WisDOT contract 20250513006 bid tabulation

City of Platteville, Camp Street; Lancaster Street to Elm Street (LOC STR, Grant County City Platteville, Camp Street). Let by Wisconsin DOT on May 13, 2025, Grant. 2 bids received; low bid $813,555 by Parisi Construction, LLC.

Owner
Wisconsin DOT
Letting
13 MAY 2025
Pay items
82
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Parisi Construction, LLC$813,555Low
2H. James & Sons, Inc$881,517+8.0%
WisDOT contract 20250513006: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Parisi Construction, LLC2. H. James & Sons, Inc
1Grubbing (201.0220)ID48$69.00$32.00
2Removing concrete pavement (204.0100)SY355$10.00$16.00
3Removing asphaltic surface (204.0110)SY190$15.00$25.00
4Removing curb & gutter (204.0150)LF2,030$7.30$5.50
5Removing concrete sidewalk (204.0155)SY345$17.25$12.00
6Removing inlets (204.0220)EACH7$670.00$800.00
7Removing storm sewer (size) 01. 12-inch (204.0245)LF593$26.00$20.00
8Removing storm sewer (size) 02. 15-inch (204.0245)LF25$26.00$30.00
9Removing storm sewer (size) 03. 18-inch (204.0245)LF55$28.00$30.00
10Excavation common (205.0100)CY3,350$21.75$22.00
11Backfill granular grade 2 (209.2100)CY950$10.00$0.01
12Finishing roadway (project) 01. 5996-01-72 (213.0100)EACH1$1,500.00$2,500.00
13Base aggregate dense 3/4-inch (305.0110)TON420$25.00$32.50
14Base aggregate dense 1 1/4-inch (305.0120)TON1,620$17.25$18.50
15Select crushed material (312.0110)TON2,500$17.25$18.50
16Tack coat (455.0605)GAL205$4.20$4.00
17Incentive density HMA pavement (460.2000)DOL800$1.00$1.00
18HMA pavement 4 LT 58-28 S (460.5224)TON850$98.00$92.05
19Asphaltic surface driveways and field entrances (465.0120)TON1$240.00$225.00
20Concrete sidewalk 4-inch (602.0405)SF4,620$7.25$6.50
21Curb ramp detectable warning field yellow (602.0505)SF30$50.00$50.00
22Concrete driveway 6-inch (602.0810)SY540$74.00$60.00
23Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF1,032$78.00$83.00
24Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF50$90.00$106.00
25Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF76$99.00$106.00
26Inlet covers type H (611.0624)EACH17$1,300.00$1,030.00
27Inlets 4-FT diameter (611.3004)EACH8$2,900.00$2,360.00
28Inlets 2X3-FT (611.3230)EACH9$2,400.00$1,775.00
29Insulation board polystyrene (inch) 01. 2-inch (612.0902.S)SY120$48.75$35.00
30Mobilization (619.1000)EACH1$45,000$114,400
31Water (624.0100)MGAL30$35.00$100.00
32Topsoil (625.0100)SY1,400$9.30$11.50
33Mobilizations erosion control (628.1905)EACH9$450.00$420.00
34Mobilizations emergency erosion control (628.1910)EACH4$270.00$250.00
35Erosion mat urban class I type A (628.2006)SY1,400$2.60$2.48
36Inlet protection type A (628.7005)EACH20$100.00$96.00
37Inlet protection type C (628.7015)EACH20$87.00$82.00
38Fertilizer type B (629.0210)CWT1$110.00$99.00
39Seeding mixture no. 40 (630.0140)LB65$13.75$13.00
40Seed water (630.0500)MGAL40$26.50$25.00
41Posts tubular steel 2X2-inch X 14- FT (634.0814)EACH7$270.00$250.00
42Signs type II reflective H (637.2210)SF15.54$30.75$29.00
43Removing signs type II (638.2602)EACH4$52.00$49.00
44Removing small sign supports (638.3000)EACH4$64.00$60.00
45Field office type B (642.5001)EACH1$8,100.00$32,135
46Traffic control drums (643.0300)DAY3,737$0.25$0.25
47Traffic control barricades type III (643.0420)DAY594$1.60$1.50
48Traffic control warning lights type A (643.0705)DAY1,188$0.55$0.50
49Traffic control warning lights type C (643.0715)DAY990$0.25$0.25
50Traffic control signs (643.0900)DAY2,970$0.25$0.25
51Temporary marking line removable tape 6-inch (643.3180)LF365$2.50$2.35
52Temporary marking crosswalk removable tape 6-inch (643.3350)LF96$2.70$2.50
53Traffic control (643.5000)EACH1$16,100$15,225
54Temporary pedestrian surface matting (644.1440)SF5,350$3.70$3.50
55Temporary pedestrian curb ramp (644.1601)DAY396$6.40$6.00
56Temporary pedestrian detectable warning field (644.1605)SF32$16.75$15.70
57Temporary pedestrian barricade (644.1810)LF1,225$7.10$6.70
58Geogrid type SR (645.0220)SY5,000$1.90$2.50
59Marking line epoxy 6-inch (646.2020)LF3,350$0.70$0.65
60Marking stop line epoxy 18-inch (646.6120)LF41$21.25$20.00
61Marking crosswalk epoxy transverse line 6-inch (646.7420)LF226$18.25$17.25
62Marking curb epoxy (646.8120)LF367$9.30$8.75
63Construction staking storm sewer (650.4000)EACH17$130.00$120.00
64Construction staking subgrade (650.4500)LF1,237$1.30$1.25
65Construction staking base (650.5000)LF1,237$1.10$1.00
66Construction staking curb gutter and curb & gutter (650.5500)LF2,460$1.60$1.50
67Construction staking curb ramps (650.9000)EACH3$420.00$400.00
68Construction staking sidewalk (project) 01. 5996-01-72 (650.9500)EACH1$1,600.00$1,550.00
69Construction staking supplemental control (project) 01. 5996-01-72 (650.9911)EACH1$1,100.00$1,000.00
70Construction staking slope stakes (650.9920)LF1,237$1.10$1.00
71Sawing asphalt (690.0150)LF197$2.10$2.00
72Sawing concrete (690.0250)LF368$3.70$3.50
73On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,200$5.00$5.00
74On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00
75Special 01. core & pour sanitary manhole adjustment (SPV.0060)EACH3$1,600.00$1,600.00
76Special 02. core & pour water main valve adjustment (SPV.0060)EACH9$640.00$1,200.00
77Special 03. water service valve adjustment (SPV.0060)EACH6$240.00$600.00
78Special 04. salvage plastic pipe (SPV.0060)EACH1$1,300.00$750.00
79Special 05. erecting city owned signs type II (SPV.0060)EACH4$370.00$350.00
80Special 06. adjusting hydrant (SPV.0060)EACH3$1,300.00$1,600.00
81Special 01. concrete curb and gutter 24 inch type D (SPV.0090)LF2,460$22.00$20.00
82Special 02. void reducing asphalt membrane (SPV.0090)LF1,154$12.75$13.00
WisDOT contract 20250513006: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy