WisDOT contract 20250812011 bid tabulation

Kewaunee Co, CTH Kb; Black Creek Bridge (CTH KB, Kewaunee County Kewaunee Co, CTH KB). Let by Wisconsin DOT on August 12, 2025, Kewaunee. 5 bids received.

Owner
Wisconsin DOT
Letting
12 AUG 2025
Pay items
70
Data through
10 NOV 2026

4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
2Radtke Contractors Inc.$625,728+1.0%
3Larson Construction Co., Inc.$684,408+10%
4Sheet Piling Services LLC$721,107+16%
5Lunda Construction Company$798,519+28%
WisDOT contract 20250812011: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Radtke Contractors Inc.2. Larson Construction Co., Inc.3. Sheet Piling Services LLC4. Lunda Construction Company
1Grubbing (201.0205)STA4$950.00$1,500.00$745.00$745.00
2Removing structure over waterway minimal debris (structure) 01. B-31- 0893 (203.0260)EACH1$53,804$39,500$40,000$60,000
3Removing asphaltic surface (204.0110)SY680$5.00$6.18$6.18$6.18
4Excavation common (205.0100)CY340$14.40$21.76$21.76$21.76
5Excavation marsh (205.0400)CY100$20.00$22.90$22.90$22.90
6Excavation for structures bridges (structure) 01. B-31-0113 (206.1001)EACH1$20,959$34,000$8,795.00$8,975.00
7Borrow (208.0100)CY653$18.00$15.00$15.00$15.00
8Select borrow (208.1100)CY150$29.00$37.60$37.60$37.60
9Backfill structure type A (210.1500)TON528$30.77$25.87$25.87$25.87
10Base aggregate dense 3/4-inch (305.0110)TON90$50.00$49.00$49.00$49.00
11Base aggregate dense 1 1/4-inch (305.0120)TON910$17.45$19.12$19.12$19.12
12Tack coat (455.0605)GAL60$15.30$15.30$15.30$15.30
13Asphaltic surface (465.0105)TON240$148.00$148.00$148.00$148.00
14Concrete masonry bridges (502.0100)CY200$617.05$672.00$1,250.00$1,200.00
15Protective surface treatment (502.3200)SY250$3.51$4.00$2.50$5.00
16Bar steel reinforcement HS structures (505.0400)LB4,940$1.29$1.20$1.25$1.15
17Bar steel reinforcement HS coated structures (505.0600)LB30,410$1.30$1.20$1.35$1.29
18Railing tubular type M (513.4061)LF105$277.54$315.00$275.00$275.00
19Rubberized membrane waterproofing (516.0500)SY12$63.44$50.00$18.00$25.00
20Pile points (550.0500)EACH14$105.50$200.00$125.00$205.73
21Piling steel HP 10-inch X 42 LB (550.1100)LF700$32.07$54.51$36.00$60.00
22Riprap heavy (606.0300)CY275$76.54$82.00$81.30$81.30
23Pipe underdrain wrapped 6-inch (612.0406)LF150$4.14$10.00$6.00$10.00
24MGS guardrail 3 (614.2300)LF75$35.00$35.00$35.00$35.00
25MGS thrie beam transition (614.2500)LF157.60$92.00$92.00$92.00$92.00
26MGS guardrail terminal eat (614.2610)EACH4$4,000.00$4,000.00$4,000.00$4,000.00
27Mobilization (619.1000)EACH1$81,744$103,150$86,082$112,617
28Water (624.0100)MGAL22$30.00$50.00$50.00$50.00
29Topsoil (625.0100)SY1,380$3.50$7.64$7.64$7.64
30Mulching (627.0200)SY640$1.00$1.00$1.00$1.00
31Silt fence (628.1504)LF1,000$2.50$2.50$2.50$2.50
32Silt fence maintenance (628.1520)LF2,000$0.01$0.01$0.01$0.01
33Mobilizations erosion control (628.1905)EACH3$250.00$250.00$250.00$250.00
34Mobilizations emergency erosion control (628.1910)EACH5$100.00$100.00$100.00$100.00
35Erosion mat urban class I type B (628.2008)SY1,380$1.90$1.90$1.90$1.90
36Turbidity barriers (628.6005)SY224$58.00$49.00$0.01$58.00
37Rock bags (628.7570)EACH75$15.00$15.00$15.00$15.00
38Fertilizer type B (629.0210)CWT1.50$150.00$150.00$150.00$150.00
39Seeding mixture no. 20 (630.0120)LB70$9.25$9.25$9.25$9.25
40Seeding temporary (630.0200)LB40$5.00$5.00$5.00$5.00
41Seeding borrow pit (630.0300)LB30$12.00$12.00$12.00$12.00
42Seed water (630.0500)MGAL40$5.00$5.00$5.00$5.00
43Posts wood 4X6-inch X 12-FT (634.0612)EACH4$150.00$150.00$150.00$150.00
44Signs type II reflective F (637.2230)SF12$40.00$40.00$40.00$40.00
45Moving signs type II (638.2102)EACH3$75.00$75.00$75.00$75.00
46Removing signs type II (638.2602)EACH14$40.00$40.00$40.00$40.00
47Removing small sign supports (638.3000)EACH14$40.00$40.00$40.00$40.00
48Field office type B (642.5001)EACH1$1,819.36$4,300.00$4,000.00$3,000.00
49Traffic control barricades type III (643.0420)DAY6,882$0.39$0.39$0.39$0.39
50Traffic control warning lights type A (643.0705)DAY11,988$0.13$0.13$0.13$0.13
51Traffic control signs (643.0900)DAY29,082$0.25$0.25$0.25$0.25
52Traffic control covering signs type II (643.0920)EACH8$105.00$105.00$105.00$105.00
53Traffic control signs PCMS (643.1050)DAY14$60.00$60.00$60.00$60.00
54Traffic control (643.5000)EACH1$5,150.00$5,150.00$5,150.00$5,150.00
55Geotextile type DF schedule A (645.0111)SY96$4.81$6.00$6.00$6.00
56Geotextile type HR (645.0120)SY490$4.56$3.00$3.00$3.00
57Marking line epoxy 6-inch (646.2020)LF1,380$3.85$3.85$3.75$4.00
58Construction staking subgrade (650.4500)LF89$0.01$0.01$0.01$5.00
59Construction staking base (650.5000)LF293$1.00$1.00$1.00$1.00
60Construction staking structure layout (structure) 01. B-31-0113 (650.6501)EACH1$3,200.00$3,200.00$3,200.00$3,200.00
61Construction staking supplemental control (project) 01. 4386-00-01 (650.9911)EACH1$10.00$10.00$10.00$10.00
62Construction staking slope stakes (650.9920)LF293$5.00$5.00$5.00$5.00
63Conduit rigid nonmetallic schedule 40 1 1/4-inch (652.0215)LF143$8.00$8.00$8.00$8.00
64Sawing asphalt (690.0150)LF60$2.95$2.95$2.95$2.95
65Incentive strength concrete structures (715.0502)DOL1,200$1.00$1.00$1.00$1.00
66On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS300$5.00$5.00$5.00$5.00
67On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00$5.00
68Special 01. flashing stainless steel (SPV.0090)LF91$76.29$40.00$38.00$65.00
69Special 02. removing existing timber piling (SPV.0090)LF244$33.31$36.00$5.00$40.00
70Special 01. select crushed material for travel corridor (SPV.0195)TON22$55.13$75.00$75.00$75.00
WisDOT contract 20250812011: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of August 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy