Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Zenith Tech., Inc. - Waukesha | $10,596,532 | Low |
| 2 | Kraemer North America, LLC | $10,797,627 | +2.0% |
| 3 | Lunda Construction Company | $11,019,703 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Zenith Tech., Inc. - Waukesha | 2. Kraemer North America, LLC | 3. Lunda Construction Company |
|---|---|---|---|---|---|---|
| 1 | CPM progress schedule (108.4400) | EACH | 1 | $2,500.00 | $2,000.00 | $1.00 |
| 2 | Clearing (201.0105) | STA | 74 | $211.80 | $211.80 | $211.80 |
| 3 | Grubbing (201.0205) | STA | 74 | $211.80 | $211.80 | $211.80 |
| 4 | Removing curb & gutter (204.0150) | LF | 300 | $10.00 | $10.00 | $10.00 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 64 | $15.00 | $14.00 | $14.00 |
| 6 | Removing fence (204.0170) | LF | 7,414 | $4.50 | $1.98 | $1.98 |
| 7 | Finishing roadway (project) 01. 1090-03-78 (213.0100) | EACH | 1 | $8,800.00 | $2,500.00 | $1,500.00 |
| 8 | Drilled tie bars (416.0610) | EACH | 36 | $8.72 | $13.00 | $15.00 |
| 9 | Culvert pipe reinforced concrete class III 12-inch (522.0112) | LF | 8 | $240.00 | $242.00 | $242.00 |
| 10 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 5 | $1,550.00 | $1,535.00 | $1,535.00 |
| 11 | Concrete masonry ancillary structures type NS (531.1100) | CY | 4.40 | $1,200.00 | $1,200.00 | $2,000.00 |
| 12 | Steel reinforcement HS ancillary structures type NS (531.1140) | LB | 580 | $5.00 | $5.00 | $5.00 |
| 13 | Drilling shaft 24-inch (531.2024) | LF | 36 | $50.00 | $150.00 | $75.00 |
| 14 | Noise barriers double-sided sound absorptive (structure) 01. N-40-107 (541.0300.S) | SF | 31,100 | $76.05 | $73.00 | $75.00 |
| 15 | Noise barriers double-sided sound absorptive (structure) 02. N-40-108 (541.0300.S) | SF | 45,660 | $75.85 | $73.00 | $75.00 |
| 16 | Noise barriers double-sided sound absorptive (structure) 03. N-40-109 (541.0300.S) | SF | 42,070 | $75.25 | $73.00 | $75.00 |
| 17 | Concrete curb & gutter 31-inch (601.0331) | LF | 150 | $71.32 | $35.00 | $35.00 |
| 18 | Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553) | LF | 150 | $71.32 | $30.00 | $35.00 |
| 19 | Concrete sidewalk 5-inch (602.0410) | SF | 300 | $8.57 | $7.00 | $10.00 |
| 20 | Concrete barrier temporary precast delivered (603.8000) | LF | 1,775 | $25.00 | $20.00 | $10.00 |
| 21 | Concrete barrier temporary precast installed (603.8125) | LF | 1,775 | $4.75 | $3.00 | $6.00 |
| 22 | Riprap medium (606.0200) | CY | 11 | $170.00 | $162.00 | $162.00 |
| 23 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 58 | $175.00 | $208.00 | $208.00 |
| 24 | Manhole covers type J-special (611.0535) | EACH | 1 | $900.00 | $891.00 | $891.00 |
| 25 | Inlet covers type MS (611.0642) | EACH | 3 | $800.00 | $593.00 | $593.00 |
| 26 | Inlets median 1 grate (611.3901) | EACH | 3 | $3,650.00 | $3,633.00 | $3,633.00 |
| 27 | Adjusting manhole covers (611.8110) | EACH | 1 | $1,200.00 | $524.00 | $524.00 |
| 28 | Fence chain link 6-FT (616.0206) | LF | 653 | $39.15 | $39.15 | $39.15 |
| 29 | Gates chain link (width) 01. 8-FT (616.0329) | EACH | 3 | $2,182.00 | $2,182.00 | $2,182.00 |
| 30 | Gates chain link (width) 02. 10-FT (616.0329) | EACH | 1 | $2,388.00 | $2,388.00 | $2,388.00 |
| 31 | Gates chain link (width) 03. 12-FT (616.0329) | EACH | 3 | $2,362.00 | $2,362.00 | $2,362.00 |
| 32 | Fence safety (616.0700.S) | LF | 953 | $3.50 | $3.99 | $3.99 |
| 33 | Maintenance and repair of haul roads (project) 01. 1090-03-78 (618.0100) | EACH | 1 | $15,000 | $500.00 | $1,500.00 |
| 34 | Mobilization (619.1000) | EACH | 1 | $646,215 | $1,291,355 | $1,306,166 |
| 35 | Dust control surface treatment (623.0200) | SY | 2,578 | $3.00 | $1.25 | $0.01 |
| 36 | Topsoil (625.0100) | SY | 50,334 | $4.00 | $3.50 | $3.50 |
| 37 | Mulching (627.0200) | SY | 14,080 | $0.25 | $0.30 | $0.30 |
| 38 | Silt fence (628.1504) | LF | 7,873 | $2.25 | $1.55 | $1.55 |
| 39 | Silt fence maintenance (628.1520) | LF | 395 | $0.50 | $0.05 | $0.05 |
| 40 | Mobilizations erosion control (628.1905) | EACH | 9 | $250.00 | $150.00 | $150.00 |
| 41 | Mobilizations emergency erosion control (628.1910) | EACH | 6 | $300.00 | $50.00 | $50.00 |
| 42 | Erosion mat class I type B (628.2004) | SY | 35,627 | $0.93 | $1.15 | $1.15 |
| 43 | Erosion mat urban class I type B (628.2008) | SY | 628 | $2.00 | $1.89 | $1.89 |
| 44 | Soil stabilizer type A (628.6505) | ACRE | 17 | $3,500.00 | $2,580.00 | $2,580.00 |
| 45 | Inlet protection type A (628.7005) | EACH | 35 | $150.00 | $88.10 | $88.10 |
| 46 | Inlet protection type C (628.7015) | EACH | 10 | $60.00 | $38.10 | $38.10 |
| 47 | Inlet protection type D (628.7020) | EACH | 43 | $125.00 | $75.00 | $75.00 |
| 48 | Culvert pipe checks (628.7555) | EACH | 2 | $25.00 | $50.00 | $50.00 |
| 49 | Tracking pads (628.7560) | EACH | 7 | $2,500.00 | $1,746.00 | $1,746.00 |
| 50 | Rock bags (628.7570) | EACH | 100 | $17.50 | $9.00 | $9.00 |
| 51 | Fertilizer type B (629.0210) | CWT | 24 | $65.00 | $78.50 | $78.50 |
| 52 | Seeding mixture no. 20 (630.0120) | LB | 965 | $7.65 | $8.10 | $8.10 |
| 53 | Seeding mixture no. 40 (630.0140) | LB | 256 | $8.95 | $9.00 | $9.00 |
| 54 | Seeding mixture no. 60 (630.0160) | LB | 9 | $45.00 | $15.00 | $15.00 |
| 55 | Seeding temporary (630.0200) | LB | 1,361 | $4.00 | $3.05 | $3.05 |
| 56 | Seed water (630.0500) | MGAL | 1,134 | $20.00 | $5.00 | $5.00 |
| 57 | Markers culvert end (633.5200) | EACH | 5 | $55.00 | $60.00 | $60.00 |
| 58 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 14 | $125.00 | $87.10 | $87.10 |
| 59 | Sign supports structural steel HS (635.0200) | LB | 2,700 | $4.75 | $12.90 | $12.90 |
| 60 | Signs type II reflective H (637.2210) | SF | 189 | $65.00 | $21.90 | $21.90 |
| 61 | Moving signs type I (638.2101) | EACH | 3 | $700.00 | $2,200.00 | $2,200.00 |
| 62 | Moving signs type II (638.2102) | EACH | 5 | $75.00 | $100.00 | $100.00 |
| 63 | Removing small sign supports (638.3000) | EACH | 14 | $35.00 | $21.00 | $21.00 |
| 64 | Removing structural steel sign supports (638.3100) | EACH | 4 | $400.00 | $650.00 | $650.00 |
| 65 | Field office type D (642.5401) | EACH | 1 | $21,000 | $12,000 | $10,000 |
| 66 | Traffic control drums (643.0300) | DAY | 12,477 | $0.15 | $0.15 | $0.15 |
| 67 | Traffic control barricades type III (643.0420) | DAY | 1,213 | $0.55 | $0.55 | $0.55 |
| 68 | Traffic control warning lights type A (643.0705) | DAY | 2,426 | $0.25 | $0.25 | $0.25 |
| 69 | Traffic control warning lights type C (643.0715) | DAY | 405 | $0.50 | $0.50 | $0.50 |
| 70 | Traffic control arrow boards (643.0800) | DAY | 181 | $10.25 | $10.25 | $10.25 |
| 71 | Traffic control signs (643.0900) | DAY | 29,475 | $0.16 | $0.16 | $0.16 |
| 72 | Traffic control covering signs type I (643.0910) | EACH | 4 | $240.00 | $240.00 | $240.00 |
| 73 | Traffic control covering signs type II (643.0920) | EACH | 242 | $40.00 | $40.00 | $40.00 |
| 74 | Traffic control signs PCMS (643.1050) | DAY | 373 | $14.50 | $14.50 | $14.50 |
| 75 | Temporary marking line removable tape 6-inch (643.3180) | LF | 871 | $2.15 | $2.15 | $2.15 |
| 76 | Traffic control interim lane closure (643.4100) | EACH | 20 | $550.00 | $550.00 | $550.00 |
| 77 | Traffic control (643.5000) | EACH | 1 | $15,250 | $30,000 | $15,250 |
| 78 | Geotextile type HR (645.0120) | SY | 22 | $20.00 | $18.00 | $18.00 |
| 79 | Marking line epoxy 6-inch (646.2020) | LF | 600 | $4.00 | $4.00 | $5.25 |
| 80 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 50 | $5.00 | $5.00 | $6.50 |
| 81 | Marking line epoxy 10-inch (646.4020) | LF | 15 | $7.00 | $7.00 | $8.75 |
| 82 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 900 | $8.00 | $8.00 | $10.35 |
| 83 | Marking line grooved permanent tape 10-inch (646.4050) | LF | 2,225 | $20.00 | $20.00 | $12.75 |
| 84 | Marking arrow epoxy (646.5020) | EACH | 5 | $500.00 | $500.00 | $250.00 |
| 85 | Marking symbol epoxy (646.5220) | EACH | 3 | $400.00 | $400.00 | $435.00 |
| 86 | Marking stop line epoxy 18-inch (646.6120) | LF | 35 | $25.00 | $25.00 | $15.75 |
| 87 | Marking diagonal epoxy 12-inch (646.7120) | LF | 35 | $20.00 | $20.00 | $10.50 |
| 88 | Marking chevron epoxy 24-inch (646.7220) | LF | 100 | $30.00 | $30.00 | $21.00 |
| 89 | Sawing concrete (690.0250) | LF | 54 | $2.75 | $2.75 | $2.75 |
| 90 | Special 01, survey project 1090-03- 78 (SPV.0060) | EACH | 1 | $73,000 | $70,100 | $70,100 |
| 91 | Special 02. traffic control close- open freeway entrance ramp (SPV.0060) | EACH | 10 | $225.00 | $225.00 | $225.00 |
| 92 | Special 03. utility line opening (SPV.0060) | EACH | 11 | $2,000.00 | $1,200.00 | $2,500.00 |
| 93 | Special 04. adjusting water valve boxes (SPV.0060) | EACH | 1 | $700.00 | $574.00 | $574.00 |
| 94 | Special 01. pavement cleanup project 1090-03-78 (SPV.0075) | HRS | 120 | $210.00 | $175.00 | $200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.