WisDOT contract 20250311045 bid tabulation

V Frederic, Third Avenue; Ash Street to Oak Street (LOC STR, Polk County V Frederic, Third Avenue). Let by Wisconsin DOT on March 11, 2025, Polk. 3 bids received; low bid $584,100 by McCabe Construction, Inc..

Owner
Wisconsin DOT
Letting
11 MAR 2025
Pay items
85
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1McCabe Construction, Inc.$584,100Low
2A-1 Excavating LLC$597,739+2.0%
3Pember Companies, Inc.$642,295+10%
WisDOT contract 20250311045: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. McCabe Construction, Inc.2. A-1 Excavating LLC3. Pember Companies, Inc.
1Removing concrete pavement (204.0100)SY10$50.00$50.00$15.20
2Removing asphaltic surface (204.0110)SY6$50.00$50.00$11.50
3Removing curb & gutter (204.0150)LF1,234$4.00$4.00$6.20
4Removing concrete sidewalk (204.0155)SY16$32.00$50.00$15.20
5Removing manholes (204.0210)EACH3$725.00$600.00$625.00
6Removing catch basins (204.0215)EACH6$475.00$600.00$570.00
7Removing inlets (204.0220)EACH1$475.00$600.00$445.00
8Removing storm sewer (size) 01. 8- inch (204.0245)LF3$15.00$12.00$18.50
9Removing storm sewer (size) 02. 12-inch (204.0245)LF34$15.50$13.00$12.50
10Removing storm sewer (size) 03. 15-inch (204.0245)LF227$17.00$14.00$12.70
11Removing storm sewer (size) 04. 18-inch (204.0245)LF2$18.75$15.00$18.75
12Removing storm sewer (size) 05. 27-inch (204.0245)LF161$24.00$16.00$25.30
13Removing storm sewer (size) 06. 30-inch (204.0245)LF125$27.00$17.00$30.40
14Removing (item description) 01. apron endwalls (204.9060.S)EACH1$145.00$200.00$205.00
15Excavation common (205.0100)CY2,003$19.50$17.00$26.30
16Finishing roadway (project) 01. 8420-02-72 (213.0100)EACH1$1,525.00$500.00$500.00
17Base aggregate dense 1 1/4-inch (305.0120)TON2,788$19.40$18.00$27.25
18Tack coat (455.0605)GAL244$5.00$6.00$5.00
19Incentive density HMA pavement (460.2000)DOL590$1.00$1.00$1.00
20HMA pavement 4 LT 58-34 S (460.5244)TON918$108.00$106.00$108.10
21Asphaltic surface driveways and field entrances (465.0120)TON23$188.40$200.00$188.40
22Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015)EACH1$1,010.00$1,365.00$1,270.00
23Concrete curb & gutter 30-inch type D (601.0411)LF2,698$19.70$19.30$17.30
24Concrete curb pedestrian (601.0600)LF27$68.25$66.00$35.35
25Concrete sidewalk 4-inch (602.0405)SF1,394$8.65$9.25$6.35
26Curb ramp detectable warning field yellow (602.0505)SF40$63.00$61.00$47.70
27Concrete driveway 6-inch (602.0810)SY11$103.00$108.00$77.70
28Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF324$65.00$68.00$67.65
29Storm sewer pipe reinforced concrete class III 15-inch (608.0315)LF126$75.00$74.00$75.60
30Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF367$76.00$78.00$73.40
31Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF160$90.00$98.00$92.15
32Storm sewer pipe reinforced concrete class III 30-inch (608.0330)LF152$130.00$138.00$131.00
33Manhole covers type J (611.0530)EACH1$775.00$990.00$1,025.00
34Inlet covers type C (611.0612)EACH1$810.00$1,010.00$950.00
35Inlet covers type H (611.0624)EACH16$890.00$1,230.00$1,000.00
36Inlet covers type H-S (611.0639)EACH2$890.00$1,280.00$1,000.00
37Catch basins 4-FT diameter (611.1004)EACH1$3,560.00$3,625.00$3,565.00
38Catch basins 5-FT diameter (611.1005)EACH5$6,160.00$5,595.00$5,515.00
39Catch basins 2X3-FT (611.1230)EACH4$2,375.00$2,550.00$2,270.00
40Manholes 4-FT diameter (611.2004)EACH1$3,100.00$3,625.00$3,225.00
41Inlets 3-FT diameter (611.3003)EACH1$1,390.00$2,060.00$1,705.00
42Inlets 2X3-FT (611.3230)EACH9$1,965.00$2,550.00$2,270.00
43Adjusting inlet covers (611.8115)EACH1$515.00$550.00$590.00
44Maintenance and repair of haul roads (project) 01. 8420-02-72 (618.0100)EACH1$1.00$500.00$500.00
45Mobilization (619.1000)EACH1$27,497$44,800$47,625
46Water (624.0100)MGAL55.80$35.00$30.00$65.80
47Topsoil (625.0100)SY1,710$10.40$6.00$10.80
48Silt fence (628.1504)LF2,030$2.60$2.00$2.65
49Silt fence maintenance (628.1520)LF2,030$0.02$0.10$0.02
50Mobilizations erosion control (628.1905)EACH4$420.00$300.00$420.00
51Mobilizations emergency erosion control (628.1910)EACH2$262.50$100.00$265.00
52Erosion mat urban class I type B (628.2008)SY1,710$2.55$2.30$2.60
53Inlet protection type A (628.7005)EACH23$147.00$100.00$150.00
54Inlet protection type C (628.7015)EACH23$77.70$50.00$80.00
55Culvert pipe checks (628.7555)EACH9$15.75$20.00$15.90
56Fertilizer type B (629.0210)CWT1$84.00$200.00$84.85
57Seeding mixture no. 40 (630.0140)LB77$10.40$10.00$10.50
58Seeding temporary (630.0200)LB47$6.10$8.00$6.00
59Seed water (630.0500)MGAL29.70$47.70$30.00$49.30
60Moving signs type II (638.2102)EACH12$105.00$100.00$105.00
61Moving small sign supports (638.4000)EACH8$142.00$200.00$145.00
62Field office type B (642.5001)EACH1$6,500.00$7,000.00$8,300.00
63Traffic control barricades type III (643.0420)DAY1,120$0.58$0.75$0.60
64Traffic control warning lights type A (643.0705)DAY1,820$0.26$0.45$0.25
65Traffic control signs (643.0900)DAY1,470$0.58$0.70$0.60
66Traffic control signs fixed message (643.1000)SF36$12.40$13.80$12.50
67Traffic control (643.5000)EACH1$2,384.00$4,770.00$3,800.00
68Marking crosswalk epoxy transverse line 6-inch (646.7420)LF124$47.70$47.00$47.75
69Construction staking storm sewer (650.4000)EACH22$126.00$210.00$210.00
70Construction staking subgrade (650.4500)LF1,288$0.01$0.01$1.00
71Construction staking base (650.5000)LF1,288$0.32$0.50$0.30
72Construction staking curb gutter and curb & gutter (650.5500)LF2,753$1.05$1.60$1.60
73Construction staking curb ramps (650.9000)EACH4$181.00$60.00$10.60
74Construction staking sidewalk (project) 01. 8420-02-72 (650.9500)EACH1$157.50$350.00$105.00
75Construction staking supplemental control (project) 01. 8420-02-72 (650.9911)EACH1$1,435.00$2,000.00$1,855.00
76Construction staking slope stakes (650.9920)LF1,288$0.72$0.50$0.30
77Sawing asphalt (690.0150)LF335$2.05$3.00$2.50
78Sawing concrete (690.0250)LF51$3.10$5.00$3.65
79On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS300$5.00$5.00$5.00
80On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS300$5.00$5.00$5.00
81Special 01. connect to existing storm sewer (SPV.0060)EACH4$1,065.00$1,000.00$1,325.00
82Special 02. inlet cover type driveway special (SPV.0060)EACH1$825.00$1,295.00$930.00
83Special 03. adjusting water valve boxes (SPV.0060)EACH3$250.00$200.00$235.00
84Special 04. adjusting sanitary sewer manhole covers (SPV.0060)EACH3$1,000.00$500.00$1,105.00
85Special 01. concrete curb & gutter 24-inch type D (SPV.0090)LF55$63.00$63.00$37.40
WisDOT contract 20250311045: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy