WisDOT contract 20251014004 bid tabulation

Town of Coon, Dodson Hollow Road; Dodson Hollow Creek Br B-62-0270 (LOC STR, Vernon County Town of Coon, Dodson Hollow Road). Let by Wisconsin DOT on October 14, 2025, Vernon. 6 bids received; low bid $448,288 by Lunda Construction Company.

Owner
Wisconsin DOT
Letting
14 OCT 2025
Pay items
57
Data through
10 NOV 2026

4 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Lunda Construction Company$448,288Low
3Radtke Contractors Inc.$489,388+9.0%
5Brennan Construction Company$539,560+20%
6Concrete Structures, Inc.$542,426+21%
WisDOT contract 20251014004: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Lunda Construction Company2. Radtke Contractors Inc.3. Brennan Construction Company4. Concrete Structures, Inc.
1Clearing (201.0120)ID60$35.00$63.87$50.00$63.87
2Grubbing (201.0220)ID60$35.00$24.85$50.00$24.85
3Removing structure over waterway minimal debris (structure) 01. P-62- 180 (203.0260)EACH1$10,000$25,912$50,000$63,000
4Excavation common (205.0100)CY98$20.00$57.39$15.00$57.39
5Excavation for structures bridges (structure) 01. B-62-270 (206.1001)EACH1$3,500.00$13,452$10,000$13,000
6Backfill structure type A (210.1500)TON408$30.00$32.54$55.00$32.50
7Finishing roadway (project) 01. 5378-00-73 (213.0100)EACH1$500.00$250.00$2,000.00$500.00
8Base aggregate dense 3/4-inch (305.0110)TON16$50.00$43.35$25.00$43.35
9Base aggregate dense 1 1/4-inch (305.0120)TON173$25.00$22.47$15.00$22.47
10Tack coat (455.0605)GAL17$11.75$11.75$11.75$11.75
11Asphaltic surface (465.0105)TON71$307.25$307.25$307.25$307.25
12Concrete masonry bridges (502.0100)CY216$830.00$663.22$995.00$1,000.00
13Protective surface treatment (502.3200)SY175$5.00$3.94$5.00$7.00
14Pigmented surface sealer (502.3210)SY73$8.00$15.63$10.00$10.00
15Bar steel reinforcement HS structures (505.0400)LB3,900$1.10$1.40$1.50$1.30
16Bar steel reinforcement HS coated structures (505.0600)LB28,325$1.20$1.44$1.50$1.50
17Rubberized membrane waterproofing (516.0500)SY19$25.00$59.04$40.00$37.00
18Pile points (550.0500)EACH12$125.00$110.78$160.00$200.00
19Piling steel HP 10-inch X 42 LB (550.1100)LF355$40.00$27.27$55.00$60.00
20Concrete surface drains (602.3010)CY4$1,485.11$1,485.11$1,400.00$1,485.11
21Riprap medium (606.0200)CY3$200.00$298.86$150.00$298.86
22Riprap extra-heavy (606.0400)CY197$80.00$90.92$100.00$91.00
23Pipe underdrain wrapped 6-inch (612.0406)LF140$15.00$9.82$10.00$10.00
24Maintenance and repair of haul roads (project) 01. 5378-00-73 (618.0100)EACH1$1.00$250.00$500.00$250.00
25Mobilization (619.1000)EACH1$87,246$130,430$67,455$56,887
26Water (624.0100)MGAL4$50.00$87.81$25.00$87.81
27Salvaged topsoil (625.0500)SY289$3.00$11.14$2.00$11.14
28Mulching (627.0200)SY433$1.00$1.00$1.00$1.00
29Silt fence (628.1504)LF354$2.30$2.30$2.30$2.30
30Silt fence maintenance (628.1520)LF354$0.02$0.02$0.02$0.02
31Mobilizations erosion control (628.1905)EACH4$400.00$400.00$400.00$400.00
32Mobilizations emergency erosion control (628.1910)EACH3$100.00$100.00$100.00$100.00
33Turbidity barriers (628.6005)SY205$45.00$45.00$45.00$45.00
34Fertilizer type B (629.0210)CWT0.50$110.00$110.00$110.00$110.00
35Seeding mixture no. 20 (630.0120)LB19.70$8.75$8.75$8.75$8.75
36Seeding temporary (630.0200)LB11.80$3.55$3.55$3.55$3.55
37Seed water (630.0500)MGAL10$25.00$25.00$25.00$25.00
38Posts wood 4X6-inch X 12-FT (634.0612)EACH4$90.00$90.00$90.00$90.00
39Signs type II reflective F (637.2230)SF12$28.00$28.00$28.00$28.00
40Removing small sign supports (638.3000)EACH8$25.00$25.00$25.00$25.00
41Field office type B (642.5001)EACH1$3,500.00$3,238.72$6,500.00$1,500.00
42Traffic control barricades type III (643.0420)DAY1,360$0.50$0.50$0.50$0.50
43Traffic control warning lights type A (643.0705)DAY2,040$0.15$0.10$0.10$0.15
44Traffic control signs (643.0900)DAY1,020$0.25$0.35$0.35$0.25
45Traffic control (643.5000)EACH1$6,100.00$1,250.00$1,250.00$6,100.00
46Geotextile type DF schedule A (645.0111)SY68$8.00$8.29$3.00$8.30
47Geotextile type HR (645.0120)SY312$6.00$3.97$5.00$4.00
48Construction staking subgrade (650.4500)LF128$0.05$0.05$0.05$0.05
49Construction staking base (650.5000)LF128$1.00$1.00$1.00$1.00
50Construction staking structure layout (structure) 01. B-62-0270 (650.6501)EACH1$2,500.00$2,500.00$2,500.00$2,500.00
51Construction staking supplemental control (project) 01. 5378-00-73 (650.9911)EACH1$250.00$250.00$250.00$250.00
52Construction staking slope stakes (650.9920)LF128$1.00$1.00$1.00$1.00
53Sawing asphalt (690.0150)LF48$10.00$10.00$9.00$10.00
54Incentive strength concrete structures (715.0502)DOL1,296$1.00$1.00$1.00$1.00
55Installing and maintaining bird deterrent system (station) 01. 10+00 (999.2000.S)EACH1$0.01$0.01$1,500.00$100.00
56On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,200$5.00$5.00$5.00$5.00
57On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00$5.00
WisDOT contract 20251014004: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of October 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy