WisDOT contract 20250311010 bid tabulation
5998-00-01. Let by Wisconsin DOT on March 11, 2025, Dane. 5 bids received; low bid $1,648,139 by James Peterson Sons, Inc..
- Owner
- Wisconsin DOT
- Letting
- 11 MAR 2025
- Pay items
- 100
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | James Peterson Sons, Inc. | $1,648,139 | Low |
| 2 | Parisi Construction, LLC | $1,749,191 | +6.0% |
| 3 | Speedway Sand & Gravel, Inc. | $1,881,971 | +14% |
| 4 | Fischer Excavating, Inc. | $1,920,943 | +17% |
| 5 | R.G. Huston Company, Inc. | $1,965,600 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. James Peterson Sons, Inc. | 2. Parisi Construction, LLC | 3. Speedway Sand & Gravel, Inc. | 4. Fischer Excavating, Inc. | 5. R.G. Huston Company, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing curb & gutter (204.0150) | LF | 3,180 | $2.36 | $3.60 | $2.90 | $4.00 | $4.00 |
| 2 | Removing concrete sidewalk (204.0155) | SY | 800 | $6.12 | $14.25 | $5.30 | $16.00 | $7.00 |
| 3 | Removing inlets (204.0220) | EACH | 6 | $400.00 | $590.00 | $475.00 | $500.00 | $800.00 |
| 4 | Removing storm sewer (size) 001. 12-inch (204.0245) | LF | 220 | $23.44 | $26.25 | $31.00 | $17.00 | $20.00 |
| 5 | Excavation common (205.0100) | CY | 5,529 | $16.20 | $20.00 | $24.50 | $42.00 | $21.00 |
| 6 | Backfill granular grade 1 (209.1500) | TON | 100 | $15.00 | $19.00 | $26.95 | $25.00 | $36.00 |
| 7 | Finishing roadway (project) 001. 5998-00-01 (213.0100) | EACH | 1 | $1,000.00 | $790.00 | $1,000.00 | $12,000 | $4,000.00 |
| 8 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 3,107 | $20.10 | $17.25 | $22.95 | $19.00 | $23.00 |
| 9 | Base aggregate dense 3-inch (305.0130) | TON | 1,339 | $18.75 | $20.25 | $19.70 | $19.00 | $20.00 |
| 10 | Tack coat (455.0605) | GAL | 305 | $2.00 | $2.10 | $2.00 | $2.00 | $2.00 |
| 11 | Incentive density HMA pavement (460.2000) | DOL | 1,100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 12 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 1,030 | $76.00 | $78.00 | $76.00 | $76.00 | $76.00 |
| 13 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 685 | $77.00 | $79.00 | $77.00 | $77.00 | $77.00 |
| 14 | Asphaltic surface driveways and field entrances (465.0120) | TON | 13 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 15 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 1 | $1,360.21 | $1,900.00 | $1,955.00 | $1,300.00 | $2,200.00 |
| 16 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 3,320 | $20.45 | $20.00 | $24.50 | $21.10 | $21.31 |
| 17 | Concrete curb pedestrian (601.0600) | LF | 50 | $45.00 | $50.00 | $49.50 | $48.00 | $48.48 |
| 18 | Concrete sidewalk 5-inch (602.0410) | SF | 800 | $7.25 | $8.20 | $6.85 | $10.00 | $7.37 |
| 19 | Concrete sidewalk 6-inch (602.0415) | SF | 11,200 | $7.25 | $8.40 | $7.05 | $8.70 | $6.06 |
| 20 | Curb ramp detectable warning field yellow (602.0505) | SF | 30 | $50.00 | $32.00 | $48.00 | $45.00 | $45.45 |
| 21 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 140 | $70.00 | $55.00 | $93.00 | $65.00 | $65.66 |
| 22 | Concrete driveway 6-inch (602.0810) | SY | 169 | $70.00 | $65.00 | $66.60 | $90.00 | $66.36 |
| 23 | Riprap medium (606.0200) | CY | 2.20 | $250.00 | $130.00 | $805.00 | $150.00 | $300.00 |
| 24 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 467 | $98.82 | $87.00 | $84.40 | $95.00 | $120.00 |
| 25 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 327 | $70.45 | $76.00 | $92.25 | $97.00 | $126.00 |
| 26 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 504 | $73.88 | $86.00 | $98.60 | $115.00 | $133.00 |
| 27 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 174 | $127.08 | $94.00 | $132.10 | $117.00 | $147.00 |
| 28 | Inlet covers type C (611.0612) | EACH | 8 | $1,232.59 | $1,100.00 | $937.00 | $520.00 | $1,200.00 |
| 29 | Inlet covers type H (611.0624) | EACH | 13 | $1,628.92 | $1,300.00 | $1,160.00 | $765.00 | $1,500.00 |
| 30 | Inlet covers type H-S (611.0639) | EACH | 5 | $1,628.92 | $1,300.00 | $1,160.00 | $765.00 | $1,500.00 |
| 31 | Manholes 4-FT diameter (611.2004) | EACH | 4 | $2,151.11 | $3,000.00 | $5,385.00 | $3,500.00 | $1,900.00 |
| 32 | Manholes 5-FT diameter (611.2005) | EACH | 4 | $3,702.86 | $4,000.00 | $4,480.00 | $4,500.00 | $3,800.00 |
| 33 | Manholes 6-FT diameter (611.2006) | EACH | 2 | $9,275.64 | $9,400.00 | $11,599 | $12,500 | $10,600 |
| 34 | Inlets 2X3-FT (611.3230) | EACH | 16 | $1,357.50 | $2,200.00 | $2,982.00 | $3,100.00 | $1,600.00 |
| 35 | Pipe underdrain 6-inch (612.0106) | LF | 200 | $17.00 | $16.50 | $11.55 | $19.00 | $21.00 |
| 36 | Insulation board polystyrene (inch) 001. 2-inch (612.0902.S) | SY | 25 | $27.00 | $43.25 | $38.00 | $28.00 | $40.00 |
| 37 | Mobilization (619.1000) | EACH | 1 | $148,400 | $160,000 | $103,572 | $95,000 | $124,245 |
| 38 | Water (624.0100) | MGAL | 50 | $50.00 | $29.75 | $1.00 | $0.01 | $77.00 |
| 39 | Topsoil (625.0100) | SY | 3,333 | $5.57 | $7.30 | $8.85 | $6.50 | $8.00 |
| 40 | Mulching (627.0200) | SY | 8,889 | $0.25 | $1.00 | $0.40 | $0.25 | $0.25 |
| 41 | Silt fence (628.1504) | LF | 980 | $2.50 | $3.10 | $2.05 | $2.50 | $2.50 |
| 42 | Silt fence maintenance (628.1520) | LF | 980 | $0.10 | $0.01 | $0.01 | $0.10 | $0.10 |
| 43 | Mobilizations erosion control (628.1905) | EACH | 3 | $250.00 | $260.00 | $200.00 | $250.00 | $250.00 |
| 44 | Mobilizations emergency erosion control (628.1910) | EACH | 1 | $300.00 | $100.00 | $200.00 | $300.00 | $300.00 |
| 45 | Erosion mat urban class I type A (628.2006) | SY | 2,280 | $1.80 | $3.61 | $1.70 | $1.80 | $1.80 |
| 46 | Inlet protection type A (628.7005) | EACH | 19 | $125.00 | $51.00 | $100.00 | $125.00 | $125.00 |
| 47 | Inlet protection type C (628.7015) | EACH | 19 | $60.00 | $150.00 | $55.00 | $60.00 | $60.00 |
| 48 | Inlet protection type D (628.7020) | EACH | 8 | $125.00 | $150.00 | $90.00 | $125.00 | $125.00 |
| 49 | Tracking pads (628.7560) | EACH | 2 | $2,000.00 | $810.00 | $1,650.00 | $1,650.00 | $2,555.84 |
| 50 | Fertilizer type B (629.0210) | CWT | 5.60 | $75.00 | $310.00 | $80.00 | $75.00 | $75.00 |
| 51 | Seeding mixture no. 40 (630.0140) | LB | 150 | $8.50 | $31.00 | $12.00 | $8.00 | $8.50 |
| 52 | Seeding borrow pit (630.0300) | LB | 250 | $7.50 | $5.20 | $7.75 | $7.50 | $7.50 |
| 53 | Seed water (630.0500) | MGAL | 199.70 | $25.00 | $1.00 | $12.00 | $25.00 | $25.00 |
| 54 | Moving signs type II (638.2102) | EACH | 6 | $75.00 | $210.00 | $80.00 | $75.00 | $75.00 |
| 55 | Field office type B (642.5001) | EACH | 1 | $7,500.00 | $8,800.00 | $16,250 | $25,000 | $1,000.00 |
| 56 | Traffic control drums (643.0300) | DAY | 2,275 | $0.30 | $0.05 | $0.05 | $0.05 | $0.05 |
| 57 | Traffic control barricades type III (643.0420) | DAY | 4,860 | $0.40 | $1.00 | $1.00 | $1.00 | $1.01 |
| 58 | Traffic control warning lights type A (643.0705) | DAY | 9,720 | $0.07 | $0.05 | $0.05 | $0.05 | $0.05 |
| 59 | Traffic control signs (643.0900) | DAY | 14,670 | $0.30 | $0.25 | $0.25 | $0.25 | $0.25 |
| 60 | Traffic control signs PCMS (643.1050) | DAY | 14 | $35.00 | $31.00 | $30.00 | $30.00 | $30.30 |
| 61 | Temporary marking crosswalk paint 6-inch (643.3305) | LF | 90 | $3.50 | $2.60 | $2.50 | $2.50 | $2.53 |
| 62 | Traffic control (643.5000) | EACH | 1 | $9,070.29 | $2,100.00 | $2,000.00 | $2,000.00 | $2,020.20 |
| 63 | Temporary pedestrian surface matting (644.1440) | SF | 1,800 | $1.00 | $2.10 | $2.00 | $2.00 | $2.02 |
| 64 | Temporary pedestrian curb ramp (644.1601) | DAY | 120 | $3.13 | $10.25 | $10.00 | $10.00 | $10.10 |
| 65 | Temporary pedestrian detectable warning field (644.1605) | SF | 100 | $9.91 | $12.25 | $12.00 | $12.00 | $12.12 |
| 66 | Temporary pedestrian barricade (644.1810) | LF | 550 | $2.04 | $4.10 | $4.00 | $4.00 | $4.04 |
| 67 | Geotextile type HR (645.0120) | SY | 3 | $100.00 | $10.75 | $55.00 | $40.30 | $5.00 |
| 68 | Marking line paint 4-inch (646.1005) | LF | 90 | $5.00 | $5.20 | $3.95 | $3.95 | $3.95 |
| 69 | Marking stop line paint 18-inch (646.6105) | LF | 65 | $13.00 | $13.50 | $17.95 | $17.95 | $17.95 |
| 70 | Marking crosswalk paint block style 24-inch (646.7505) | LF | 240 | $14.00 | $14.50 | $23.95 | $23.95 | $23.95 |
| 71 | Marking curb paint (646.8105) | LF | 55 | $10.00 | $10.25 | $19.95 | $19.95 | $19.95 |
| 72 | Construction staking storm sewer (650.4000) | EACH | 27 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 |
| 73 | Construction staking subgrade (650.4500) | LF | 1,705 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 74 | Construction staking base (650.5000) | LF | 1,705 | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 |
| 75 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 3,320 | $1.20 | $1.20 | $1.20 | $1.20 | $1.20 |
| 76 | Construction staking curb ramps (650.9000) | EACH | 10 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 |
| 77 | Construction staking sidewalk (project) 001. 5998-00-01 (650.9500) | EACH | 1 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 78 | Construction staking supplemental control (project) 001. 5998-00-01 (650.9911) | EACH | 1 | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 |
| 79 | Construction staking slope stakes (650.9920) | LF | 1,705 | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 |
| 80 | Sawing asphalt (690.0150) | LF | 180 | $1.10 | $1.80 | $1.75 | $1.75 | $1.10 |
| 81 | Sawing concrete (690.0250) | LF | 125 | $2.10 | $2.80 | $2.75 | $2.75 | $2.10 |
| 82 | Incentive iri ride (740.0440) | DOL | 1,290 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 83 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,200 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 84 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 85 | Special 001. temporary mailbox station (SPV.0060) | EACH | 1 | $1,500.00 | $1,700.00 | $300.00 | $300.00 | $700.00 |
| 86 | Special 200. 4-foot dia. precast sanitary manhole (SPV.0060) | EACH | 4 | $6,176.62 | $6,300.00 | $6,045.00 | $6,000.00 | $6,600.00 |
| 87 | Special 201. connect to existing sanitary sewer (SPV.0060) | EACH | 2 | $2,716.86 | $2,400.00 | $2,964.00 | $2,150.00 | $1,800.00 |
| 88 | Special 202. connect to existing water main (SPV.0060) | EACH | 4 | $2,461.73 | $2,900.00 | $3,303.00 | $4,600.00 | $2,700.00 |
| 89 | Special 203. 8-inch water valve and valve box (SPV.0060) | EACH | 7 | $3,759.34 | $4,600.00 | $3,941.00 | $3,400.00 | $3,500.00 |
| 90 | Special 204. fire hydrant with auxiliary valve and 6-inch lead (SPV.0060) | EACH | 4 | $10,739 | $11,700 | $11,292 | $9,400.00 | $11,000 |
| 91 | Special 205. 1-inch brass corp stop, curb stop, and curb stop box (SPV.0060) | EACH | 19 | $894.97 | $3,300.00 | $2,395.00 | $1,100.00 | $1,800.00 |
| 92 | Special 206. abandon existing water main (SPV.0060) | EACH | 5 | $2,730.48 | $2,800.00 | $17,350 | $2,150.00 | $1,000.00 |
| 93 | Special 207. abandon existing sanitary sewer (SPV.0060) | EACH | 2 | $0.01 | $75.00 | $625.00 | $1,550.00 | $1,900.00 |
| 94 | Special 208. adjusting sanitary manhole covers (SPV.0060) | EACH | 1 | $1,092.00 | $1,000.00 | $710.00 | $1,100.00 | $1,400.00 |
| 95 | Special 209. adjusting water valve boxes (SPV.0060) | EACH | 3 | $350.00 | $400.00 | $470.00 | $900.00 | $300.00 |
| 96 | Special 200. 8-inch PVC sanitary sewer main (SPV.0090) | LF | 1,120 | $128.35 | $120.00 | $158.65 | $165.00 | $219.00 |
| 97 | Special 201. 4-inch ductile iron water main (SPV.0090) | LF | 20 | $199.96 | $170.00 | $145.75 | $155.00 | $189.00 |
| 98 | Special 202. 8-inch ductile iron water main (SPV.0090) | LF | 1,670 | $135.82 | $140.00 | $138.05 | $145.00 | $182.00 |
| 99 | Special 203. 6-inch PVC sanitary lateral (SPV.0090) | LF | 530 | $105.28 | $140.00 | $135.95 | $130.00 | $239.00 |
| 100 | Special 204. 1-inch copper water service (SPV.0090) | LF | 575 | $109.60 | $30.75 | $70.15 | $111.00 | $58.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.