WisDOT contract 20250311010 bid tabulation

5998-00-01. Let by Wisconsin DOT on March 11, 2025, Dane. 5 bids received; low bid $1,648,139 by James Peterson Sons, Inc..

Owner
Wisconsin DOT
Letting
11 MAR 2025
Pay items
100
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1James Peterson Sons, Inc.$1,648,139Low
2Parisi Construction, LLC$1,749,191+6.0%
3Speedway Sand & Gravel, Inc.$1,881,971+14%
4Fischer Excavating, Inc.$1,920,943+17%
5R.G. Huston Company, Inc.$1,965,600+19%
WisDOT contract 20250311010: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. James Peterson Sons, Inc.2. Parisi Construction, LLC3. Speedway Sand & Gravel, Inc.4. Fischer Excavating, Inc.5. R.G. Huston Company, Inc.
1Removing curb & gutter (204.0150)LF3,180$2.36$3.60$2.90$4.00$4.00
2Removing concrete sidewalk (204.0155)SY800$6.12$14.25$5.30$16.00$7.00
3Removing inlets (204.0220)EACH6$400.00$590.00$475.00$500.00$800.00
4Removing storm sewer (size) 001. 12-inch (204.0245)LF220$23.44$26.25$31.00$17.00$20.00
5Excavation common (205.0100)CY5,529$16.20$20.00$24.50$42.00$21.00
6Backfill granular grade 1 (209.1500)TON100$15.00$19.00$26.95$25.00$36.00
7Finishing roadway (project) 001. 5998-00-01 (213.0100)EACH1$1,000.00$790.00$1,000.00$12,000$4,000.00
8Base aggregate dense 1 1/4-inch (305.0120)TON3,107$20.10$17.25$22.95$19.00$23.00
9Base aggregate dense 3-inch (305.0130)TON1,339$18.75$20.25$19.70$19.00$20.00
10Tack coat (455.0605)GAL305$2.00$2.10$2.00$2.00$2.00
11Incentive density HMA pavement (460.2000)DOL1,100$1.00$1.00$1.00$1.00$1.00
12HMA pavement 3 LT 58-28 S (460.5223)TON1,030$76.00$78.00$76.00$76.00$76.00
13HMA pavement 4 LT 58-28 S (460.5224)TON685$77.00$79.00$77.00$77.00$77.00
14Asphaltic surface driveways and field entrances (465.0120)TON13$100.00$100.00$100.00$100.00$100.00
15Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH1$1,360.21$1,900.00$1,955.00$1,300.00$2,200.00
16Concrete curb & gutter 30-inch type D (601.0411)LF3,320$20.45$20.00$24.50$21.10$21.31
17Concrete curb pedestrian (601.0600)LF50$45.00$50.00$49.50$48.00$48.48
18Concrete sidewalk 5-inch (602.0410)SF800$7.25$8.20$6.85$10.00$7.37
19Concrete sidewalk 6-inch (602.0415)SF11,200$7.25$8.40$7.05$8.70$6.06
20Curb ramp detectable warning field yellow (602.0505)SF30$50.00$32.00$48.00$45.00$45.45
21Curb ramp detectable warning field radial yellow (602.0605)SF140$70.00$55.00$93.00$65.00$65.66
22Concrete driveway 6-inch (602.0810)SY169$70.00$65.00$66.60$90.00$66.36
23Riprap medium (606.0200)CY2.20$250.00$130.00$805.00$150.00$300.00
24Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF467$98.82$87.00$84.40$95.00$120.00
25Storm sewer pipe reinforced concrete class III 15-inch (608.0315)LF327$70.45$76.00$92.25$97.00$126.00
26Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF504$73.88$86.00$98.60$115.00$133.00
27Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF174$127.08$94.00$132.10$117.00$147.00
28Inlet covers type C (611.0612)EACH8$1,232.59$1,100.00$937.00$520.00$1,200.00
29Inlet covers type H (611.0624)EACH13$1,628.92$1,300.00$1,160.00$765.00$1,500.00
30Inlet covers type H-S (611.0639)EACH5$1,628.92$1,300.00$1,160.00$765.00$1,500.00
31Manholes 4-FT diameter (611.2004)EACH4$2,151.11$3,000.00$5,385.00$3,500.00$1,900.00
32Manholes 5-FT diameter (611.2005)EACH4$3,702.86$4,000.00$4,480.00$4,500.00$3,800.00
33Manholes 6-FT diameter (611.2006)EACH2$9,275.64$9,400.00$11,599$12,500$10,600
34Inlets 2X3-FT (611.3230)EACH16$1,357.50$2,200.00$2,982.00$3,100.00$1,600.00
35Pipe underdrain 6-inch (612.0106)LF200$17.00$16.50$11.55$19.00$21.00
36Insulation board polystyrene (inch) 001. 2-inch (612.0902.S)SY25$27.00$43.25$38.00$28.00$40.00
37Mobilization (619.1000)EACH1$148,400$160,000$103,572$95,000$124,245
38Water (624.0100)MGAL50$50.00$29.75$1.00$0.01$77.00
39Topsoil (625.0100)SY3,333$5.57$7.30$8.85$6.50$8.00
40Mulching (627.0200)SY8,889$0.25$1.00$0.40$0.25$0.25
41Silt fence (628.1504)LF980$2.50$3.10$2.05$2.50$2.50
42Silt fence maintenance (628.1520)LF980$0.10$0.01$0.01$0.10$0.10
43Mobilizations erosion control (628.1905)EACH3$250.00$260.00$200.00$250.00$250.00
44Mobilizations emergency erosion control (628.1910)EACH1$300.00$100.00$200.00$300.00$300.00
45Erosion mat urban class I type A (628.2006)SY2,280$1.80$3.61$1.70$1.80$1.80
46Inlet protection type A (628.7005)EACH19$125.00$51.00$100.00$125.00$125.00
47Inlet protection type C (628.7015)EACH19$60.00$150.00$55.00$60.00$60.00
48Inlet protection type D (628.7020)EACH8$125.00$150.00$90.00$125.00$125.00
49Tracking pads (628.7560)EACH2$2,000.00$810.00$1,650.00$1,650.00$2,555.84
50Fertilizer type B (629.0210)CWT5.60$75.00$310.00$80.00$75.00$75.00
51Seeding mixture no. 40 (630.0140)LB150$8.50$31.00$12.00$8.00$8.50
52Seeding borrow pit (630.0300)LB250$7.50$5.20$7.75$7.50$7.50
53Seed water (630.0500)MGAL199.70$25.00$1.00$12.00$25.00$25.00
54Moving signs type II (638.2102)EACH6$75.00$210.00$80.00$75.00$75.00
55Field office type B (642.5001)EACH1$7,500.00$8,800.00$16,250$25,000$1,000.00
56Traffic control drums (643.0300)DAY2,275$0.30$0.05$0.05$0.05$0.05
57Traffic control barricades type III (643.0420)DAY4,860$0.40$1.00$1.00$1.00$1.01
58Traffic control warning lights type A (643.0705)DAY9,720$0.07$0.05$0.05$0.05$0.05
59Traffic control signs (643.0900)DAY14,670$0.30$0.25$0.25$0.25$0.25
60Traffic control signs PCMS (643.1050)DAY14$35.00$31.00$30.00$30.00$30.30
61Temporary marking crosswalk paint 6-inch (643.3305)LF90$3.50$2.60$2.50$2.50$2.53
62Traffic control (643.5000)EACH1$9,070.29$2,100.00$2,000.00$2,000.00$2,020.20
63Temporary pedestrian surface matting (644.1440)SF1,800$1.00$2.10$2.00$2.00$2.02
64Temporary pedestrian curb ramp (644.1601)DAY120$3.13$10.25$10.00$10.00$10.10
65Temporary pedestrian detectable warning field (644.1605)SF100$9.91$12.25$12.00$12.00$12.12
66Temporary pedestrian barricade (644.1810)LF550$2.04$4.10$4.00$4.00$4.04
67Geotextile type HR (645.0120)SY3$100.00$10.75$55.00$40.30$5.00
68Marking line paint 4-inch (646.1005)LF90$5.00$5.20$3.95$3.95$3.95
69Marking stop line paint 18-inch (646.6105)LF65$13.00$13.50$17.95$17.95$17.95
70Marking crosswalk paint block style 24-inch (646.7505)LF240$14.00$14.50$23.95$23.95$23.95
71Marking curb paint (646.8105)LF55$10.00$10.25$19.95$19.95$19.95
72Construction staking storm sewer (650.4000)EACH27$150.00$150.00$150.00$150.00$150.00
73Construction staking subgrade (650.4500)LF1,705$0.01$0.01$0.01$0.01$0.01
74Construction staking base (650.5000)LF1,705$1.50$1.50$1.50$1.50$1.50
75Construction staking curb gutter and curb & gutter (650.5500)LF3,320$1.20$1.20$1.20$1.20$1.20
76Construction staking curb ramps (650.9000)EACH10$150.00$150.00$150.00$150.00$150.00
77Construction staking sidewalk (project) 001. 5998-00-01 (650.9500)EACH1$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00
78Construction staking supplemental control (project) 001. 5998-00-01 (650.9911)EACH1$1,200.00$1,200.00$1,200.00$1,200.00$1,200.00
79Construction staking slope stakes (650.9920)LF1,705$1.50$1.50$1.50$1.50$1.50
80Sawing asphalt (690.0150)LF180$1.10$1.80$1.75$1.75$1.10
81Sawing concrete (690.0250)LF125$2.10$2.80$2.75$2.75$2.10
82Incentive iri ride (740.0440)DOL1,290$1.00$1.00$1.00$1.00$1.00
83On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,200$5.00$5.00$5.00$5.00$5.00
84On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00$5.00$5.00
85Special 001. temporary mailbox station (SPV.0060)EACH1$1,500.00$1,700.00$300.00$300.00$700.00
86Special 200. 4-foot dia. precast sanitary manhole (SPV.0060)EACH4$6,176.62$6,300.00$6,045.00$6,000.00$6,600.00
87Special 201. connect to existing sanitary sewer (SPV.0060)EACH2$2,716.86$2,400.00$2,964.00$2,150.00$1,800.00
88Special 202. connect to existing water main (SPV.0060)EACH4$2,461.73$2,900.00$3,303.00$4,600.00$2,700.00
89Special 203. 8-inch water valve and valve box (SPV.0060)EACH7$3,759.34$4,600.00$3,941.00$3,400.00$3,500.00
90Special 204. fire hydrant with auxiliary valve and 6-inch lead (SPV.0060)EACH4$10,739$11,700$11,292$9,400.00$11,000
91Special 205. 1-inch brass corp stop, curb stop, and curb stop box (SPV.0060)EACH19$894.97$3,300.00$2,395.00$1,100.00$1,800.00
92Special 206. abandon existing water main (SPV.0060)EACH5$2,730.48$2,800.00$17,350$2,150.00$1,000.00
93Special 207. abandon existing sanitary sewer (SPV.0060)EACH2$0.01$75.00$625.00$1,550.00$1,900.00
94Special 208. adjusting sanitary manhole covers (SPV.0060)EACH1$1,092.00$1,000.00$710.00$1,100.00$1,400.00
95Special 209. adjusting water valve boxes (SPV.0060)EACH3$350.00$400.00$470.00$900.00$300.00
96Special 200. 8-inch PVC sanitary sewer main (SPV.0090)LF1,120$128.35$120.00$158.65$165.00$219.00
97Special 201. 4-inch ductile iron water main (SPV.0090)LF20$199.96$170.00$145.75$155.00$189.00
98Special 202. 8-inch ductile iron water main (SPV.0090)LF1,670$135.82$140.00$138.05$145.00$182.00
99Special 203. 6-inch PVC sanitary lateral (SPV.0090)LF530$105.28$140.00$135.95$130.00$239.00
100Special 204. 1-inch copper water service (SPV.0090)LF575$109.60$30.75$70.15$111.00$58.00
WisDOT contract 20250311010: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy