WisDOT contract 20250408014 bid tabulation

Kewaunee Co, CTH C; CTH L to Clyde Hill Road (CTH C, Kewaunee County Kewaunee Co, CTH C). Let by Wisconsin DOT on April 8, 2025, Kewaunee. 2 bids received; low bid $1,630,919 by Relyco Plus, LLC.

Owner
Wisconsin DOT
Letting
08 APR 2025
Pay items
66
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Relyco Plus, LLC$1,630,919Low
2Northeast Asphalt, Inc$1,646,226+1.0%
WisDOT contract 20250408014: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Relyco Plus, LLC2. Northeast Asphalt, Inc
1Removing small pipe culverts (203.0100)EACH2$825.00$825.00
2Removing asphaltic surface (204.0110)SY510$4.50$4.50
3Removing curb & gutter (204.0150)LF135$5.13$5.13
4Excavation common (205.0100)CY7,800$11.39$11.39
5Finishing roadway (project) 01. 4390-01-74 (213.0100)EACH1$2,000.00$1,450.00
6Base aggregate dense 3/4-inch (305.0110)TON1,700$26.17$26.17
7Base aggregate dense 1 1/4-inch (305.0120)TON6,950$16.85$16.85
8Pulverize and relay (325.0100)SY36,320$0.75$0.75
9Tack coat (455.0605)GAL2,705$4.20$4.20
10Incentive density HMA pavement (460.2000)DOL6,540$1.00$1.00
11HMA pavement 3 LT 58-28 S (460.5223)TON5,760$86.40$86.40
12HMA pavement 4 LT 58-28 S (460.5224)TON4,490$79.80$79.80
13Asphaltic surface driveways and field entrances (465.0120)TON95$255.00$255.00
14Asphaltic flumes (465.0315)SY10$75.80$75.80
15Culvert pipe reinforced concrete class III 36-inch (522.0136)LF88$288.00$288.00
16Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036)EACH2$3,313.00$3,313.00
17Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 38X60-inch (522.2638)EACH2$5,068.00$5,068.00
18Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF270$38.90$82.90
19Riprap medium (606.0200)CY18$120.00$120.00
20Pipe grates (size) 01. 38X60-inch (611.9850.S)EACH2$3,804.00$3,804.00
21Salvaged rail (614.0920)LF650$3.50$3.50
22MGS guardrail 3 (614.2300)LF225$26.03$26.03
23MGS guardrail 3 K (614.2330)LF600$38.13$38.13
24MGS guardrail terminal eat (614.2610)EACH4$3,433.00$3,433.00
25Mobilization (619.1000)EACH1$202,000$202,740
26Water (624.0100)MGAL390$0.01$10.00
27Topsoil (625.0100)SY5,100$2.18$2.18
28Silt fence (628.1504)LF2,600$1.75$1.75
29Silt fence maintenance (628.1520)LF5,200$0.03$0.03
30Mobilizations erosion control (628.1905)EACH4$293.00$293.00
31Mobilizations emergency erosion control (628.1910)EACH3$393.00$393.00
32Erosion mat class I type B (628.2004)SY1,070$1.25$1.25
33Erosion mat urban class I type B (628.2008)SY4,030$1.87$1.87
34Temporary ditch checks (628.7504)LF70$8.00$8.00
35Culvert pipe checks (628.7555)EACH27$30.00$30.00
36Rock bags (628.7570)EACH45$9.00$9.00
37Fertilizer type B (629.0210)CWT4$100.00$100.00
38Seeding mixture no. 20 (630.0120)LB155$9.00$9.00
39Seeding mixture no. 40 (630.0140)LB70$12.00$12.00
40Seed water (630.0500)MGAL120$5.00$5.00
41Markers culvert end (633.5200)EACH14$80.00$80.00
42Field office type B (642.5001)EACH1$8,500.00$8,600.00
43Traffic control drums (643.0300)DAY200$1.00$1.00
44Traffic control barricades type III (643.0420)DAY2,800$0.45$0.45
45Traffic control warning lights type A (643.0705)DAY5,600$0.15$0.15
46Traffic control signs (643.0900)DAY8,000$0.19$0.19
47Traffic control covering signs type II (643.0920)EACH10$110.00$110.00
48Traffic control signs PCMS (643.1050)DAY14$40.00$40.00
49Traffic control (643.5000)EACH1$7,950.00$7,950.00
50Geotextile type HR (645.0120)SY50$5.00$5.00
51Marking line epoxy 4-inch (646.1020)LF42,670$0.39$0.39
52Marking line epoxy 8-inch (646.3020)LF400$1.50$1.50
53Locating no-passing zones (648.0100)MI2.50$416.00$416.00
54Construction staking subgrade (650.4500)LF1,725$0.01$0.01
55Construction staking base (650.5000)LF1,725$0.75$0.75
56Construction staking pipe culverts (650.6000)EACH2$150.00$150.00
57Construction staking resurfacing reference (650.8000)LF13,288$0.12$0.12
58Construction staking supplemental control (project) 01. 4390-01-74 (650.9911)EACH1$10.00$10.00
59Construction staking slope stakes (650.9920)LF2,400$0.95$0.95
60Sawing asphalt (690.0150)LF490$3.50$1.95
61Incentive iri ride (740.0440)DOL10,068$1.00$1.00
62On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,200$5.00$5.00
63On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00
64Special 01. foundation backfill (SPV.0035)CY400$32.42$32.42
65Special 01. culvert pipe reinforced concrete horizontal elliptical class HE-IV 38X60 (SPV.0090)LF48$518.00$518.00
66Special 01. remove excess pulverized material (SPV.0180)SY4,400$0.20$0.20
WisDOT contract 20250408014: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way