WisDOT contract 20250812015 bid tabulation

Wausau - Wittenberg; CTH Q to Bass Lake Road, Wb (STH 029, Marathon County Wausau - Wittenberg). Let by Wisconsin DOT on August 12, 2025, Marathon. 5 bids received; low bid $3,175,990 by Vinton Construction Company.

Owner
Wisconsin DOT
Letting
12 AUG 2025
Pay items
147
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Vinton Construction Company$3,175,990Low
2Chippewa Concrete Services, Inc.$3,489,602+10%
3Michels Road & Stone, Inc.$3,594,954+13%
4Zignego Company, Inc.$3,823,605+20%
5Integrity Grading and Excavating, Inc.$3,837,847+21%
WisDOT contract 20250812015: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Vinton Construction Company2. Chippewa Concrete Services, Inc.3. Michels Road & Stone, Inc.4. Zignego Company, Inc.5. Integrity Grading and Excavating, Inc.
1Removing concrete pavement (204.0100)SY340$34.41$15.84$38.00$15.50$6.65
2Removing asphaltic surface (204.0110)SY3,660$3.94$4.34$4.50$4.25$2.00
3Removing asphaltic surface butt joints (204.0115)SY200$5.60$5.72$5.60$5.60$1.60
4Removing asphaltic surface milling (204.0120)SY27,700$2.34$2.39$2.34$2.34$2.00
5Removing curb & gutter (204.0150)LF650$7.83$5.11$8.00$5.00$8.07
6Removing concrete sidewalk (204.0155)SY210$12.96$10.22$13.00$10.00$3.92
7Removing guardrail (204.0165)LF1,060$3.00$3.07$3.00$3.00$3.00
8Removing concrete slope paving (204.0175)SY280$12.00$12.26$12.00$12.00$12.00
9Removing delineators and markers (204.0180)EACH147$20.00$30.46$20.00$20.00$20.00
10Removing inlets (204.0220)EACH2$391.25$511.00$950.00$500.00$1,463.93
11Removing storm sewer (size) 01. 24-inch (204.0245)LF207$17.26$25.55$32.00$25.00$37.87
12Abandoning sewer (204.0291.S)CY26$181.73$740.95$450.00$725.00$546.22
13Excavation common (205.0100)CY9,050$11.00$12.26$11.80$12.00$13.28
14Prepare foundation for asphaltic paving (project) 01. 1053-07-61 (211.0101)EACH1$17,560$17,946$17,560$17,560$17,560
15Prepare foundation for asphaltic shoulders (211.0400)STA6$348.00$355.66$348.00$348.00$348.00
16Base aggregate dense 3/4-inch (305.0110)TON4,370$22.36$27.98$23.10$27.38$31.01
17Base aggregate dense 1 1/4-inch (305.0120)TON13,300$17.15$21.26$15.00$20.80$20.00
18Concrete pavement approach slab (415.0410)SY221$225.00$321.52$196.56$300.00$314.60
19Rout and seal (415.6000.S)LF46,300$0.75$0.99$0.97$0.97$0.97
20Drilled tie bars (416.0610)EACH1,110$9.00$8.99$18.33$30.00$10.72
21Drilled dowel bars (416.0620)EACH2,210$14.50$16.86$21.02$30.00$15.88
22Concrete pavement repair (416.1710)SY1,030$98.41$98.06$107.65$146.00$100.97
23Concrete pavement replacement (416.1720)SY3,470$102.41$98.06$118.06$146.00$100.97
24Continuous diamond grinding concrete pavement (420.1000)SY6,540$6.92$7.00$6.85$6.85$10.24
25HMA cold weather paving (450.4000)TON975$0.80$0.82$0.80$0.80$0.80
26Tack coat (455.0605)GAL4,010$5.19$5.30$5.19$5.19$5.19
27Incentive density HMA pavement (460.2000)DOL2,496$1.00$1.00$1.00$1.00$1.00
28HMA pavement 4 LT 58-28 S (460.5224)TON9,170$83.81$85.65$83.81$83.81$83.81
29Asphaltic surface (465.0105)TON23$152.04$155.38$152.04$152.04$152.04
30Asphaltic surface patching (465.0110)TON200$143.51$146.67$143.51$143.51$143.51
31Asphaltic rumble strips, shoulder divided roadway (465.0510)LF20,300$0.33$0.51$0.50$0.50$0.33
32Pigmented surface sealer reseal (502.3205)SY402$8.96$9.16$8.96$8.96$8.96
33Polymer overlay (509.5100.S)SY1,563$37.45$38.27$37.45$37.45$37.45
34Removing polymer overlay (structure) 01. B-37-0377 (509.9015.S)SY1,563$9.65$9.86$9.65$9.65$9.65
35Apron endwalls for culvert pipe 18- inch (520.1018)EACH2$461.74$494.65$1,500.00$484.00$1,546.50
36Concrete collars for pipe (520.8000)EACH4$884.13$868.70$1,100.00$850.00$1,569.58
37Apron endwalls for culvert pipe steel 12-inch (521.1012)EACH1$264.89$458.88$900.00$449.00$815.39
38Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036)EACH2$2,519.06$2,586.68$3,600.00$2,531.00$3,453.94
39Culvert pipe corrugated polyethylene 12-inch (530.0112)LF158$54.36$56.72$81.10$55.50$65.51
40Concrete curb & gutter 30-inch type A (601.0409)LF280$58.00$64.29$45.00$60.00$62.91
41Concrete curb & gutter 4-inch sloped 30-inch type TBT (601.0584)LF160$58.00$64.29$45.00$60.00$62.91
42Concrete curb & gutter 4-inch sloped 30-inch type TBTT (601.0586)LF265$58.00$64.29$45.00$60.00$62.91
43Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588)LF190$60.50$66.01$45.00$60.00$64.59
44Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590)LF10$60.50$66.01$65.00$60.00$64.59
45Concrete sidewalk 5-inch (602.0410)SF1,170$13.25$16.32$8.50$12.00$15.97
46Curb ramp detectable warning field yellow (602.0505)SF40$35.00$63.89$60.00$100.00$62.51
47Curb ramp detectable warning field radial yellow (602.0605)SF17$55.00$69.33$70.00$200.00$67.84
48Concrete surface drains (602.3010)CY6$925.00$2,206.48$900.00$1,000.00$2,158.98
49Concrete rumble strips, shoulder divided roadway (602.3210)LF19,900$0.64$0.62$0.61$0.61$0.63
50Slope paving crushed aggregate (604.0500)SY295$40.00$40.88$56.27$40.00$40.00
51Riprap medium (606.0200)CY42$120.00$153.30$173.00$150.00$136.48
52Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF8$173.25$370.99$228.20$363.00$842.10
53Storm sewer pipe reinforced concrete class III 36-inch (608.0336)LF207$244.66$291.27$294.20$285.00$400.00
54Storm sewer pipe class III-B 18- inch (608.3618)LF756$59.57$81.76$107.60$80.00$100.00
55Reconstructing inlets (611.0430)EACH2$1,770.00$2,744.07$3,340.00$3,800.00$1,298.45
56Manhole covers type J (611.0530)EACH1$516.73$725.62$730.00$710.00$670.98
57Inlet covers type C (611.0612)EACH1$537.83$746.06$750.00$730.00$708.36
58Inlet covers type HM (611.0627)EACH1$740.39$970.90$970.00$950.00$947.39
59Inlet covers type MS (611.0642)EACH2$527.28$684.74$600.00$670.00$695.90
60Inlet covers type V (611.0654)EACH1$688.69$914.69$910.00$895.00$860.17
61Manholes 4-FT diameter (611.2004)EACH2$4,015.78$3,103.81$5,500.00$3,037.00$4,898.01
62Inlets 2X2-FT (611.3220)EACH1$2,838.85$2,473.24$3,400.00$2,420.00$4,243.58
63Inlets median 2 grate (611.3902)EACH1$7,321.50$9,003.82$7,900.00$8,810.00$8,374.82
64Barrier system grading shaping finishing (614.0010)EACH5$4,980.00$7,133.56$6,280.00$6,980.00$12,310
65Steel thrie beam bullnose terminal (614.0220)EACH2$15,000$15,330$15,000$15,000$15,000
66Steel thrie beam (614.0230)LF175$40.00$40.88$40.00$40.00$40.00
67Guardrail mow strip concrete (614.0395)SY18$150.00$112.42$110.00$500.00$122.00
68Guardrail mow strip emulsified asphalt (614.0397)SY23$150.00$102.20$100.00$150.00$150.00
69MGS guardrail 3 (614.2300)LF275$31.00$31.68$31.00$31.00$31.00
70MGS thrie beam transition (614.2500)LF160$90.00$91.98$90.00$90.00$90.00
71MGS guardrail terminal eat (614.2610)EACH4$4,300.00$4,394.60$4,300.00$4,300.00$4,300.00
72Fence woven wire (height) 01. 4- FT (616.0100)LF7,900$6.25$6.39$6.25$6.25$6.25
73Maintenance and repair of haul roads (project) 01. 1053-07-61 (618.0100)EACH1$0.01$2,555.00$5,000.00$1.00$500.00
74Mobilization (619.1000)EACH1$165,500$225,967$328,983$310,400$376,912
75Concrete median sloped nose (620.0300)SF15$15.00$17.52$50.00$20.00$17.14
76Water (624.0100)MGAL267$0.01$40.88$55.00$40.00$50.51
77Topsoil (625.0100)SY19,000$1.31$0.01$3.40$0.01$5.02
78Mulching (627.0200)SY950$1.00$1.02$1.00$1.00$1.00
79Silt fence (628.1504)LF1,300$2.50$2.56$2.50$2.50$2.50
80Silt fence maintenance (628.1520)LF1,300$0.01$0.01$0.01$0.01$0.01
81Mobilizations erosion control (628.1905)EACH4$100.00$102.20$100.00$100.00$100.00
82Mobilizations emergency erosion control (628.1910)EACH2$100.00$102.20$100.00$100.00$100.00
83Erosion mat urban class I type B (628.2008)SY15,000$1.80$1.84$1.80$1.80$1.80
84Erosion mat class II type C (628.2027)SY4,000$3.25$3.32$3.25$3.25$3.25
85Inlet protection type A (628.7005)EACH6$90.00$91.98$90.00$90.00$90.00
86Inlet protection type C (628.7015)EACH6$65.00$66.43$65.00$65.00$65.00
87Temporary ditch checks (628.7504)LF120$9.00$9.20$9.00$9.00$9.00
88Culvert pipe checks (628.7555)EACH14$20.00$20.44$20.00$20.00$20.00
89Rock bags (628.7570)EACH55$20.00$20.44$20.00$20.00$20.00
90Fertilizer type B (629.0210)CWT21$90.00$91.98$90.00$90.00$90.00
91Seeding mixture no. 30 (630.0130)LB867$9.00$9.20$9.00$9.00$9.00
92Seeding temporary (630.0200)LB200$4.00$4.09$4.00$4.00$4.00
93Seed water (630.0500)MGAL440$10.00$10.22$10.00$10.00$10.00
94Delineator posts steel (633.0100)EACH102$30.00$30.66$30.00$30.00$30.00
95Delineator reflectors (633.0500)EACH140$6.00$6.13$6.00$6.00$6.00
96Delineators temporary (633.1100)EACH62$25.00$25.55$29.80$25.00$25.00
97Markers culvert end (633.5200)EACH2$75.00$76.65$75.00$75.00$75.00
98Markers permanent flexible (633.5350)EACH180$75.00$76.65$75.00$75.00$75.00
99Moving signs type II (638.2102)EACH7$200.00$204.40$200.00$200.00$200.00
100Moving small sign supports (638.4000)EACH4$150.00$153.30$150.00$150.00$150.00
101Field office type B (642.5001)EACH1$10,000$7,665.00$7,000.00$10,000$12,000
102Traffic control drums (643.0300)DAY39,876$0.20$0.20$0.20$0.20$0.20
103Traffic control barricades type III (643.0420)DAY7,938$0.55$0.56$0.55$0.55$0.55
104Traffic control flexible tubular marker posts (643.0500)EACH541$34.50$35.26$34.50$34.50$34.50
105Traffic control flexible tubular marker bases (643.0600)EACH541$12.00$12.26$12.00$12.00$12.00
106Traffic control warning lights type A (643.0705)DAY16,074$0.12$0.12$0.12$0.12$0.12
107Traffic control warning lights type C (643.0715)DAY3,496$0.14$0.14$0.14$0.14$0.14
108Connected arrow board (643.0810.S)DAY222$10.00$10.22$10.00$10.00$10.00
109Traffic control signs (643.0900)DAY17,446$0.26$0.27$0.26$0.26$0.26
110Traffic control covering signs type I (643.0910)EACH7$225.00$229.95$225.00$225.00$225.00
111Traffic control covering signs type II (643.0920)EACH31$95.00$97.09$95.00$95.00$95.00
112Traffic control signs fixed message (643.1000)SF136$15.00$15.33$15.00$15.00$15.00
113Connected work zone start and end location markers (643.1220.S)DAY222$6.50$6.64$6.50$6.50$6.50
114Temporary marking line paint 6- inch (643.3165)LF79,400$0.25$0.26$0.25$0.25$0.25
115Traffic control (643.5000)EACH1$31,225$31,912$31,225$31,225$31,225
116Geotextile type HR (645.0120)SY48$10.00$24.53$5.00$24.00$7.40
117Marking line epoxy 6-inch (646.2020)LF1,220$0.50$0.51$0.50$0.50$0.50
118Marking line grooved black epoxy 6-inch (646.2025)LF11,900$0.75$0.77$0.75$0.75$0.85
119Marking line grooved wet ref epoxy 6-inch (646.2040)LF77,300$1.20$1.23$1.20$1.20$1.37
120Marking line grooved permanent tape 6-inch (646.2050)LF11,900$6.95$7.10$6.95$6.95$7.17
121Marking line epoxy 10-inch (646.4020)LF400$1.05$1.07$1.05$1.05$1.05
122Marking line grooved wet ref epoxy 10-inch (646.4040)LF3,000$2.50$2.56$2.50$2.50$2.75
123Marking arrow epoxy (646.5020)EACH4$350.00$357.70$350.00$350.00$362.55
124Marking word epoxy (646.5120)EACH2$360.00$367.92$360.00$360.00$367.05
125Marking stop line epoxy 18-inch (646.6120)LF40$15.25$15.59$15.25$15.25$15.25
126Cold weather marking epoxy 6-inch (646.6466)LF90,420$0.01$0.34$0.33$0.33$0.46
127Cold weather marking epoxy 10- inch (646.6470)LF3,400$0.01$1.07$1.05$1.05$1.05
128Marking chevron epoxy 24-inch (646.7220)LF90$23.00$23.51$23.00$23.00$25.00
129Marking crosswalk epoxy transverse line 6-inch (646.7420)LF80$14.50$14.82$14.50$14.50$14.50
130Marking curb epoxy (646.8120)LF30$7.50$7.67$7.50$7.50$7.50
131Marking island nose epoxy (646.8220)EACH4$273.00$279.82$273.00$273.00$273.80
132Marking removal line 4-inch (646.9000)LF30,100$0.24$0.25$0.24$0.24$0.24
133Marking removal line 6-inch (646.9002)LF380$0.90$0.92$0.90$0.90$0.90
134Construction staking storm sewer (650.4000)EACH3$400.00$408.80$400.00$400.00$400.00
135Construction staking subgrade (650.4500)LF4,240$0.01$0.01$0.01$0.01$0.01
136Construction staking base (650.5000)LF4,240$0.92$0.94$0.92$0.92$0.92
137Construction staking curb gutter and curb & gutter (650.5500)LF900$0.75$0.77$0.75$0.75$0.75
138Construction staking resurfacing reference (650.8000)LF28,710$0.11$0.11$0.11$0.11$0.11
139Construction staking curb ramps (650.9000)EACH5$200.00$204.40$200.00$200.00$200.00
140Construction staking supplemental control (project) 01. 1053-07-61 (650.9911)EACH1$10.00$10.22$100.00$10.00$10.00
141Sawing asphalt (690.0150)LF40$5.00$1.79$1.75$1.75$1.75
142Sawing concrete (690.0250)LF7,500$2.30$2.40$2.30$7.30$2.30
143Special 01. connect to existing (SPV.0060)EACH3$900.00$1,277.50$1,800.00$1,250.00$10,574
144Special 02. removing raised pavement markers and filling voids (SPV.0060)EACH240$50.00$72.56$71.00$71.00$71.00
145Special 01. concrete joint and crack cleaning and repair (SPV.0090)LF230$47.71$48.76$47.71$47.71$25.40
146Special 01. removing distressed asphaltic surface milling (SPV.0180)SY1,400$3.95$4.04$3.95$3.95$2.75
147Special 02. concrete pavement repair - centerline (SPV.0180)SY120$106.41$133.88$161.95$211.00$126.71
WisDOT contract 20250812015: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of August 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way