WisDOT contract 20250909022 bid tabulation

Rhinelander - Monico; STH 47 to STH 17 North (USH 008, Oneida County Rhinelander - Monico). Let by Wisconsin DOT on September 9, 2025, Oneida. 3 bids received; low bid $6,156,658 by Musson Bros., Inc..

Owner
Wisconsin DOT
Letting
09 SEP 2025
Pay items
205
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Musson Bros., Inc.$6,156,658Low
2Northeast Asphalt, Inc$6,306,561+2.0%
3James Peterson Sons, Inc.$6,794,113+10%
WisDOT contract 20250909022: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Musson Bros., Inc.2. Northeast Asphalt, Inc3. James Peterson Sons, Inc.
1Clearing (201.0105)STA12$680.84$680.84$400.00
2Grubbing (201.0205)STA12$608.75$608.75$630.00
3Removing small pipe culverts (203.0100)EACH5$1,145.36$1,145.36$1,327.00
4Removing concrete pavement (204.0100)SY51,100$1.00$1.00$3.57
5Removing asphaltic surface (204.0110)SY2,050$2.12$2.12$4.05
6Removing asphaltic surface butt joints (204.0115)SY480$5.10$5.10$5.10
7Removing asphaltic surface milling (204.0120)SY26,960$1.40$1.40$1.40
8Removing curb & gutter (204.0150)LF1,730$7.38$7.38$2.00
9Removing guardrail (204.0165)LF370$5.00$4.00$5.00
10Removing concrete bases (204.0195)EACH25$565.00$565.00$565.00
11Removing ancillary structure (structure) 01. S-43-11 (204.0246)EACH1$650.00$650.00$7,500.00
12Removing advance flasher assemblies type 2 (204.9002.S)EACH3$2,357.00$2,357.00$2,357.00
13Removing (item description) 01. traffic signal wire, loop detector wire & lead-in cable, ush 8 & STH 17S (204.9060.S)EACH1$1,755.00$1,755.00$1,755.00
14Removing (item description) 02. traffic signal wire, loop detector wire & lead-in cable, ush 8 & CTH G (204.9060.S)EACH1$1,755.00$1,755.00$1,755.00
15Removing (item description) 03. traffic signal wire, loop detector wire & lead-in cable, ush 8 & STH 17N (204.9060.S)EACH1$1,755.00$1,755.00$1,755.00
16Excavation common (205.0100)CY64,445$7.03$7.03$9.50
17Excavation marsh (205.0400)CY19$40.42$40.42$25.00
18Borrow (208.0100)CY11,020$6.54$6.54$0.01
19Select borrow (208.1100)CY29$82.57$82.57$23.32
20Prepare foundation for asphaltic shoulders (211.0400)STA4$669.46$800.00$100.00
21Finishing roadway (project) 01. 1590-12-75 (213.0100)EACH1$1,000.00$2,500.00$3,000.00
22Base aggregate dense 3/4-inch (305.0110)TON9,100$15.14$15.14$18.27
23Base aggregate dense 1 1/4-inch (305.0120)TON67,700$12.01$12.01$13.24
24Base aggregate open-graded (310.0115)CY50$66.74$66.74$39.79
25Coloring concrete wisdot red (405.0100)CY530$92.45$92.45$92.45
26Concrete truck apron 12-inch (415.2010)SY1,640$106.80$106.80$106.80
27HMA cold weather paving (450.4000)TON1,406$3.00$3.00$3.00
28Tack coat (455.0605)GAL10,450$2.80$2.80$2.80
29Incentive density HMA pavement (460.2000)DOL16,730$1.00$1.00$1.00
30HMA pavement 3 MT 58-28 S (460.6223)TON17,460$65.20$65.20$65.20
31HMA pavement 4 MT 58-34 S (460.6244)TON6,500$77.10$77.10$77.10
32HMA pavement 4 MT 58-34 H (460.6444)TON2,170$92.95$92.95$92.95
33Asphaltic surface (465.0105)TON155$230.00$230.00$230.00
34Asphaltic surface patching (465.0110)TON120$143.00$143.00$143.00
35Asphaltic surface driveways and field entrances (465.0120)TON37$164.00$164.00$164.00
36Asphaltic surface temporary (465.0125)TON1,197$83.60$83.60$83.60
37Asphaltic flumes (465.0315)SY132$62.00$62.00$72.00
38Culvert pipe temporary 18-inch (520.2018)LF120$25.88$25.88$81.00
39Culvert pipe reinforced concrete class III 30-inch (522.0130)LF123$210.08$210.08$283.00
40Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH1$1,185.85$1,185.85$1,301.00
41Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015)EACH6$1,259.48$1,259.48$1,367.00
42Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030)EACH3$2,102.74$2,102.74$2,029.00
43Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036)EACH2$2,912.65$2,912.65$2,810.00
44Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624)EACH2$2,456.16$2,456.16$2,400.00
45Concrete curb & gutter 18-inch type A (601.0405)LF573$48.31$48.31$48.31
46Concrete curb & gutter 30-inch type D (601.0411)LF4,597$31.02$31.02$31.02
47Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF2,019$29.99$29.99$29.99
48Concrete curb & gutter 4-inch sloped 30-inch type R (601.0581)LF815$40.19$40.19$40.19
49Concrete curb pedestrian (601.0600)LF265$46.45$46.45$46.45
50Concrete sidewalk 4-inch (602.0405)SF14,800$8.07$8.07$8.07
51Concrete sidewalk 6-inch (602.0415)SF3,420$9.12$9.12$9.12
52Curb ramp detectable warning field yellow (602.0505)SF456$60.32$60.32$60.32
53Riprap light (606.0100)CY174$148.17$148.17$112.80
54Riprap medium (606.0200)CY82$172.26$172.26$106.86
55Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF74$128.26$128.26$196.00
56Storm sewer pipe reinforced concrete class III 15-inch (608.0315)LF240$114.79$114.79$127.90
57Storm sewer pipe reinforced concrete class III 30-inch (608.0330)LF98$201.00$201.00$254.04
58Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF147$133.57$133.57$196.00
59Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF36$112.41$112.41$127.90
60Storm sewer pipe reinforced concrete class IV 36-inch (608.0436)LF77$307.99$307.99$353.87
61Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (608.2424)LF104$250.84$250.84$279.18
62Manhole covers type J-special (611.0535)EACH2$1,093.79$1,093.79$524.00
63Inlet covers type H (611.0624)EACH6$1,120.06$1,120.06$805.00
64Inlet covers type HM (611.0627)EACH10$1,125.34$1,125.34$812.00
65Inlet covers type H-S (611.0639)EACH4$1,120.06$1,120.06$805.00
66Inlet covers type MS (611.0642)EACH1$615.86$615.86$565.00
67Inlet covers type T (611.0652)EACH4$1,454.54$1,454.54$1,429.00
68Manholes 5-FT diameter (611.2005)EACH1$7,753.10$7,753.10$9,101.00
69Manholes 7-FT diameter (611.2007)EACH1$9,930.13$9,930.13$10,596
70Inlets 2X2.5-FT (611.3225)EACH4$2,489.07$2,489.07$2,989.00
71Inlets 2X3-FT (611.3230)EACH18$2,670.50$2,670.50$2,952.00
72Inlets median 2 grate (611.3902)EACH1$5,955.93$5,955.93$5,200.00
73Pipe underdrain 6-inch (612.0106)LF880$16.07$16.07$14.02
74MGS guardrail 3 (614.2300)LF200$32.50$32.00$32.50
75MGS thrie beam transition (614.2500)LF78.80$115.00$99.00$115.00
76MGS guardrail terminal eat (614.2610)EACH2$3,785.00$5,200.00$3,785.00
77Maintenance and repair of haul roads (project) 01. 1590-12-75 (618.0100)EACH1$1.00$1.00$100.00
78Mobilization (619.1000)EACH1$275,000$383,460$411,960
79Concrete median sloped nose (620.0300)SF490$13.67$13.67$13.67
80Water (624.0100)MGAL1,200$0.01$0.01$45.00
81Topsoil (625.0100)SY44,800$0.25$0.25$2.03
82Mulching (627.0200)SY36,600$0.35$0.25$0.35
83Silt fence (628.1504)LF6,590$1.85$2.00$1.85
84Silt fence maintenance (628.1520)LF13,180$0.03$0.01$0.03
85Mobilizations erosion control (628.1905)EACH11$151.00$400.00$151.00
86Mobilizations emergency erosion control (628.1910)EACH6$201.00$200.00$201.00
87Erosion mat urban class I type B (628.2008)SY2,390$2.75$2.40$2.75
88Erosion mat class II type C (628.2027)SY5,180$4.25$4.00$4.25
89Inlet protection type A (628.7005)EACH32$150.00$175.00$150.00
90Inlet protection type B (628.7010)EACH2$75.00$60.00$75.00
91Inlet protection type C (628.7015)EACH24$75.00$60.00$75.00
92Inlet protection type D (628.7020)EACH8$250.00$150.00$250.00
93Temporary ditch checks (628.7504)LF340$9.55$10.00$9.55
94Culvert pipe checks (628.7555)EACH15$32.00$15.00$32.00
95Rock bags (628.7570)EACH120$6.00$15.00$6.00
96Fertilizer type B (629.0210)CWT36$105.00$155.00$105.00
97Seeding mixture no. 40 (630.0140)LB2,290$8.55$9.00$8.55
98Seeding temporary (630.0200)LB110$5.25$5.00$5.25
99Seed water (630.0500)MGAL1,000$0.10$1.00$0.05
100Trees (species, root, size) 01. cole'S select serviceberry, B&B, 5' (632.0101)EACH6$825.00$475.00$825.00
101Landscape planting surveillance and care cycles (632.9101)EACH20$1,985.00$1,250.00$1,985.00
102Delineators temporary (633.1100)EACH65$18.00$22.38$18.00
103Posts wood 4X6-inch X 12-FT (634.0612)EACH2$90.00$135.00$90.00
104Posts wood 4X6-inch X 14-FT (634.0614)EACH75$98.00$135.00$98.00
105Posts wood 4X6-inch X 16-FT (634.0616)EACH13$101.00$150.00$101.00
106Posts wood 4X6-inch X 18-FT (634.0618)EACH2$105.00$165.00$105.00
107Signs type II reflective H (637.2210)SF811.23$22.75$24.00$22.75
108Signs type II reflective F (637.2230)SF59.50$25.75$25.00$25.75
109Moving signs type II (638.2102)EACH10$85.00$100.00$85.00
110Removing signs type II (638.2602)EACH74$25.00$35.00$25.00
111Removing small sign supports (638.3000)EACH61$25.00$35.00$25.00
112Moving small sign supports (638.4000)EACH11$85.00$100.00$85.00
113Field office type B (642.5001)EACH1$15,000$14,670$10,000
114Traffic control drums (643.0300)DAY19,829$0.27$0.29$0.27
115Traffic control barricades type III (643.0420)DAY7,548$0.45$0.50$0.45
116Traffic control warning lights type A (643.0705)DAY10,210$0.05$0.21$0.05
117Traffic control warning lights type C (643.0715)DAY4,466$0.05$0.46$0.05
118Traffic control signs (643.0900)DAY48,258$0.29$0.28$0.29
119Traffic control covering signs type II (643.0920)EACH10$25.00$118.93$25.00
120Traffic control signs PCMS (643.1050)DAY28$40.00$65.00$40.00
121Temporary marking line paint 6- inch (643.3165)LF8,800$0.40$0.45$0.40
122Temporary marking line removable tape 6-inch (643.3180)LF2,140$1.69$2.79$1.69
123Temporary marking raised pavement marker type I (643.3760)EACH21$4.75$22.84$4.75
124Temporary marking stop line removable tape 18-inch (643.3850)LF106$5.25$12.48$5.25
125Traffic control (643.5000)EACH1$2,850.00$21,643$2,850.00
126Geotextile type DF schedule A (645.0111)SY640$5.36$5.36$3.00
127Geotextile type HR (645.0120)SY1,015$7.27$7.27$4.78
128Marking line grooved wet ref epoxy 6-inch (646.2040)LF57,700$1.50$1.50$1.50
129Marking line grooved wet ref epoxy 10-inch (646.4040)LF1,750$2.35$2.35$2.35
130Marking line same day paint 4- inch (646.4505)LF5,860$0.80$0.80$0.80
131Marking line same day paint 8- inch (646.4605)LF520$1.45$1.45$1.45
132Marking arrow epoxy (646.5020)EACH16$300.00$300.00$300.00
133Marking word epoxy (646.5120)EACH8$315.00$315.00$315.00
134Marking stop line epoxy 12-inch (646.6020)LF90$14.00$14.00$14.00
135Marking stop line epoxy 18-inch (646.6120)LF92$19.00$19.00$19.00
136Marking dotted extension epoxy 18-inch (646.6320)LF150$18.00$18.00$18.00
137Cold weather marking epoxy 6-inch (646.6466)LF25,326$0.55$0.55$0.55
138Cold weather marking epoxy 10- inch (646.6470)LF1,750$1.15$1.15$1.15
139Marking diagonal epoxy 12-inch (646.7120)LF720$14.00$14.00$14.00
140Marking crosswalk epoxy transverse line 6-inch (646.7420)LF890$7.00$7.00$7.00
141Marking curb epoxy (646.8120)LF80$8.00$8.00$8.00
142Marking island nose epoxy (646.8220)EACH8$340.00$340.00$340.00
143Marking removal line 6-inch (646.9002)LF2,231$3.00$1.60$1.60
144Construction staking storm sewer (650.4000)EACH37$135.14$135.14$135.00
145Construction staking subgrade (650.4500)LF18,061$0.01$0.01$0.01
146Construction staking base (650.5000)LF18,061$0.28$0.28$0.96
147Construction staking curb gutter and curb & gutter (650.5500)LF9,370$0.38$0.38$1.22
148Construction staking pipe culverts (650.6000)EACH1$1,000.00$1,000.00$600.00
149Construction staking resurfacing reference (650.8000)LF5,268$0.28$0.28$0.11
150Construction staking electrical installations (project) 01. 1590-12- 75 (650.8501)EACH1$4,000.00$4,000.00$5,000.00
151Construction staking curb ramps (650.9000)EACH32$207.81$207.81$135.00
152Construction staking sidewalk (project) 01. 1590-12-75 (650.9500)EACH1$1,500.00$1,500.00$1,500.00
153Construction staking supplemental control (project) 01. 1590-12-75 (650.9911)EACH1$3,000.00$3,000.00$3,000.00
154Construction staking slope stakes (650.9920)LF18,061$0.53$0.53$0.92
155Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF3,949$11.11$11.11$11.11
156Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF300$13.70$13.70$13.70
157Conduit loop detector (652.0800)LF90$11.80$11.80$11.80
158Pull boxes steel 12X30-inch (653.0110)EACH2$1,285.00$1,285.00$1,285.00
159Pull boxes non-conductive 24X42- inch (653.0164)EACH20$2,285.00$2,285.00$2,285.00
160Removing pull boxes (653.0905)EACH41$468.00$468.00$468.00
161Concrete bases type 5 (654.0105)EACH28$1,418.00$1,418.00$1,418.00
162Concrete control cabinet bases type L30 (654.0230)EACH2$2,761.00$2,761.00$2,761.00
163Cable traffic signal 7-12 AWG (655.0235)LF450$3.66$3.66$3.66
164Electrical wire lighting 12 AWG (655.0610)LF4,200$1.10$1.10$1.10
165Electrical wire lighting 10 AWG (655.0615)LF16,182$1.25$1.25$1.25
166Electrical wire lighting 8 AWG (655.0620)LF1,965$1.65$1.65$1.65
167Loop detector lead in cable (655.0700)LF1,035$2.48$2.48$2.48
168Loop detector wire (655.0800)LF320$1.25$1.25$1.25
169Electrical service meter breaker pedestal (location) 01. LCC B (656.0201)EACH1$2,845.00$2,845.00$2,845.00
170Electrical service meter breaker pedestal (location) 02. LCC B (656.0201)EACH1$2,845.00$2,845.00$2,845.00
171Pedestal bases (657.0100)EACH1$370.00$370.00$370.00
172Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH28$750.00$750.00$750.00
173Poles type 5-aluminum (657.0322)EACH28$2,755.00$2,755.00$2,755.00
174Traffic signal standards aluminum 15-FT (657.0425)EACH1$886.00$886.00$886.00
175Trombone arms 25-FT (657.0595)EACH1$2,390.00$2,390.00$2,390.00
176Luminaire arms single member 4 1/2-inch clamp 8-FT (657.0615)EACH28$486.00$486.00$486.00
177Traffic signal face 5S 12-inch (658.0175)EACH2$1,356.00$1,356.00$1,356.00
178Luminaires utility LED A (659.1115)EACH28$295.00$295.00$295.00
179Lighting control cabinets 120/240 30-inch (659.2130)EACH2$10,871$10,871$10,871
180Lamp, ballast, LED, switch disposal by contractor (659.5000.S)EACH13$46.00$46.00$46.00
181Temporary traffic signals for bridges (structure) 01. station 37+50 (661.0101)EACH1$16,800$13,592$10,000
182Temporary traffic signals for bridges (structure) 02. station 83+81 (661.0101)EACH1$4,400.00$6,641.29$10,000
183Sawing asphalt (690.0150)LF3,640$3.00$1.75$2.00
184Sawing concrete (690.0250)LF300$5.00$2.95$2.50
185Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00
186Incentive iri ride (740.0440)DOL6,000$1.00$1.00$1.00
187On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,400$5.00$5.00$5.00
188On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS2,760$5.00$5.00$5.00
189Special 01. planting mixture (SPV.0035)CY145$125.00$97.50$125.00
190Special 01. driveway assistance device system 1590-12-75 (SPV.0045)DAY100$50.00$85.44$50.00
191Special 01. perennials autumn joy sedum, SP4, CG (SPV.0060)EACH238$32.00$40.00$32.00
192Special 02. perennials blue oat grass, SP4, CG (SPV.0060)EACH291$32.00$40.00$32.00
193Special 03. perennials catmint 'walkers low', SP4, CG (SPV.0060)EACH225$32.00$32.00$32.00
194Special 04. perennials prarie dropseed, SP4, CG (SPV.0060)EACH873$32.00$40.00$32.00
195Special 05. inlets 5-FT diameter (SPV.0060)EACH2$7,237.64$7,237.64$7,148.00
196Special 06. salvage traffic signals ush 8 & STH 17 (SPV.0060)EACH1$10,515$10,515$10,515
197Special 07. salvage traffic signals ush 8 & CTH G (SPV.0060)EACH1$10,515$10,515$10,515
198Special 08. traffic signal modifications courtney ST & pelham ST (SPV.0060)EACH1$7,671.00$7,671.00$7,671.00
199Special 01. concrete curb & gutter 4-inch sloped 36-inch type A full depth (SPV.0090)LF611$42.86$42.86$42.86
200Special 02. installing and maintaining climbing turtle exclusion fence (SPV.0090)LF2,160$1.00$12.00$1.00
201Special 01. stone mulch epoxied (SPV.0165)SF4,016$12.65$9.50$12.65
202Special 02. weed barrier (SPV.0165)SF11,825$0.75$0.65$0.75
203Special 01. protective thermoplastic coating at snowmobile crossing (SPV.0180)SY384$100.00$100.00$100.00
204Special 02. removing distressed asphaltic surface milling (SPV.0180)SY500$13.80$13.80$13.80
205Special 01. stone mulch (SPV.0195)TON164$80.00$125.00$80.00
WisDOT contract 20250909022: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of September 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy