WisDOT contract 20250812003 bid tabulation

5163-07-72. Let by Wisconsin DOT on August 12, 2025, La Crosse. 3 bids received; low bid $9,506,768 by Gerke Excavating Inc.

Owner
Wisconsin DOT
Letting
12 AUG 2025
Pay items
241
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Gerke Excavating Inc$9,506,768Low
2Zenith Tech., Inc. - Waukesha$10,498,740+10%
3Integrity Grading and Excavating, Inc.$11,340,942+19%
WisDOT contract 20250812003: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Gerke Excavating Inc2. Zenith Tech., Inc. - Waukesha3. Integrity Grading and Excavating, Inc.
1Clearing (201.0105)STA19$715.00$715.00$715.00
2Grubbing (201.0205)STA19$349.00$349.00$349.00
3Removing small pipe culverts (203.0100)EACH19$492.21$510.02$638.18
4Removing structure over waterway minimal debris (structure) 01. B-32- 163 (203.0260)EACH1$175,000$650,000$275,000
5Removing concrete pavement (204.0100)SY512$7.85$7.85$9.36
6Removing asphaltic surface (204.0110)SY9,242$3.24$3.24$3.76
7Removing asphaltic surface butt joints (204.0115)SY262$10.00$5.08$10.00
8Removing asphaltic surface milling (204.0120)SY1,050$7.15$33.20$7.15
9Removing curb & gutter (204.0150)LF1,088$3.26$3.26$11.00
10Removing concrete sidewalk (204.0155)SY14$17.01$17.01$49.84
11Removing guardrail (204.0165)LF2,753$2.30$2.30$2.30
12Removing surface drains (204.0190)EACH8$401.79$401.79$615.45
13Removing concrete bases (204.0195)EACH1$321.04$321.04$500.00
14Removing inlets (204.0220)EACH3$891.19$891.19$1,673.21
15Removing storm sewer (size) 01. 12-inch (204.0245)LF28$96.27$96.27$60.73
16Removing storm sewer (size) 02. 24-inch (204.0245)LF160$67.32$67.32$47.26
17Sealing pipes (204.0280)EACH1$2,069.03$2,069.03$1,868.37
18Excavation common (205.0100)CY43,163$8.25$8.26$22.00
19Excavation for structures bridges (structure) 01. B-32-163 (206.1001)EACH1$32,372$180,000$50,000
20Excavation for structures culverts (structure) 01. C-32-104 (206.2001)EACH1$22,557$17,746$50,000
21Borrow (208.0100)CY6,231$13.53$13.53$26.74
22Backfill structure type A (210.1500)TON770$25.22$25.22$40.45
23Backfill structure type B (210.2500)TON1,348$25.45$20.25$33.83
24Prepare foundation for asphaltic shoulders (211.0400)STA1$933.61$933.61$500.00
25Finishing roadway (project) 01. 5163-07-72 (213.0100)EACH1$5,187.73$2,500.00$500.00
26Base aggregate dense 3/4-inch (305.0110)TON1,655$21.54$21.54$33.00
27Base aggregate dense 1 1/4-inch (305.0120)TON32,863$15.20$15.20$20.00
28Select crushed material (312.0110)TON35,680$18.38$18.40$21.64
29QMP base aggregate dense 1 1/4- inch compaction (371.2000.S)EACH17$324.12$300.00$324.12
30Concrete pavement approach slab (415.0410)SY251$173.01$173.01$173.01
31HMA cold weather paving (450.4000)TON65$5.50$5.50$5.50
32Tack coat (455.0605)GAL4,052$6.05$6.05$6.05
33Incentive density HMA pavement (460.2000)DOL7,260$1.00$1.00$1.00
34HMA pavement 3 MT 58-28 S (460.6223)TON7,230$101.43$101.43$101.43
35HMA pavement 4 MT 58-28 S (460.6224)TON4,360$103.70$103.70$103.70
36Asphaltic surface (465.0105)TON1,490$131.14$131.14$131.14
37Asphaltic surface driveways and field entrances (465.0120)TON161$199.11$199.11$199.91
38Asphaltic surface temporary (465.0125)TON2,822$104.47$104.47$104.47
39Asphaltic curb (465.0310)LF351$11.33$11.33$11.33
40Asphaltic flumes (465.0315)SY35$185.74$185.74$185.74
41Asphaltic rumble strips, shoulder (465.0520)LF12,691$0.45$0.80$0.35
42Asphaltic rumble strips, centerline (465.0560)LF5,104$0.61$0.80$0.35
43Concrete masonry bridges (502.0100)CY735$900.00$1,400.00$900.00
44Protective surface treatment (502.3200)SY1,410$4.00$4.00$4.00
45Pigmented surface sealer (502.3210)SY430$5.00$14.50$5.00
46Adhesive anchors no. 5 bar (502.4205)EACH269$25.00$25.00$25.00
47Adhesive anchors no. 6 bar (502.4206)EACH32$30.00$35.50$30.00
48Prestressed girder type I 36-inch (503.0136)LF660$350.00$285.00$350.00
49Removing and resetting prestressed girders (structure) 01. B-32-0163 (503.1006.S)EACH16$550.00$2,535.00$550.00
50Concrete masonry culverts (504.0100)CY177$698.00$698.00$698.00
51Concrete masonry endwalls (504.0900)CY30$1,520.00$1,520.00$1,520.00
52Bar steel reinforcement HS structures (505.0400)LB20,550$2.42$1.28$1.21
53Bar steel reinforcement HS coated structures (505.0600)LB140,890$2.51$1.50$1.30
54Bar couplers no. 6 (505.0906)EACH12$80.00$187.00$80.00
55Bearing pads elastomeric non- laminated (506.2605)EACH56$150.00$107.00$150.00
56Steel diaphragms (structure) 01. B- 32-163 (506.4000)EACH24$850.00$1,900.00$850.00
57Temporary shoring (511.1100)SF920$40.00$40.00$40.00
58Temporary shoring (structure) 01. B-32-163 (511.1200)SF680$30.00$34.60$30.00
59Temporary shoring (structure) 02. C-32-0104 (511.1200)SF2,153$15.00$17.85$15.00
60Railing steel type C2 (513.7011)LF248$250.00$215.00$250.00
61Rubberized membrane waterproofing (516.0500)SY69$25.00$55.00$25.00
62Apron endwalls for culvert pipe 12- inch (520.1012)EACH7$379.96$379.96$921.72
63Apron endwalls for culvert pipe 15- inch (520.1015)EACH7$401.44$401.44$952.43
64Apron endwalls for culvert pipe 18- inch (520.1018)EACH5$441.14$441.14$994.94
65Apron endwalls for culvert pipe 24- inch (520.1024)EACH5$596.14$596.14$1,088.18
66Apron endwalls for culvert pipe 30- inch (520.1030)EACH5$840.81$840.81$1,316.55
67Culvert pipe temporary 15-inch (520.2015)LF4$401.59$401.59$485.08
68Culvert pipe class III-A 12-inch (520.3312)LF64$47.18$47.18$105.81
69Culvert pipe class III-A 15-inch (520.3315)LF63$48.30$48.30$109.52
70Culvert pipe class III-A 18-inch (520.3318)LF50$54.40$54.40$114.46
71Culvert pipe class III-A 24-inch (520.3324)LF71$64.26$64.26$128.21
72Culvert pipe class III-A 30-inch (520.3330)LF58$78.72$78.72$137.87
73Culvert pipe class III-B non-metal 12-inch (520.3612)LF16$86.64$86.64$134.87
74Culvert pipe class III-B non-metal 15-inch (520.3615)LF20$74.28$74.28$110.63
75Culvert pipe class III-B non-metal 18-inch (520.3618)LF20$80.46$80.46$116.19
76Culvert pipe class III-B non-metal 24-inch (520.3624)LF80$76.54$76.54$139.61
77Culvert pipe class III-B non-metal 30-inch (520.3630)LF122$113.85$113.85$170.56
78Culvert pipe class IV 12-inch (520.4112)LF29$70.57$70.57$130.79
79Concrete collars for pipe (520.8000)EACH6$611.76$611.76$1,129.20
80Cleaning culvert pipes (520.8700)EACH3$2,471.89$975.00$975.00
81Culvert pipe reinforced concrete class IV 24-inch (522.0424)LF176$102.29$102.29$166.92
82Culvert pipe reinforced concrete class IV 36-inch (522.0436)LF432$208.60$208.60$379.19
83Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH2$2,036.72$2,036.72$1,626.23
84Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015)EACH2$2,094.47$2,094.47$1,678.98
85Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH8$1,771.42$1,771.42$1,905.63
86Culvert pipe reinforced concrete horizontal elliptical class HE-IV 34X53-inch (522.2434)LF56$272.58$272.58$1,051.03
87Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 34X53-inch (522.2634)EACH2$3,083.95$3,083.95$3,811.24
88Pile points (550.0500)EACH27$150.00$120.00$150.00
89Piling steel HP 12-inch X 53 LB (550.1120)LF2,430$40.00$82.00$40.00
90Concrete curb & gutter 30-inch type A (601.0409)LF132$33.66$33.66$33.66
91Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553)LF3,130$24.33$24.33$24.33
92Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF86$77.68$77.68$77.68
93Concrete curb & gutter 4-inch sloped 30-inch type TBT (601.0584)LF71$88.51$88.51$88.51
94Concrete curb & gutter 4-inch sloped 30-inch type TBTT (601.0586)LF11$91.14$91.14$91.14
95Concrete sidewalk 5-inch (602.0410)SF1,157$7.91$7.91$7.91
96Curb ramp detectable warning field yellow (602.0505)SF40$53.45$53.45$53.45
97Curb ramp detectable warning field radial yellow (602.0605)SF64$77.48$77.48$77.48
98Concrete surface drains (602.3010)CY9$1,199.14$1,199.14$1,199.14
99Concrete barrier type S42 (603.1142)LF725$125.74$125.74$125.74
100Concrete barrier temporary precast delivered (603.8000)LF8,350$13.88$13.88$13.88
101Concrete barrier temporary precast installed (603.8125)LF13,919$3.10$3.10$3.10
102Anchoring concrete barrier temporary precast (603.8500)LF5,116$9.25$9.25$9.25
103Anchoring concrete barrier temporary precast on bridge decks (603.8505)LF446$11.25$11.25$11.25
104Riprap medium (606.0200)CY65$85.86$85.86$181.71
105Riprap heavy (606.0300)CY606$87.78$86.34$149.04
106Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF42$71.46$71.46$131.10
107Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF416$73.17$73.17$135.70
108Storm sewer pipe reinforced concrete class IV 24-inch (608.0424)LF580$102.71$102.71$150.03
109Storm sewer pipe class III-A 12- inch (608.3012)LF58$45.65$45.65$110.13
110Storm sewer pipe class III-A 15- inch (608.3015)LF59$48.22$48.22$117.36
111Storm sewer pipe class III-A 18- inch (608.3018)LF152$52.37$52.37$117.94
112Storm sewer pipe class III-A 24- inch (608.3024)LF371$61.84$61.84$114.17
113Storm sewer pipe class III-A 30- inch (608.3030)LF43$90.76$90.76$150.21
114Manhole covers type J (611.0530)EACH5$862.95$862.95$705.47
115Inlet covers type B (611.0606)EACH2$1,356.76$1,356.76$1,070.69
116Inlet covers type HM (611.0627)EACH9$1,121.97$1,121.97$978.31
117Inlet covers type HM-S (611.0636)EACH2$1,314.03$1,314.03$978.31
118Inlet covers type MS (611.0642)EACH5$875.65$875.65$729.39
119Catch basins 4-FT diameter (611.1004)EACH11$3,412.08$3,412.08$3,851.81
120Manholes 4-FT diameter (611.2004)EACH5$3,887.65$3,887.65$6,439.61
121Inlets 2X2-FT (611.3220)EACH2$2,199.35$2,199.35$3,478.16
122Inlets median 2 grate (611.3902)EACH5$4,377.08$4,377.08$4,863.52
123Adjusting manhole covers (611.8110)EACH5$741.82$741.82$626.14
124Cover plates temporary (611.8120.S)EACH5$410.19$410.19$326.12
125Pipe underdrain wrapped 6-inch (612.0406)LF100$15.19$15.19$4.14
126Anchor assemblies for steel plate beam guard (614.0150)EACH2$200.00$300.00$200.00
127Crash cushions temporary (614.0905)EACH35$2,606.60$4,665.47$2,106.60
128MGS guardrail 3 (614.2300)LF382$23.30$23.30$23.30
129MGS thrie beam transition (614.2500)LF160$95.00$95.00$95.00
130MGS guardrail terminal eat (614.2610)EACH6$3,470.00$3,470.00$3,470.00
131Maintenance and repair of haul roads (project) 01. 5163-07-72 (618.0100)EACH1$0.01$3,500.00$500.00
132Mobilization (619.1000)EACH1$1,502,508$1,455,000$1,401,393
133Concrete corrugated median (620.0100)SF13,319$11.50$11.50$11.50
134Concrete median sloped nose (620.0300)SF49$10.73$10.73$10.73
135Water (624.0100)MGAL619$47.38$47.38$58.24
136Salvaged topsoil (625.0500)SY87,883$0.96$0.96$5.61
137Silt fence (628.1504)LF16,320$1.80$1.80$1.80
138Silt fence maintenance (628.1520)LF16,320$0.01$0.01$0.01
139Silt fence heavy duty (628.1530.S)LF3,900$12.50$12.50$12.50
140Silt fence heavy duty maintenance (628.1535.S)LF3,900$0.35$0.35$0.35
141Mobilizations erosion control (628.1905)EACH10$250.00$250.00$250.00
142Mobilizations emergency erosion control (628.1910)EACH5$250.00$250.00$250.00
143Erosion mat urban class I type B (628.2008)SY87,883$1.35$1.35$1.35
144Inlet protection type A (628.7005)EACH22$80.00$80.00$80.00
145Inlet protection type C (628.7015)EACH13$40.00$40.00$40.00
146Temporary ditch checks (628.7504)LF862$5.75$5.75$5.75
147Culvert pipe checks (628.7555)EACH277$13.80$13.80$13.80
148Rock bags (628.7570)EACH400$12.50$12.50$12.50
149Fertilizer type B (629.0210)CWT66.90$85.00$85.00$85.00
150Seeding mixture no. 40 (630.0140)LB93$10.00$10.00$10.00
151Seeding mixture no. 75 (630.0175)LB575$60.00$60.00$60.00
152Seeding temporary (630.0200)LB332$2.75$2.75$2.75
153Seeding nurse crop (630.0400)LB657$3.00$3.00$3.00
154Seed water (630.0500)MGAL1,544$1.00$1.00$1.00
155Posts wood 4X6-inch X 14-FT (634.0614)EACH21$80.00$80.00$80.00
156Posts wood 4X6-inch X 16-FT (634.0616)EACH43$84.00$84.00$84.00
157Posts wood 4X6-inch X 18-FT (634.0618)EACH8$90.00$90.00$90.00
158Signs type II reflective H (637.2210)SF225.93$17.75$17.75$17.75
159Signs type II reflective F (637.2230)SF148.57$20.15$20.15$20.15
160Moving signs type II (638.2102)EACH25$105.00$105.00$105.00
161Removing signs type II (638.2602)EACH36$16.60$16.60$16.60
162Removing small sign supports (638.3000)EACH57$16.60$16.60$16.60
163Field office type C (642.5201)EACH1$13,683$20,000$30,800
164Traffic control drums (643.0300)DAY28,682$0.20$0.16$0.20
165Traffic control barricades type III (643.0420)DAY2,315$0.92$0.65$0.92
166Traffic control flexible tubular marker posts (643.0500)EACH225$15.00$45.00$15.00
167Traffic control flexible tubular marker bases (643.0600)EACH225$20.00$20.00$20.00
168Traffic control warning lights type A (643.0705)DAY2,310$0.32$0.20$0.32
169Traffic control warning lights type C (643.0715)DAY5,727$0.14$0.20$0.14
170Traffic control signs (643.0900)DAY15,341$0.28$0.21$0.28
171Traffic control covering signs type II (643.0920)EACH8$150.00$125.00$150.00
172Traffic control signs PCMS (643.1050)DAY14$65.00$54.50$65.00
173Traffic control cones 42-inch (643.1070)DAY5,156$0.36$0.16$0.36
174Temporary marking line paint 4- inch (643.3105)LF1,939$0.41$0.19$0.41
175Temporary marking line paint 6- inch (643.3165)LF139,643$0.44$0.20$0.44
176Temporary marking line removable tape 6-inch (643.3180)LF2,088$2.35$2.05$2.35
177Temporary marking line paint 10- inch (643.3265)LF6,227$0.90$0.30$0.90
178Temporary marking stop line paint 18-inch (643.3805)LF102$10.00$3.25$10.00
179Traffic control (643.5000)EACH1$81,725$54,225$81,725
180Temporary pedestrian barricade (644.1810)LF15$55.00$15.00$55.00
181Geotextile type C (645.0105)SY298$3.58$3.90$1.59
182Geotextile type DF schedule A (645.0111)SY52$16.43$16.10$2.94
183Geotextile type HR (645.0120)SY1,478$2.66$2.74$1.71
184Geogrid type SR (645.0220)SY33,417$1.27$1.22$0.66
185Marking line epoxy 4-inch (646.1020)LF3,973$0.75$0.45$0.75
186Marking line epoxy 6-inch (646.2020)LF490$0.90$1.00$0.90
187Marking line grooved wet ref epoxy 6-inch (646.2040)LF28,243$1.53$1.66$1.53
188Marking line grooved wet ref epoxy 10-inch (646.4040)LF2,195$3.00$3.30$3.00
189Marking arrow epoxy (646.5020)EACH10$315.00$450.00$315.00
190Marking word epoxy (646.5120)EACH3$460.00$475.00$460.00
191Marking symbol epoxy (646.5220)EACH2$330.00$425.00$330.00
192Marking stop line epoxy 18-inch (646.6120)LF62$18.00$18.50$18.00
193Marking diagonal epoxy 12-inch (646.7120)LF162$14.00$18.00$14.00
194Marking corrugated median epoxy (646.8020)SF3,581$5.25$10.45$5.25
195Marking curb epoxy (646.8120)LF10$9.00$10.00$9.00
196Marking island nose epoxy (646.8220)EACH7$300.00$333.00$300.00
197Marking removal line 4-inch (646.9000)LF9,230$0.65$0.40$0.65
198Marking removal line 8-inch (646.9100)LF734$1.30$1.30$1.30
199Marking removal line wide (646.9200)LF39$2.00$3.70$2.00
200Marking removal special marking (646.9300)EACH4$175.00$85.00$175.00
201Locating no-passing zones (648.0100)MI1.52$2,500.00$633.00$2,500.00
202Construction staking storm sewer (650.4000)EACH26$110.00$115.00$115.00
203Construction staking subgrade (650.4500)LF14,856$0.26$0.10$0.10
204Construction staking base (650.5000)LF14,856$1.00$1.00$1.00
205Construction staking curb gutter and curb & gutter (650.5500)LF3,348$1.50$1.00$1.00
206Construction staking pipe culverts (650.6000)EACH22$150.00$115.00$115.00
207Construction staking structure layout (structure) 01. B-32-163 (650.6501)EACH1$1,500.00$2,500.00$2,500.00
208Construction staking structure layout (structure) 02. C-32-104 (650.6501)EACH1$1,200.00$2,500.00$2,500.00
209Construction staking concrete barrier (650.7500)LF446$2.00$5.00$5.00
210Construction staking curb ramps (650.9000)EACH4$125.00$145.00$145.00
211Construction staking sidewalk (project) 01. 5163-07-72 (650.9500)EACH1$1,200.00$2,000.00$2,000.00
212Construction staking sidewalk (project) 01. 5991-06-73 (650.9500)EACH1$5,000.00$1,750.00$1,750.00
213Construction staking supplemental control (project) 01. 5163-07-72 (650.9911)EACH1$1,500.00$3,500.00$3,500.00
214Construction staking supplemental control (project) 01. 5991-06-73 (650.9911)EACH1$850.00$3,000.00$3,000.00
215Construction staking slope stakes (650.9920)LF8,900$1.00$1.00$1.00
216Sawing asphalt (690.0150)LF18,187$1.55$1.55$1.59
217Sawing concrete (690.0250)LF182$2.95$2.95$2.90
218Incentive strength concrete structures (715.0502)DOL5,472$1.00$1.00$1.00
219Incentive strength concrete barrier (715.0603)DOL363$1.00$1.00$1.00
220Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00
221Incentive iri ride (740.0440)DOL6,050$1.00$1.00$1.00
222Railroad flagging reimbursement (801.0117)DOL39,000$1.00$1.00$1.00
223Installing and maintaining bird deterrent system (station) 01. station 619+58.35 (999.2000.S)EACH1$0.01$23,800$0.01
224On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,400$5.00$5.00$5.00
225On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS4,900$5.00$5.00$5.00
226Special 01. driveway assistance device system 5163-07-72 (SPV.0045)DAY301$135.60$72.50$135.60
227Special 01. research and locate existing land parcel monuments (SPV.0060)EACH18$200.00$250.00$250.00
228Special 02. verify landmark reference monuments (SPV.0060)EACH4$150.00$1,000.00$1,000.00
229Special 03. verify and replace existing land parcel monuments (SPV.0060)EACH18$350.00$500.00$500.00
230Special 04. inlet covers flat temporary (SPV.0060)EACH2$1,323.27$1,323.27$1,358.75
231Special 05. temporary support B- 32-0163 (SPV.0060)EACH1$0.01$30,000$0.01
232Special 06. temporary water diversion, C-32-104 (SPV.0060)EACH1$3,727.87$7,500.00$100,000
233Special 07. temporary water diversion, sta 581+45 (SPV.0060)EACH1$8,878.69$8,878.69$100,000
234Special 08. temporary pipe connection (SPV.0060)EACH4$4,715.40$4,715.40$5,105.05
235Special 09. installing city furnished signs (SPV.0060)EACH4$75.00$75.00$75.00
236Special 01. shortgrass prairie seed mix (SPV.0085)LB1$750.00$750.00$750.00
237Special 01. culvert pipe reinforced concrete pipe arch class IV 59X36- inch (SPV.0090)LF330$415.49$415.49$557.67
238Special 02. pipe underdrain (6- inch) with geotextile fabric and aggregate (SPV.0090)LF385$28.46$28.46$63.37
239Special 03. removing centerline rumble strips (SPV.0090)LF442$28.22$28.22$28.22
240Special 04. marking railroad stop line epoxy 24-inch (SPV.0090)LF35$30.00$30.50$30.50
241Special 01. 16-inch X 2-inch select crushed material (SPV.0195)TON42$48.17$48.17$53.53
WisDOT contract 20250812003: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of August 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy