WisDOT contract 20251014014 bid tabulation
C Wausau, West Wausau Avenue; Stevens Drive to North 10th Avenue (LOC STR, Marathon County C Wausau, West Wausau Avenue). Let by Wisconsin DOT on October 14, 2025, Marathon. 6 bids received; low bid $1,208,153 by James Peterson Sons, Inc..
- Owner
- Wisconsin DOT
- Letting
- 14 OCT 2025
- Pay items
- 128
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | James Peterson Sons, Inc. | $1,208,153 | Low |
| 2 | A-1 Excavating LLC | $1,232,109 | +2.0% |
| 3 | Haas Sons, Inc. | $1,284,959 | +6.0% |
| 4 | S & N Incorporated | $1,358,574 | +12% |
| 5 | Pember Companies, Inc. | $1,407,299 | +16% |
| 6 | Integrity Grading and Excavating, Inc. | $1,559,419 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. James Peterson Sons, Inc. | 2. A-1 Excavating LLC | 3. Haas Sons, Inc. | 4. S & N Incorporated | 5. Pember Companies, Inc. | 6. Integrity Grading and Excavating, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0120) | ID | 12 | $50.00 | $5.00 | $60.00 | $30.00 | $47.30 | $40.00 |
| 2 | Grubbing (201.0220) | ID | 12 | $50.00 | $25.00 | $60.00 | $30.00 | $26.70 | $0.01 |
| 3 | Removing concrete pavement (204.0100) | SY | 7,220 | $4.59 | $6.00 | $6.60 | $7.10 | $10.70 | $5.68 |
| 4 | Removing curb & gutter (204.0150) | LF | 275 | $5.00 | $4.00 | $10.00 | $3.00 | $5.65 | $8.65 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 1,080 | $3.50 | $6.00 | $4.00 | $5.70 | $8.20 | $3.50 |
| 6 | Removing inlets (204.0220) | EACH | 4 | $400.00 | $500.00 | $750.00 | $450.00 | $675.00 | $1,350.00 |
| 7 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 63 | $30.00 | $20.00 | $30.00 | $15.00 | $18.55 | $47.70 |
| 8 | Removing storm sewer (size) 02. 24-inch (204.0245) | LF | 36 | $30.00 | $25.00 | $30.00 | $15.00 | $27.00 | $47.25 |
| 9 | Removing (item description) 01. hydrants (204.9060.S) | EACH | 1 | $997.92 | $400.00 | $500.00 | $500.00 | $855.00 | $1,768.00 |
| 10 | Removing (item description) 02. sanitary manholes (204.9060.S) | EACH | 7 | $500.00 | $600.00 | $650.00 | $500.00 | $960.00 | $1,350.00 |
| 11 | Removing (item description) 01. sanitary sewer 8-inch (204.9090.S) | LF | 90 | $25.49 | $3.00 | $5.00 | $10.00 | $5.60 | $13.15 |
| 12 | Removing (item description) 02. sanitary sewer 10-inch (204.9090.S) | LF | 30 | $25.49 | $3.00 | $5.00 | $10.00 | $8.40 | $18.15 |
| 13 | Removing (item description) 03. sanitary sewer 12-inch (204.9090.S) | LF | 1,414 | $2.00 | $3.00 | $5.00 | $8.00 | $5.70 | $11.95 |
| 14 | Removing (item description) 04. water main 6-inch (204.9090.S) | LF | 199 | $3.26 | $3.00 | $6.00 | $8.00 | $10.10 | $12.95 |
| 15 | Removing (item description) 05. water main 8-inch (204.9090.S) | LF | 1,296 | $3.08 | $3.00 | $6.00 | $8.00 | $7.80 | $12.00 |
| 16 | Excavation common (205.0100) | CY | 3,797 | $13.65 | $15.00 | $14.67 | $17.10 | $17.80 | $18.00 |
| 17 | Finishing roadway (project) 01. 6999-00-76 (213.0100) | EACH | 1 | $2,000.00 | $500.00 | $1.00 | $1,200.00 | $500.00 | $500.00 |
| 18 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 5,000 | $19.73 | $19.00 | $16.81 | $18.15 | $24.10 | $18.00 |
| 19 | Tack coat (455.0605) | GAL | 300 | $4.42 | $5.50 | $4.42 | $4.42 | $4.65 | $4.42 |
| 20 | Incentive density HMA pavement (460.2000) | DOL | 850 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 21 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 745 | $93.28 | $94.00 | $99.99 | $93.28 | $97.95 | $93.28 |
| 22 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 580 | $104.18 | $105.00 | $104.18 | $104.18 | $109.40 | $104.18 |
| 23 | Asphaltic surface patching (465.0110) | TON | 5 | $350.72 | $371.00 | $350.72 | $350.72 | $368.25 | $350.72 |
| 24 | Asphaltic surface driveways and field entrances (465.0120) | TON | 45 | $252.18 | $263.00 | $252.18 | $252.18 | $264.80 | $252.18 |
| 25 | Concrete collars for pipe (520.8000) | EACH | 1 | $800.00 | $1,000.00 | $1,500.00 | $950.00 | $1,440.00 | $760.00 |
| 26 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 2,680 | $21.68 | $22.20 | $17.00 | $19.35 | $17.00 | $21.68 |
| 27 | Concrete sidewalk 6-inch (602.0415) | SF | 12,100 | $6.79 | $7.30 | $7.90 | $8.85 | $7.90 | $6.79 |
| 28 | Curb ramp detectable warning field natural patina (602.0515) | SF | 136 | $50.25 | $51.25 | $62.00 | $60.32 | $62.00 | $50.25 |
| 29 | Concrete driveway 6-inch (602.0810) | SY | 90 | $61.91 | $67.00 | $74.60 | $80.51 | $74.60 | $61.91 |
| 30 | Concrete driveway hes 6-inch (602.0860) | SY | 415 | $64.01 | $68.00 | $85.00 | $81.79 | $85.00 | $64.01 |
| 31 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 86 | $111.92 | $95.00 | $118.50 | $117.28 | $85.00 | $431.00 |
| 32 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 36 | $149.98 | $135.00 | $146.00 | $152.49 | $125.60 | $209.00 |
| 33 | Reconstructing manholes (611.0420) | EACH | 3 | $660.79 | $1,300.00 | $3,000.00 | $1,800.00 | $1,300.00 | $1,518.00 |
| 34 | Manhole covers type J-special (611.0535) | EACH | 5 | $1,333.98 | $950.00 | $1,125.00 | $1,136.00 | $1,470.00 | $725.00 |
| 35 | Inlet covers type H (611.0624) | EACH | 6 | $1,644.78 | $1,200.00 | $1,725.00 | $1,343.00 | $985.00 | $970.00 |
| 36 | Inlets 4-FT diameter (611.3004) | EACH | 1 | $3,612.08 | $4,100.00 | $3,500.00 | $2,798.00 | $4,105.00 | $5,368.00 |
| 37 | Inlets 2X3-FT (611.3230) | EACH | 5 | $2,119.60 | $2,740.00 | $2,500.00 | $1,942.00 | $2,735.00 | $5,295.00 |
| 38 | Adjusting inlet covers (611.8115) | EACH | 1 | $792.66 | $450.00 | $1,150.00 | $700.00 | $840.00 | $500.00 |
| 39 | Insulation board polystyrene (inch) 01. 2-inch (612.0902.S) | SY | 28 | $27.00 | $28.00 | $27.00 | $30.00 | $51.40 | $13.98 |
| 40 | Mobilization (619.1000) | EACH | 1 | $95,454 | $98,240 | $59,530 | $99,979 | $89,725 | $154,000 |
| 41 | Landmark reference monuments (621.0100) | EACH | 4 | $100.00 | $150.00 | $100.00 | $100.00 | $105.00 | $100.00 |
| 42 | Water (624.0100) | MGAL | 50 | $40.00 | $30.00 | $60.00 | $45.00 | $93.00 | $44.00 |
| 43 | Topsoil (625.0100) | SY | 2,900 | $8.86 | $5.00 | $8.40 | $7.75 | $10.25 | $3.75 |
| 44 | Silt fence (628.1504) | LF | 480 | $6.00 | $6.20 | $6.00 | $6.00 | $2.45 | $6.00 |
| 45 | Silt fence maintenance (628.1520) | LF | 480 | $0.01 | $0.05 | $0.01 | $0.01 | $0.08 | $0.01 |
| 46 | Mobilizations erosion control (628.1905) | EACH | 4 | $750.00 | $800.00 | $750.00 | $750.00 | $445.00 | $750.00 |
| 47 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $1.00 | $51.00 | $1.00 | $1.00 | $370.00 | $1.00 |
| 48 | Erosion mat urban class I type A (628.2006) | SY | 2,900 | $2.50 | $2.60 | $2.50 | $2.50 | $2.45 | $2.50 |
| 49 | Inlet protection type A (628.7005) | EACH | 9 | $125.00 | $140.00 | $125.00 | $125.00 | $112.40 | $125.00 |
| 50 | Inlet protection type C (628.7015) | EACH | 10 | $75.00 | $90.00 | $75.00 | $75.00 | $76.40 | $75.00 |
| 51 | Inlet protection type D (628.7020) | EACH | 5 | $125.00 | $140.00 | $125.00 | $125.00 | $148.50 | $125.00 |
| 52 | Seeding mixture no. 40 (630.0140) | LB | 55 | $12.00 | $14.00 | $12.00 | $12.00 | $14.65 | $12.00 |
| 53 | Seed water (630.0500) | MGAL | 65 | $50.00 | $51.00 | $50.00 | $50.00 | $1.05 | $50.00 |
| 54 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 13 | $300.00 | $310.00 | $300.00 | $300.00 | $260.00 | $300.00 |
| 55 | Posts tubular steel 2X2-inch X 16- FT (634.0816) | EACH | 2 | $300.00 | $310.00 | $300.00 | $300.00 | $265.00 | $300.00 |
| 56 | Signs type II reflective H (637.2210) | SF | 49.79 | $50.00 | $53.00 | $50.00 | $50.00 | $30.20 | $50.00 |
| 57 | Signs type II reflective SH (637.2220) | SF | 13.25 | $50.00 | $53.00 | $50.00 | $50.00 | $29.70 | $50.00 |
| 58 | Signs type II reflective F (637.2230) | SF | 2.75 | $50.00 | $53.00 | $50.00 | $50.00 | $29.70 | $50.00 |
| 59 | Moving signs type II (638.2102) | EACH | 3 | $150.00 | $160.00 | $150.00 | $150.00 | $126.25 | $150.00 |
| 60 | Removing signs type II (638.2602) | EACH | 17 | $50.00 | $60.00 | $50.00 | $50.00 | $43.50 | $50.00 |
| 61 | Removing small sign supports (638.3000) | EACH | 14 | $50.00 | $60.00 | $50.00 | $50.00 | $36.40 | $50.00 |
| 62 | Field office type B (642.5001) | EACH | 1 | $9,668.75 | $7,000.00 | $20,000 | $9,000.00 | $9,400.00 | $12,500 |
| 63 | Traffic control drums (643.0300) | DAY | 600 | $0.50 | $0.60 | $0.50 | $0.50 | $0.55 | $0.50 |
| 64 | Traffic control barricades type III (643.0420) | DAY | 1,500 | $0.50 | $0.60 | $0.50 | $0.50 | $0.55 | $0.50 |
| 65 | Traffic control warning lights type A (643.0705) | DAY | 1,875 | $0.10 | $0.20 | $0.10 | $0.10 | $0.10 | $0.10 |
| 66 | Traffic control signs (643.0900) | DAY | 2,040 | $0.50 | $0.60 | $0.50 | $0.50 | $0.55 | $0.50 |
| 67 | Temporary marking line removable tape 4-inch (643.3150) | LF | 850 | $0.85 | $1.30 | $0.85 | $0.85 | $0.90 | $0.85 |
| 68 | Temporary marking line removable tape 6-inch (643.3180) | LF | 230 | $1.65 | $3.00 | $1.65 | $1.65 | $1.75 | $1.65 |
| 69 | Traffic control (643.5000) | EACH | 1 | $1,675.00 | $4,175.00 | $1,675.00 | $1,675.00 | $4,635.00 | $1,675.00 |
| 70 | Temporary pedestrian surface plate (644.1430) | SF | 110 | $8.00 | $10.00 | $125.00 | $12.00 | $10.60 | $8.00 |
| 71 | Temporary pedestrian surface matting (644.1440) | SF | 1,050 | $5.00 | $5.50 | $5.00 | $5.00 | $5.30 | $5.00 |
| 72 | Temporary pedestrian curb ramp (644.1601) | DAY | 130 | $5.00 | $7.00 | $5.00 | $5.00 | $5.30 | $5.00 |
| 73 | Temporary pedestrian detectable warning field (644.1605) | SF | 64 | $5.00 | $7.00 | $5.00 | $5.00 | $5.30 | $5.00 |
| 74 | Temporary pedestrian barricade (644.1810) | LF | 880 | $4.50 | $5.00 | $4.50 | $4.50 | $4.80 | $4.50 |
| 75 | Marking line epoxy 4-inch (646.1020) | LF | 3,770 | $1.05 | $1.10 | $1.05 | $1.28 | $1.10 | $1.05 |
| 76 | Marking line epoxy 8-inch (646.3020) | LF | 110 | $1.28 | $1.80 | $1.28 | $2.10 | $1.35 | $1.28 |
| 77 | Marking arrow epoxy (646.5020) | EACH | 1 | $310.00 | $335.00 | $310.00 | $265.00 | $330.00 | $310.00 |
| 78 | Marking word epoxy (646.5120) | EACH | 1 | $325.00 | $350.00 | $325.00 | $270.00 | $345.00 | $325.00 |
| 79 | Marking stop line epoxy 18-inch (646.6120) | LF | 85 | $16.15 | $18.00 | $16.15 | $21.00 | $17.15 | $16.15 |
| 80 | Marking diagonal epoxy 12-inch (646.7120) | LF | 50 | $14.80 | $16.00 | $14.80 | $18.00 | $15.70 | $14.80 |
| 81 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 350 | $10.50 | $11.00 | $10.50 | $14.00 | $11.15 | $10.50 |
| 82 | Marking removal line 4-inch (646.9000) | LF | 730 | $0.85 | $1.00 | $0.85 | $0.85 | $0.90 | $0.85 |
| 83 | Marking removal line 6-inch (646.9002) | LF | 190 | $0.95 | $1.00 | $0.95 | $0.95 | $1.00 | $0.95 |
| 84 | Marking removal line 8-inch (646.9100) | LF | 110 | $1.90 | $2.50 | $1.90 | $1.90 | $2.00 | $1.90 |
| 85 | Marking removal line wide (646.9200) | LF | 95 | $2.50 | $3.00 | $2.50 | $2.50 | $2.65 | $2.50 |
| 86 | Marking removal special marking (646.9300) | EACH | 2 | $60.00 | $85.00 | $60.00 | $60.00 | $65.00 | $60.00 |
| 87 | Construction staking storm sewer (650.4000) | EACH | 6 | $120.00 | $145.00 | $120.00 | $120.00 | $125.00 | $120.00 |
| 88 | Construction staking subgrade (650.4500) | LF | 1,474 | $0.01 | $0.01 | $1.00 | $0.50 | $0.10 | $0.01 |
| 89 | Construction staking base (650.5000) | LF | 1,474 | $1.00 | $1.20 | $1.00 | $1.00 | $1.05 | $1.00 |
| 90 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 3,130 | $0.80 | $0.90 | $0.80 | $0.80 | $0.90 | $0.80 |
| 91 | Construction staking curb ramps (650.9000) | EACH | 10 | $250.00 | $260.00 | $250.00 | $250.00 | $265.00 | $250.00 |
| 92 | Construction staking sidewalk (project) 01. 6999-00-76 (650.9500) | EACH | 1 | $250.00 | $500.00 | $250.00 | $250.00 | $265.00 | $250.00 |
| 93 | Construction staking supplemental control (project) 01. 6999-00-76 (650.9911) | EACH | 1 | $1,094.11 | $1,345.00 | $1,094.11 | $1,094.11 | $1,160.00 | $1,094.11 |
| 94 | Construction staking slope stakes (650.9920) | LF | 1,474 | $1.25 | $1.50 | $1.25 | $1.25 | $1.35 | $1.25 |
| 95 | Sawing asphalt (690.0150) | LF | 305 | $1.75 | $4.00 | $1.75 | $3.75 | $3.40 | $1.75 |
| 96 | Sawing concrete (690.0250) | LF | 330 | $2.35 | $6.00 | $2.35 | $4.35 | $5.90 | $2.35 |
| 97 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,200 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 98 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 99 | Special 01. fertilizer for lawn type turf (SPV.0030) | CWT | 2 | $300.00 | $350.00 | $300.00 | $300.00 | $132.60 | $300.00 |
| 100 | Special 01. research and locate existing land parcel monuments (SPV.0060) | EACH | 7 | $69.77 | $80.00 | $69.77 | $69.77 | $74.00 | $69.77 |
| 101 | Special 02. verify and replace existing land parcel monuments (SPV.0060) | EACH | 7 | $95.00 | $105.00 | $95.00 | $95.00 | $101.00 | $95.00 |
| 102 | Special 03. reestablish section corner monuments (SPV.0060) | EACH | 1 | $500.00 | $600.00 | $500.00 | $500.00 | $530.00 | $500.00 |
| 103 | Special 05. temporary water service (SPV.0060) | EACH | 1 | $28,007 | $9,000.00 | $9,000.00 | $23,500 | $5,000.00 | $22,400 |
| 104 | Special 06. connecting water main (SPV.0060) | EACH | 6 | $2,329.62 | $2,200.00 | $2,050.00 | $1,915.88 | $2,470.00 | $8,200.00 |
| 105 | Special 07. 8X8X6-inch tee (SPV.0060) | EACH | 5 | $681.57 | $1,030.00 | $1,150.00 | $805.96 | $1,050.00 | $553.53 |
| 106 | Special 08. 8-inch 45 degree bend (SPV.0060) | EACH | 4 | $460.23 | $750.00 | $950.00 | $578.33 | $810.00 | $373.75 |
| 107 | Special 09. 6-inch valve & valve box (SPV.0060) | EACH | 5 | $2,499.56 | $2,430.00 | $2,900.00 | $2,453.92 | $2,765.00 | $2,030.09 |
| 108 | Special 10. 8-inch valve & valve box (SPV.0060) | EACH | 3 | $3,469.41 | $3,270.00 | $3,700.00 | $3,299.80 | $3,650.00 | $2,817.77 |
| 109 | Special 11. standard hydrant (SPV.0060) | EACH | 2 | $6,743.59 | $6,550.00 | $6,800.00 | $7,191.50 | $7,000.00 | $7,500.00 |
| 110 | Special 12. connecting sanitary sewer (SPV.0060) | EACH | 4 | $2,121.15 | $1,800.00 | $1,000.00 | $1,719.78 | $1,650.00 | $5,375.00 |
| 111 | Special 13. sanitary manhole covers type J-special (SPV.0060) | EACH | 5 | $1,221.54 | $1,275.00 | $1,525.00 | $1,398.54 | $1,050.00 | $725.00 |
| 112 | Special 14. manholes sanitary 4-FT diameter (SPV.0060) | EACH | 5 | $5,120.95 | $5,850.00 | $4,800.00 | $5,723.40 | $5,580.00 | $6,880.00 |
| 113 | Special 15. sanitary sewer PVC wyes (SPV.0060) | EACH | 8 | $495.20 | $700.00 | $1,075.00 | $721.88 | $805.00 | $358.67 |
| 114 | Special 16. 6-inch 45 degree bend (SPV.0060) | EACH | 6 | $344.26 | $540.00 | $800.00 | $460.40 | $685.00 | $279.60 |
| 115 | Special 17. construction staking water main (6999-00-76) (SPV.0060) | EACH | 1 | $1,100.00 | $1,600.00 | $1,100.00 | $1,100.00 | $1,165.00 | $1,100.00 |
| 116 | Special 18. construction staking sanitary sewer (6999-00-76) (SPV.0060) | EACH | 1 | $1,100.00 | $1,600.00 | $1,100.00 | $1,100.00 | $1,165.00 | $1,100.00 |
| 117 | Special 01. concrete curb & gutter 24-inch type D (SPV.0090) | LF | 60 | $79.32 | $83.00 | $44.75 | $71.30 | $44.75 | $79.32 |
| 118 | Special 02. concrete curb & gutter 12-inch sloped 24-inch type D (SPV.0090) | LF | 30 | $79.35 | $83.02 | $59.00 | $71.30 | $59.00 | $79.35 |
| 119 | Special 03. concrete curb & gutter hes 30-inch type D (SPV.0090) | LF | 360 | $51.47 | $54.00 | $41.00 | $31.29 | $41.00 | $51.47 |
| 120 | Special 04. 6-inch DI water main (SPV.0090) | LF | 135 | $99.44 | $88.00 | $102.00 | $95.74 | $120.00 | $106.00 |
| 121 | Special 05. 8-inch DI water main (SPV.0090) | LF | 1,406 | $75.51 | $78.00 | $85.00 | $97.49 | $100.00 | $103.25 |
| 122 | Special 06. water laterals (SPV.0090) | LF | 234 | $73.31 | $81.00 | $102.00 | $73.28 | $82.50 | $102.00 |
| 123 | Special 07. sanitary sewer 8-inch (SPV.0090) | LF | 30 | $81.57 | $90.00 | $92.00 | $112.46 | $177.00 | $550.50 |
| 124 | Special 08. sanitary sewer 10-inch (SPV.0090) | LF | 30 | $87.18 | $97.00 | $96.00 | $117.97 | $134.00 | $555.75 |
| 125 | Special 09. sanitary sewer 12-inch (SPV.0090) | LF | 1,413 | $63.60 | $66.00 | $89.00 | $102.91 | $96.50 | $115.00 |
| 126 | Special 10. sanitary sewer laterals (SPV.0090) | LF | 287 | $54.12 | $57.00 | $77.00 | $51.82 | $66.85 | $119.00 |
| 127 | Special 11. polyethylene encasement (SPV.0090) | LF | 1,541 | $0.47 | $3.00 | $2.50 | $1.44 | $1.15 | $0.38 |
| 128 | Special 01. preparing topsoil for lawn type turf (SPV.0180) | SY | 2,900 | $1.00 | $1.20 | $1.00 | $1.00 | $2.10 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of October 14, 2025. Compiled by Mirage Metrics.