WisDOT contract 20250211051 bid tabulation
Spooner - STH 77; USH 63 to Sunset Lane (CTH K, Washburn County Spooner - STH 77). Let by Wisconsin DOT on February 11, 2025, Washburn. 4 bids received; low bid $2,013,697 by James Peterson Sons, Inc..
- Owner
- Wisconsin DOT
- Letting
- 11 FEB 2025
- Pay items
- 87
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | James Peterson Sons, Inc. | $2,013,697 | Low |
| 2 | McCabe Construction, Inc. | $2,086,135 | +4.0% |
| 3 | A-1 Excavating LLC | $2,089,676 | +4.0% |
| 4 | Haas Sons, Inc. | $2,099,009 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. James Peterson Sons, Inc. | 2. McCabe Construction, Inc. | 3. A-1 Excavating LLC | 4. Haas Sons, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 324 | $5.95 | $10.00 | $12.00 | $18.00 |
| 2 | Removing asphaltic surface butt joints (204.0115) | SY | 577 | $10.50 | $8.50 | $10.00 | $7.50 |
| 3 | Removing curb & gutter (204.0150) | LF | 3,454 | $2.00 | $5.00 | $3.00 | $3.25 |
| 4 | Removing concrete sidewalk (204.0155) | SY | 126 | $8.58 | $9.00 | $12.00 | $10.00 |
| 5 | Removing inlets (204.0220) | EACH | 10 | $799.00 | $300.00 | $400.00 | $850.00 |
| 6 | Excavation common (205.0100) | CY | 5,215 | $13.29 | $17.00 | $18.00 | $14.99 |
| 7 | Finishing roadway (project) 01. 8800-00-70 (213.0100) | EACH | 1 | $2,000.00 | $2,500.00 | $300.00 | $1.00 |
| 8 | Base aggregate dense 3/4-inch (305.0110) | TON | 1,726 | $23.21 | $26.00 | $25.00 | $20.39 |
| 9 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 6,527 | $21.12 | $18.00 | $20.00 | $16.39 |
| 10 | Pulverize and relay (325.0100) | SY | 35,474 | $1.47 | $1.93 | $2.50 | $1.20 |
| 11 | QMP pulverize and relay compaction (374.1020.S) | SY | 35,474 | $0.20 | $0.21 | $0.30 | $0.17 |
| 12 | Tack coat (455.0605) | GAL | 3,363 | $3.38 | $3.55 | $3.45 | $3.38 |
| 13 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 6,627 | $86.42 | $91.00 | $88.15 | $91.70 |
| 14 | HMA pavement 4 LT 58-34 S (460.5244) | TON | 4,639 | $95.16 | $100.00 | $97.06 | $95.16 |
| 15 | Asphaltic surface driveways and field entrances (465.0120) | TON | 76 | $174.68 | $184.00 | $194.00 | $174.68 |
| 16 | Asphaltic flumes (465.0315) | SY | 32 | $131.11 | $112.00 | $126.00 | $106.11 |
| 17 | Asphaltic rumble strips, centerline (465.0560) | LF | 6,465 | $0.65 | $0.70 | $1.00 | $0.65 |
| 18 | Apron endwalls for culvert pipe 12- inch (520.1012) | EACH | 1 | $689.00 | $1,150.00 | $1,504.00 | $1,450.00 |
| 19 | Concrete collars for pipe (520.8000) | EACH | 2 | $2,500.00 | $1,400.00 | $1,000.00 | $850.00 |
| 20 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 4,197 | $20.00 | $21.00 | $20.60 | $15.90 |
| 21 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 303 | $28.00 | $29.40 | $28.80 | $20.80 |
| 22 | Concrete sidewalk 4-inch (602.0405) | SF | 2,879 | $8.50 | $8.95 | $8.80 | $5.70 |
| 23 | Curb ramp detectable warning field yellow (602.0505) | SF | 210 | $65.00 | $68.30 | $67.00 | $46.00 |
| 24 | Concrete driveway 6-inch (602.0810) | SY | 324 | $81.00 | $85.10 | $83.00 | $72.20 |
| 25 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 174 | $224.93 | $116.00 | $118.00 | $133.00 |
| 26 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 213 | $121.94 | $125.00 | $111.00 | $105.00 |
| 27 | Inlet covers type H (611.0624) | EACH | 7 | $1,213.00 | $900.00 | $1,156.00 | $1,250.00 |
| 28 | Inlet covers type H-S (611.0639) | EACH | 4 | $1,213.00 | $900.00 | $1,156.00 | $1,250.00 |
| 29 | Inlets 2X3-FT (611.3230) | EACH | 11 | $2,772.00 | $2,500.00 | $2,873.00 | $3,800.00 |
| 30 | Adjusting manhole covers (611.8110) | EACH | 14 | $1,089.00 | $530.00 | $200.00 | $850.00 |
| 31 | Cover plates temporary (611.8120.S) | EACH | 12 | $250.00 | $285.00 | $200.00 | $350.00 |
| 32 | Insulation board polystyrene (inch) 01. 2-inch (612.0902.S) | SY | 16 | $50.00 | $40.00 | $26.00 | $21.25 |
| 33 | Maintenance and repair of haul roads (project) 01. 8800-00-70 (618.0100) | EACH | 1 | $150.00 | $1.00 | $300.00 | $1.00 |
| 34 | Mobilization (619.1000) | EACH | 1 | $133,050 | $155,503 | $148,420 | $167,730 |
| 35 | Water (624.0100) | MGAL | 122 | $45.00 | $43.00 | $30.00 | $60.00 |
| 36 | Topsoil (625.0100) | SY | 2,265 | $9.87 | $10.50 | $6.00 | $8.40 |
| 37 | Silt fence (628.1504) | LF | 70 | $2.25 | $2.35 | $2.36 | $4.00 |
| 38 | Silt fence maintenance (628.1520) | LF | 70 | $0.01 | $0.01 | $0.01 | $0.01 |
| 39 | Mobilizations erosion control (628.1905) | EACH | 1 | $990.00 | $1,040.00 | $1,040.00 | $125.00 |
| 40 | Mobilizations emergency erosion control (628.1910) | EACH | 1 | $10.00 | $10.50 | $10.50 | $175.00 |
| 41 | Erosion mat urban class I type A (628.2006) | SY | 2,265 | $1.86 | $1.95 | $1.95 | $3.00 |
| 42 | Inlet protection type C (628.7015) | EACH | 18 | $65.00 | $59.00 | $68.00 | $50.00 |
| 43 | Culvert pipe checks (628.7555) | EACH | 1 | $50.00 | $52.50 | $53.00 | $100.00 |
| 44 | Fertilizer type B (629.0210) | CWT | 1.40 | $360.00 | $378.00 | $378.00 | $170.00 |
| 45 | Seeding mixture no. 40 (630.0140) | LB | 102 | $24.60 | $25.85 | $26.00 | $35.00 |
| 46 | Seed water (630.0500) | MGAL | 25 | $100.00 | $105.00 | $105.00 | $0.01 |
| 47 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 53 | $66.50 | $70.00 | $70.00 | $90.00 |
| 48 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 25 | $72.50 | $76.00 | $76.00 | $100.00 |
| 49 | Signs type II reflective H (637.2210) | SF | 455.70 | $13.45 | $14.00 | $14.00 | $19.50 |
| 50 | Signs type II reflective F (637.2230) | SF | 115.50 | $16.80 | $17.65 | $18.00 | $22.00 |
| 51 | Removing signs type II (638.2602) | EACH | 108 | $17.25 | $18.00 | $18.00 | $25.00 |
| 52 | Removing small sign supports (638.3000) | EACH | 71 | $13.80 | $14.50 | $15.00 | $25.00 |
| 53 | Field office type B (642.5001) | EACH | 1 | $10,000 | $8,000.00 | $9,000.00 | $28,500 |
| 54 | Traffic control drums (643.0300) | DAY | 3,000 | $0.50 | $0.53 | $0.55 | $0.50 |
| 55 | Traffic control barricades type III (643.0420) | DAY | 1,764 | $0.57 | $0.60 | $0.63 | $0.57 |
| 56 | Traffic control warning lights type A (643.0705) | DAY | 3,528 | $0.13 | $0.15 | $0.14 | $0.13 |
| 57 | Traffic control signs (643.0900) | DAY | 4,880 | $0.55 | $0.60 | $0.61 | $0.55 |
| 58 | Traffic control signs fixed message (643.1000) | SF | 96 | $20.00 | $21.00 | $22.00 | $20.00 |
| 59 | Traffic control (643.5000) | EACH | 1 | $1,925.00 | $2,020.00 | $4,925.00 | $59,525 |
| 60 | Temporary pedestrian surface matting (644.1440) | SF | 2,276 | $1.05 | $1.10 | $1.16 | $1.05 |
| 61 | Temporary pedestrian curb ramp (644.1601) | DAY | 600 | $5.25 | $5.50 | $5.78 | $5.25 |
| 62 | Temporary pedestrian detectable warning field (644.1605) | SF | 96 | $10.00 | $10.50 | $11.00 | $10.00 |
| 63 | Temporary pedestrian barricade (644.1810) | LF | 475 | $2.50 | $2.60 | $2.75 | $4.50 |
| 64 | Geotextile type sas (645.0140) | SY | 12,238 | $1.67 | $1.65 | $2.00 | $1.85 |
| 65 | Marking line epoxy 4-inch (646.1020) | LF | 9,058 | $0.65 | $0.49 | $0.68 | $0.65 |
| 66 | Marking line epoxy 6-inch (646.2020) | LF | 34,164 | $0.80 | $0.62 | $0.84 | $0.80 |
| 67 | Marking line epoxy 8-inch (646.3020) | LF | 36 | $1.30 | $1.24 | $1.37 | $1.30 |
| 68 | Marking line epoxy 10-inch (646.4020) | LF | 428 | $1.45 | $1.36 | $1.52 | $1.45 |
| 69 | Marking arrow epoxy (646.5020) | EACH | 6 | $300.00 | $413.00 | $315.00 | $300.00 |
| 70 | Marking word epoxy (646.5120) | EACH | 10 | $350.00 | $475.00 | $368.00 | $350.00 |
| 71 | Marking stop line epoxy 18-inch (646.6120) | LF | 371 | $20.00 | $17.60 | $21.00 | $20.00 |
| 72 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 425 | $16.00 | $16.35 | $16.80 | $16.00 |
| 73 | Marking crosswalk epoxy block style 24-inch (646.7520) | LF | 96 | $24.50 | $28.50 | $26.00 | $24.50 |
| 74 | Construction staking storm sewer (650.4000) | EACH | 21 | $80.00 | $84.00 | $330.00 | $300.00 |
| 75 | Construction staking subgrade (650.4500) | LF | 3,427 | $0.01 | $0.01 | $0.01 | $1.00 |
| 76 | Construction staking base (650.5000) | LF | 3,427 | $0.45 | $0.47 | $1.10 | $1.00 |
| 77 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 4,500 | $0.82 | $0.86 | $1.10 | $1.00 |
| 78 | Construction staking resurfacing reference (650.8000) | LF | 10,523 | $0.10 | $0.11 | $0.11 | $0.10 |
| 79 | Construction staking curb ramps (650.9000) | EACH | 17 | $215.00 | $226.00 | $11.00 | $10.00 |
| 80 | Construction staking sidewalk (project) 01. 8800-00-70 (650.9500) | EACH | 1 | $426.28 | $4,411.00 | $2,200.00 | $2,000.00 |
| 81 | Construction staking supplemental control (project) 01. 8800-00-70 (650.9911) | EACH | 1 | $4,200.00 | $448.00 | $3,300.00 | $3,000.00 |
| 82 | Sawing asphalt (690.0150) | LF | 889 | $2.49 | $2.00 | $3.00 | $2.49 |
| 83 | Sawing concrete (690.0250) | LF | 422 | $3.30 | $3.40 | $5.00 | $3.30 |
| 84 | Incentive iri ride (740.0440) | DOL | 9,547 | $1.00 | $1.00 | $1.00 | $1.00 |
| 85 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 800 | $5.00 | $5.00 | $5.00 | $5.00 |
| 86 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 | $5.00 |
| 87 | Special 01. manhole core with concrete replacement (SPV.0060) | EACH | 12 | $1,200.00 | $1,230.00 | $1,100.00 | $1,525.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.