55$0.50
55Traffic control barricades type III (643.0420)DAY1,764$0.57$0.60$0.63$0.57
56Traffic control warning lights type A (643.0705)DAY3,528$0.13$0.15$0.14$0.13
57Traffic control signs (643.0900)DAY4,880$0.55$0.60$0.61$0.55
58Traffic control signs fixed message (643.1000)SF96$20.00$21.00$22.00$20.00
59Traffic control (643.5000)EACH1$1,925.00$2,020.00$4,925.00$59,525
60Temporary pedestrian surface matting (644.1440)SF2,276$1.05$1.10$1.16$1.05
61Temporary pedestrian curb ramp (644.1601)DAY600$5.25$5.50$5.78$5.25
62Temporary pedestrian detectable warning field (644.1605)SF96$10.00$10.50$11.00$10.00
63Temporary pedestrian barricade (644.1810)LF475$2.50$2.60$2.75$4.50
64Geotextile type sas (645.0140)SY12,238$1.67$1.65$2.00$1.85
65Marking line epoxy 4-inch (646.1020)LF9,058$0.65$0.49$0.68$0.65
66Marking line epoxy 6-inch (646.2020)LF34,164$0.80$0.62$0.84$0.80
67Marking line epoxy 8-inch (646.3020)LF36$1.30$1.24$1.37$1.30
68Marking line epoxy 10-inch (646.4020)LF428$1.45$1.36$1.52$1.45
69Marking arrow epoxy (646.5020)EACH6$300.00$413.00$315.00$300.00
70Marking word epoxy (646.5120)EACH10$350.00$475.00$368.00$350.00
71Marking stop line epoxy 18-inch (646.6120)LF371$20.00$17.60$21.00$20.00
72Marking crosswalk epoxy transverse line 6-inch (646.7420)LF425$16.00$16.35$16.80$16.00
73Marking crosswalk epoxy block style 24-inch (646.7520)LF96$24.50$28.50$26.00$24.50
74Construction staking storm sewer (650.4000)EACH21$80.00$84.00$330.00$300.00
75Construction staking subgrade (650.4500)LF3,427$0.01$0.01$0.01$1.00
76Construction staking base (650.5000)LF3,427$0.45$0.47$1.10$1.00
77Construction staking curb gutter and curb & gutter (650.5500)LF4,500$0.82$0.86$1.10$1.00
78Construction staking resurfacing reference (650.8000)LF10,523$0.10$0.11$0.11$0.10
79Construction staking curb ramps (650.9000)EACH17$215.00$226.00$11.00$10.00
80Construction staking sidewalk (project) 01. 8800-00-70 (650.9500)EACH1$426.28$4,411.00$2,200.00$2,000.00
81Construction staking supplemental control (project) 01. 8800-00-70 (650.9911)EACH1$4,200.00$448.00$3,300.00$3,000.00
82Sawing asphalt (690.0150)LF889$2.49$2.00$3.00$2.49
83Sawing concrete (690.0250)LF422$3.30$3.40$5.00$3.30
84Incentive iri ride (740.0440)DOL9,547$1.00$1.00$1.00$1.00
85On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS800$5.00$5.00$5.00$5.00
86On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00$5.00
87Special 01. manhole core with concrete replacement (SPV.0060)EACH12$1,200.00$1,230.00$1,100.00$1,525.00
WisDOT contract 20250211051: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy