WisDOT contract 20250408028 bid tabulation

STH 107 - CTH O; Little Rib River Bridge, B-37-0473 (CTH L, Marathon County STH 107 - CTH O). Let by Wisconsin DOT on April 8, 2025, Marathon. 6 bids received; low bid $639,962 by Janke General Contractors, Inc..

Owner
Wisconsin DOT
Letting
08 APR 2025
Pay items
69
Data through
10 NOV 2026

5 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Janke General Contractors, Inc.$639,962Low
3Radtke Contractors Inc.$667,554+4.0%
4Lunda Construction Company$676,475+6.0%
5Larson Construction Co., Inc.$769,403+20%
6Zenith Tech., Inc. - Waukesha$822,693+29%
WisDOT contract 20250408028: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Janke General Contractors, Inc.2. Radtke Contractors Inc.3. Lunda Construction Company4. Larson Construction Co., Inc.5. Zenith Tech., Inc. - Waukesha
1Clearing (201.0105)STA3$200.00$50.00$50.00$50.00$50.00
2Grubbing (201.0205)STA3$215.00$150.00$150.00$150.00$150.00
3Removing structure over waterway minimal debris (structure) 01. B-37- 0038 (203.0260)EACH1$17,500$45,226$125,000$45,940$45,000
4Excavation common (205.0100)CY382$15.50$9.19$9.19$9.19$9.19
5Excavation, hauling, and disposal of creosote contaminated soil (205.0506.S)TON150$121.00$88.64$97.00$97.00$97.00
6Excavation for structures bridges (structure) 01. B-37-0473 (206.1001)EACH1$38,350$59,642$10,000$37,600$40,000
7Borrow (208.0100)CY437$20.50$29.89$29.89$29.89$29.89
8Backfill structure type A (210.1500)TON615$22.00$28.50$19.78$29.78$19.78
9Finishing roadway (project) 01. 9478-03-71 (213.0100)EACH1$350.00$1,000.00$1,000.00$1,000.00$1,000.00
10Base aggregate dense 3/4-inch (305.0110)TON155$31.00$23.45$23.45$23.45$23.45
11Base aggregate dense 1 1/4-inch (305.0120)TON860$24.75$20.31$20.31$20.31$27.40
12Tack coat (455.0605)GAL105$7.20$7.20$7.20$7.20$7.20
13Asphaltic surface (465.0105)TON340$132.50$132.50$132.50$132.50$132.50
14Concrete masonry bridges (502.0100)CY243$575.00$549.52$650.00$712.00$821.01
15Protective surface treatment (502.3200)SY288$4.00$3.60$5.00$3.50$4.00
16Bar steel reinforcement HS structures (505.0400)LB5,550$1.70$1.23$0.95$1.55$1.20
17Bar steel reinforcement HS coated structures (505.0600)LB30,740$1.70$1.32$1.12$1.50$1.30
18Railing tubular type M (513.4061)LF110$360.00$295.18$275.00$265.00$280.00
19Rubberized membrane waterproofing (516.0500)SY17$32.00$74.42$25.00$62.50$60.00
20Pre-boring unconsolidated materials (550.0010)LF304$232.00$152.84$100.00$371.00$300.00
21Pile points (550.0500)EACH16$158.00$110.78$105.00$125.00$111.00
22Piling steel HP 10-inch X 42 LB (550.1100)LF480$67.00$32.81$33.75$50.00$66.00
23Riprap heavy (606.0300)CY125$91.00$129.99$78.68$83.68$78.68
24Pipe underdrain wrapped 6-inch (612.0406)LF195$11.00$4.20$6.10$6.10$6.10
25MGS guardrail 3 (614.2300)LF137.50$27.00$25.80$25.80$25.80$25.80
26MGS thrie beam transition (614.2500)LF120$96.00$88.75$88.75$88.75$88.75
27MGS guardrail terminal eat (614.2610)EACH3$4,000.00$3,500.00$3,500.00$3,500.00$3,500.00
28Maintenance and repair of haul roads (project) 01. 9478-03-71 (618.0100)EACH1$349.18$250.00$0.01$2,500.00$1,800.00
29Mobilization (619.1000)EACH1$26,000$75,257$59,987$73,450$121,150
30Water (624.0100)MGAL37$14.00$25.00$25.00$25.00$25.00
31Topsoil (625.0100)SY1,045$5.00$5.89$5.89$5.89$5.89
32Mulching (627.0200)SY1,230$0.50$0.75$0.75$0.75$0.75
33Silt fence (628.1504)LF1,575$2.20$2.80$2.80$2.80$2.80
34Silt fence maintenance (628.1520)LF3,150$0.01$0.10$0.10$0.10$0.10
35Mobilizations erosion control (628.1905)EACH4$320.00$100.00$100.00$100.00$100.00
36Mobilizations emergency erosion control (628.1910)EACH4$200.00$100.00$100.00$100.00$100.00
37Erosion mat class II type C (628.2027)SY395$4.00$3.28$3.28$3.28$3.28
38Turbidity barriers (628.6005)SY55$45.00$47.90$47.90$47.90$47.90
39Temporary ditch checks (628.7504)LF50$11.00$12.50$12.50$12.50$12.50
40Fertilizer type B (629.0210)CWT1$80.00$100.00$100.00$100.00$100.00
41Seeding mixture no. 20 (630.0120)LB74$7.00$8.10$8.10$8.10$8.10
42Seeding temporary (630.0200)LB45$4.00$3.00$3.00$3.00$3.00
43Seed water (630.0500)MGAL36$1.00$25.00$25.00$25.00$25.00
44Posts wood 4X6-inch X 14-FT (634.0614)EACH5$77.00$125.00$125.00$125.00$125.00
45Signs type II reflective H (637.2210)SF5.18$22.90$28.15$28.15$28.15$28.15
46Signs type II reflective F (637.2230)SF12$24.80$28.10$28.10$28.10$28.10
47Moving signs type II (638.2102)EACH2$100.00$25.00$25.00$25.00$25.00
48Removing signs type II (638.2602)EACH5$25.00$10.00$10.00$10.00$10.00
49Removing small sign supports (638.3000)EACH5$25.00$10.00$10.00$10.00$10.00
50Moving small sign supports (638.4000)EACH1$100.00$65.00$65.00$65.00$65.00
51Field office type B (642.5001)EACH1$4,960.00$2,489.56$3,500.00$3,200.00$4,700.00
52Traffic control barricades type III (643.0420)DAY2,860$0.35$0.35$0.40$0.35$0.40
53Traffic control warning lights type A (643.0705)DAY4,030$0.05$0.05$0.10$0.05$0.10
54Traffic control signs (643.0900)DAY2,120$0.35$0.35$0.25$0.35$0.25
55Traffic control (643.5000)EACH1$900.00$900.00$5,195.00$900.00$5,195.00
56Geotextile type DF schedule A (645.0111)SY125$2.34$5.05$8.44$8.44$8.44
57Geotextile type HR (645.0120)SY265$3.25$5.26$5.98$5.98$5.98
58Marking line epoxy 4-inch (646.1020)LF1,020$4.85$4.85$5.25$4.85$5.25
59Construction staking subgrade (650.4500)LF467$0.01$0.01$0.01$0.01$0.01
60Construction staking base (650.5000)LF401$0.01$0.01$0.01$0.01$0.01
61Construction staking structure layout (structure) 01. B-37-0473 (650.6501)EACH1$3,000.00$3,000.00$3,000.00$3,000.00$3,000.00
62Construction staking supplemental control (project) 01. 9478-03-71 (650.9911)EACH1$1,000.00$1,000.00$1,000.00$1,000.00$1,000.00
63Construction staking slope stakes (650.9920)LF467$1.20$1.20$1.20$1.20$1.20
64Sawing asphalt (690.0150)LF48$2.45$5.00$5.00$5.00$5.00
65Incentive strength concrete structures (715.0502)DOL1,458$1.00$1.00$1.00$1.00$1.00
66Maintaining bird deterrent system (station) 01. 10+00 (999.2005.S)EACH1$1,125.00$0.01$1.00$1,100.00$1,000.00
67On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS300$5.00$5.00$5.00$5.00$5.00
68On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00$5.00$5.00
69Special 01. removing existing timber piling (SPV.0090)LF150$31.00$37.36$35.00$75.00$30.00
WisDOT contract 20250408028: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy