WisDOT contract 20250909027 bid tabulation

Abbotsford - Medford; Little Black River Bridge B-60-0012 (STH 013, Taylor County Abbotsford - Medford). Let by Wisconsin DOT on September 9, 2025, Taylor. 6 bids received; low bid $893,900 by Janke General Contractors, Inc..

Owner
Wisconsin DOT
Letting
09 SEP 2025
Pay items
69
Data through
10 NOV 2026

5 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Janke General Contractors, Inc.$893,900Low
2Larson Construction Co., Inc.$898,3560.0%
3Zenith Tech., Inc. - Waukesha$936,854+5.0%
4Sheet Piling Services LLC$1,017,744+14%
5Lunda Construction Company$1,026,450+15%
WisDOT contract 20250909027: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Janke General Contractors, Inc.2. Larson Construction Co., Inc.3. Zenith Tech., Inc. - Waukesha4. Sheet Piling Services LLC5. Lunda Construction Company
1Removing structure over waterway minimal debris (structure) 01. B-60- 12 (203.0260)EACH1$116,599$143,500$75,000$185,000$200,000
2Removing guardrail (204.0165)LF414$4.90$4.90$3.05$4.90$3.05
3Excavation common (205.0100)CY537$20.00$11.00$21.95$22.25$21.95
4Excavation for structures bridges (structure) 01. B-60-12 (206.1001)EACH1$8,000.00$7,500.00$4,500.00$6,000.00$35,000
5Borrow (208.0100)CY714$44.00$23.50$38.15$23.73$38.15
6Backfill structure type A (210.1500)TON160$43.00$30.00$27.95$25.50$27.95
7Finishing roadway (project) 01. 1610-02-72 (213.0100)EACH1$300.00$100.00$525.00$500.00$525.00
8Base aggregate dense 3/4-inch (305.0110)TON283$38.00$36.50$28.95$35.25$28.95
9Base aggregate dense 1 1/4-inch (305.0120)TON851$30.00$26.00$27.37$23.10$27.37
10Subbase 10-inch (350.0135)SY615$27.00$13.00$12.10$7.15$12.10
11Concrete pavement 8-inch (415.0080)SY169$125.00$127.60$125.71$125.71$125.71
12Concrete pavement approach slab (415.0410)SY80$275.00$280.27$276.13$276.13$276.13
13Tack coat (455.0605)GAL47$16.30$16.30$16.30$16.30$16.30
14Asphaltic surface (465.0105)TON132$187.30$187.30$187.30$187.30$187.30
15Concrete masonry bridges (502.0100)CY211$900.00$855.00$1,375.00$1,350.00$1,000.00
16Protective surface treatment (502.3200)SY614$5.00$3.00$4.00$2.50$3.00
17Pigmented surface sealer (502.3210)SY164$9.00$4.00$12.00$3.00$5.00
18Adhesive anchors no. 5 bar (502.4205)EACH344$20.00$18.00$28.00$30.00$5.00
19Bar steel reinforcement HS coated structures (505.0600)LB50,700$2.40$1.83$1.56$1.65$1.52
20Steel diaphragms (structure) 01. B- 60-12 (506.4000)EACH12$1,400.00$2,400.00$1,450.00$2,500.00$1,500.00
21Concrete surface repair (509.1500)SF80$190.00$85.00$185.00$125.00$150.00
22Rubberized membrane waterproofing (516.0500)SY10$45.00$75.00$60.00$18.00$20.00
23Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590)LF138$80.00$72.52$72.43$72.43$72.43
24Concrete surface drains (602.3010)CY8$1,500.00$1,369.25$1,349.01$1,349.01$1,349.01
25Riprap medium (606.0200)CY49$128.00$120.00$115.00$105.00$110.50
26Pipe underdrain wrapped 6-inch (612.0406)LF190$15.00$10.50$6.85$6.25$6.85
27Anchor assemblies for steel plate beam guard (614.0150)EACH4$275.00$200.00$450.00$250.00$200.00
28MGS guardrail 3 (614.2300)LF150$26.00$26.00$24.45$26.00$24.45
29MGS thrie beam transition (614.2500)LF157.60$92.00$92.00$93.65$92.00$93.65
30MGS guardrail terminal eat (614.2610)EACH4$3,835.00$3,835.00$3,537.00$3,835.00$3,537.00
31Maintenance and repair of haul roads (project) 01. 1610-02-72 (618.0100)EACH1$300.00$1,500.00$500.00$1.00$0.01
32Mobilization (619.1000)EACH1$50,986$125,300$125,000$111,634$160,919
33Water (624.0100)MGAL21$30.00$100.00$1.00$40.00$1.00
34Salvaged topsoil (625.0500)SY3,350$7.00$1.25$1.61$3.95$1.61
35Silt fence (628.1504)LF1,146$2.30$2.30$2.10$2.30$2.10
36Silt fence maintenance (628.1520)LF1,146$0.02$0.02$0.01$0.02$0.01
37Mobilizations erosion control (628.1905)EACH5$200.00$420.00$400.00$420.00$400.00
38Mobilizations emergency erosion control (628.1910)EACH3$350.00$350.00$100.00$350.00$100.00
39Erosion mat urban class I type A (628.2006)SY3,350$2.19$2.19$1.55$2.19$1.55
40Turbidity barriers (628.6005)SY110$42.00$23.82$58.35$1.00$58.35
41Fertilizer type B (629.0210)CWT2.40$90.00$90.00$178.50$90.00$178.50
42Seeding mixture no. 30 (630.0130)LB151$8.80$8.80$12.15$8.80$12.15
43Seeding temporary (630.0200)LB91$3.55$3.55$5.95$3.55$5.95
44Seed water (630.0500)MGAL75$1.00$1.00$0.50$1.00$0.50
45Moving signs type II (638.2102)EACH10$100.00$100.00$86.85$100.00$86.85
46Moving small sign supports (638.4000)EACH11$110.00$110.00$86.85$110.00$86.85
47Field office type B (642.5001)EACH1$1,000.00$4,000.00$4,000.00$4,500.00$3,000.00
48Traffic control barricades type III (643.0420)DAY2,800$0.55$0.55$0.55$0.55$0.55
49Traffic control warning lights type A (643.0705)DAY5,600$0.05$0.05$0.05$0.05$0.05
50Traffic control signs (643.0900)DAY28,300$0.40$0.40$0.40$0.40$0.40
51Traffic control covering signs type II (643.0920)EACH7$20.00$20.00$20.00$20.00$20.00
52Traffic control signs PCMS (643.1050)DAY14$40.00$40.00$40.00$40.00$40.00
53Traffic control (643.5000)EACH1$2,350.00$2,350.00$2,350.00$2,350.00$2,350.00
54Geotextile type DF schedule A (645.0111)SY100$4.50$5.00$4.90$5.90$4.90
55Geotextile type HR (645.0120)SY71$6.00$2.50$6.70$6.15$6.70
56Marking line epoxy 6-inch (646.2020)LF575$8.65$8.65$8.65$8.65$11.00
57Construction staking subgrade (650.4500)LF125$0.25$0.01$0.01$0.25$0.01
58Construction staking base (650.5000)LF125$0.75$0.01$0.01$0.75$0.01
59Construction staking structure layout (structure) 01. B-60-12 (650.6501)EACH1$3,700.00$2,000.00$2,000.00$3,700.00$2,000.00
60Construction staking concrete pavement (650.7000)LF178$1.50$1.00$1.00$1.50$1.00
61Construction staking supplemental control (project) 01. 1610-02-72 (650.9911)EACH1$1,021.00$1,750.00$1,750.00$1,021.00$1,750.00
62Construction staking slope stakes (650.9920)LF541$1.00$1.50$1.50$1.00$1.50
63Sawing asphalt (690.0150)LF86$3.50$2.95$2.95$3.50$3.50
64Incentive strength concrete structures (715.0502)DOL1,266$1.00$1.00$1.00$1.00$1.00
65Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00$1.00$1.00
66Installing and maintaining bird deterrent system (station) 01. 10+00 (999.2000.S)EACH1$5,185.24$500.00$5,000.00$0.01$0.01
67Special 01. cleaning and sealing concrete girder ends (SPV.0060)EACH14$1,000.00$965.00$385.00$250.00$700.00
68Special 01. concrete girder repair (SPV.0165)SF25$335.00$285.00$365.00$200.00$200.00
69Special 02. fiber wrap reinforcing non-structural (SPV.0165)SF118$165.00$165.00$185.00$165.00$165.00
WisDOT contract 20250909027: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of September 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy