WisDOT contract 20250909029 bid tabulation

Chippewa Falls - Bloomer; Elm Street to CTH S (STH 124, Chippewa County Chippewa Falls - Bloomer). Let by Wisconsin DOT on September 9, 2025, Chippewa. 1 bid received; low bid $2,676,560 by Monarch Paving Company.

Owner
Wisconsin DOT
Letting
09 SEP 2025
Pay items
110
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Monarch Paving Company$2,676,560Low
WisDOT contract 20250909029: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Monarch Paving Company
1Grubbing (201.0205)STA2$775.00
2Removing small pipe culverts (203.0100)EACH2$920.00
3Removing concrete pavement (204.0100)SY230$11.60
4Removing asphaltic surface (204.0110)SY599$11.60
5Removing asphaltic surface butt joints (204.0115)SY1,217$21.67
6Removing asphaltic surface milling (204.0120)SY41,801$5.93
7Removing curb & gutter (204.0150)LF1,063$11.60
8Removing concrete sidewalk (204.0155)SY434$11.60
9Excavation common (205.0100)CY1,097$11.00
10Temporary lane shift during culvert work (208.1500.S)EACH2$1.00
11Prepare foundation for asphaltic paving (project) 01. 8610-08-73 (211.0101)EACH1$67,727
12Prepare foundation for asphaltic shoulders (211.0400)STA94$105.18
13Finishing roadway (project) 01. 8610-08-73 (213.0100)EACH1$10,193
14Base aggregate dense 3/4-inch (305.0110)TON595$44.75
15Base aggregate dense 1 1/4-inch (305.0120)TON1,659$28.15
16Coloring concrete wisdot red (405.0100)CY51$102.52
17Concrete pavement 8-inch (415.0080)SY226$107.67
18Tack coat (455.0605)GAL5,102$4.27
19Incentive density HMA pavement (460.2000)DOL5,750$1.00
20HMA pavement 5 MT 58-34 V (460.6645)TON8,459$119.18
21Material transfer vehicle (460.9000.S)EACH1$19,800
22Asphaltic surface (465.0105)TON332$208.34
23Asphaltic surface patching (465.0110)TON187$298.15
24Asphaltic surface driveways and field entrances (465.0120)TON40$296.82
25Cleaning culvert pipes (520.8700)EACH1$2,300.00
26Culvert pipe reinforced concrete horizontal elliptical class HE-III 19X30-inch (522.2319)LF178$248.00
27Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619)EACH6$2,300.00
28Concrete curb & gutter 30-inch type D (601.0411)LF703$81.28
29Concrete curb & gutter 6-inch sloped 30-inch type J (601.0415)LF360$41.94
30Concrete curb pedestrian (601.0600)LF109$54.95
31Concrete sidewalk 5-inch (602.0410)SF4,037$14.53
32Curb ramp detectable warning field yellow (602.0505)SF256$60.52
33Riprap medium (606.0200)CY8$142.00
34Adjusting manhole covers (611.8110)EACH23$885.00
35Adjusting inlet covers (611.8115)EACH6$760.00
36Cover plates temporary (611.8120.S)EACH23$290.00
37Salvaged inlet covers (611.9710)EACH6$195.00
38Mobilization (619.1000)EACH1$341,414
39Landmark reference monuments (621.0100)EACH1$15.00
40Water (624.0100)MGAL30$40.00
41Topsoil (625.0100)SY104$20.00
42Salvaged topsoil (625.0500)SY1,420$3.00
43Silt fence (628.1504)LF884$2.50
44Silt fence maintenance (628.1520)LF884$0.01
45Mobilizations erosion control (628.1905)EACH25$1.00
46Mobilizations emergency erosion control (628.1910)EACH4$1.00
47Erosion mat class II type B (628.2023)SY1,938$2.20
48Inlet protection type C (628.7015)EACH36$40.00
49Temporary ditch checks (628.7504)LF24$20.00
50Culvert pipe checks (628.7555)EACH28$20.00
51Fertilizer type A (629.0205)CWT1.40$500.00
52Seeding mixture no. 20 (630.0120)LB63$70.00
53Seeding temporary (630.0200)LB36.80$14.00
54Seed water (630.0500)MGAL31.10$1.00
55Sod water (631.0300)MGAL2.50$500.00
56Sod lawn (631.1000)SY104$30.00
57Markers culvert end (633.5200)EACH8$75.00
58Moving signs type II (638.2102)EACH8$90.00
59Moving small sign supports (638.4000)EACH8$90.00
60Field office type B (642.5001)EACH1$23,250
61Traffic control drums (643.0300)DAY4,346$0.45
62Traffic control barricades type III (643.0420)DAY576$0.84
63Traffic control warning lights type A (643.0705)DAY1,152$0.66
64Traffic control signs (643.0900)DAY14,939$0.47
65Traffic control covering signs type I (643.0910)EACH2$74.54
66Traffic control signs fixed message (643.1000)SF83$35.79
67Traffic control signs PCMS (643.1050)DAY42$66.92
68Temporary marking line paint 6- inch (643.3165)LF63,797$0.26
69Temporary marking line removable tape 6-inch (643.3180)LF440$3.15
70Temporary marking crosswalk removable tape 6-inch (643.3350)LF913$2.95
71Traffic control (643.5000)EACH1$118,999
72Temporary pedestrian surface plate (644.1430)SF242$24.77
73Temporary pedestrian surface matting (644.1440)SF413$14.13
74Temporary pedestrian curb ramp (644.1601)DAY670$11.93
75Temporary pedestrian detectable warning field (644.1605)SF480$11.75
76Temporary pedestrian barricade (644.1810)LF1,838$4.97
77Temporary audible message devices (644.1900.S)DAY310$3.93
78Geotextile type HR (645.0120)SY17$5.00
79Marking line grooved wet ref epoxy 6-inch (646.2040)LF37,716$1.41
80Marking line grooved wet ref epoxy 10-inch (646.4040)LF827$2.83
81Marking arrow epoxy (646.5020)EACH10$383.64
82Marking word epoxy (646.5120)EACH5$388.17
83Marking symbol epoxy (646.5220)EACH27$372.63
84Marking stop line epoxy 18-inch (646.6120)LF242$16.07
85Marking dotted extension epoxy 18-inch (646.6320)LF125$16.07
86Marking diagonal epoxy 12-inch (646.7120)LF555$15.66
87Marking crosswalk epoxy transverse line 6-inch (646.7420)LF1,033$12.78
88Marking crosswalk epoxy block style 24-inch (646.7520)LF66$26.37
89Marking curb epoxy (646.8120)LF19$7.70
90Marking parking stall epoxy (646.8320)LF12$20.00
91Marking removal line 4-inch (646.9000)LF440$2.50
92Construction staking subgrade (650.4500)LF210$0.01
93Construction staking base (650.5000)LF210$0.01
94Construction staking curb gutter and curb & gutter (650.5500)LF1,088$1.50
95Construction staking pipe culverts (650.6000)EACH3$349.00
96Construction staking concrete pavement (650.7000)LF360$1.00
97Construction staking resurfacing reference (650.8000)LF9,840$0.25
98Construction staking curb ramps (650.9000)EACH25$200.00
99Construction staking sidewalk (project) 01. 8610-08-73 (650.9500)EACH1$500.00
100Construction staking supplemental control (project) 01. 8610-08-73 (650.9911)EACH1$5,000.00
101Construction staking slope stakes (650.9920)LF210$0.58
102Sawing asphalt (690.0150)LF1,588$1.80
103Sawing concrete (690.0250)LF302$3.00
104Incentive compressive strength concrete pavement (715.0720)DOL500$1.00
105Incentive iri ride (740.0440)DOL7,460$1.00
106On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS200$5.00
107On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS300$5.00
108Special 01. ditch cleaning (SPV.0090)LF314$12.00
109Special 01. removing distressed pavement milling (SPV.0180)SY300$26.53
110Special 02. prepare topsoil for lawn type turf (SPV.0180)SY104$9.00
WisDOT contract 20250909029: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of September 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy