WisDOT contract 20251111008 bid tabulation
5990-02-41. Let by Wisconsin DOT on November 11, 2025, Rock. 2 bids received; low bid $1,532,701 by Rock Road Companies, Inc..
- Owner
- Wisconsin DOT
- Letting
- 11 NOV 2025
- Pay items
- 113
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rock Road Companies, Inc. | $1,532,701 | Low |
| 2 | Parisi Construction, LLC | $1,599,143 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rock Road Companies, Inc. | 2. Parisi Construction, LLC |
|---|---|---|---|---|---|
| 1 | Clearing (201.0120) | ID | 94 | $43.00 | $44.25 |
| 2 | Grubbing (201.0220) | ID | 94 | $20.00 | $20.50 |
| 3 | Removing concrete pavement (204.0100) | SY | 300 | $21.05 | $9.40 |
| 4 | Removing curb & gutter (204.0150) | LF | 4,935 | $0.50 | $7.70 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 580 | $22.00 | $22.00 |
| 6 | Removing manholes (204.0210) | EACH | 6 | $616.19 | $580.00 |
| 7 | Removing inlets (204.0220) | EACH | 10 | $616.19 | $580.00 |
| 8 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 395 | $16.70 | $23.25 |
| 9 | Removing storm sewer (size) 02. 18-inch (204.0245) | LF | 43 | $16.70 | $26.75 |
| 10 | Removing storm sewer (size) 03. 42-inch (204.0245) | LF | 6 | $18.79 | $48.00 |
| 11 | Sealing pipes (204.0280) | EACH | 2 | $982.82 | $200.00 |
| 12 | Excavation common (205.0100) | CY | 8,500 | $22.55 | $20.00 |
| 13 | Finishing roadway (project) 01. 5990-02-41 (213.0100) | EACH | 1 | $5,222.73 | $1,000.00 |
| 14 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 9,300 | $18.05 | $16.00 |
| 15 | Select crushed material (312.0115) | CY | 1,050 | $45.50 | $30.25 |
| 16 | Tack coat (455.0605) | GAL | 545 | $2.85 | $1.00 |
| 17 | Incentive density HMA pavement (460.2000) | DOL | 1,950 | $1.00 | $1.00 |
| 18 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 1,825 | $63.00 | $72.00 |
| 19 | HMA pavement 5 LT 58-28 S (460.5225) | TON | 1,220 | $65.00 | $74.00 |
| 20 | Concrete curb & gutter 30-inch type L (601.0419) | LF | 4,825 | $21.70 | $24.00 |
| 21 | Concrete curb pedestrian (601.0600) | LF | 19 | $45.00 | $60.00 |
| 22 | Concrete sidewalk 4-inch (602.0405) | SF | 3,500 | $9.95 | $10.75 |
| 23 | Concrete sidewalk 6-inch (602.0415) | SF | 2,550 | $10.50 | $12.75 |
| 24 | Curb ramp detectable warning field natural patina (602.0515) | SF | 300 | $40.00 | $45.00 |
| 25 | Curb ramp detectable warning field radial natural patina (602.0615) | SF | 29.60 | $65.00 | $55.00 |
| 26 | Concrete driveway 6-inch (602.0810) | SY | 330 | $79.20 | $68.00 |
| 27 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 1,121 | $108.41 | $71.00 |
| 28 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 43 | $142.70 | $82.00 |
| 29 | Manholes 4-FT diameter (611.2004) | EACH | 5 | $3,148.73 | $2,600.00 |
| 30 | Manholes 6-FT diameter (611.2006) | EACH | 5 | $8,249.34 | $7,100.00 |
| 31 | Inlets 2X3-FT (611.3230) | EACH | 13 | $2,428.01 | $2,100.00 |
| 32 | Adjusting manhole covers (611.8110) | EACH | 7 | $964.57 | $690.00 |
| 33 | Adjusting inlet covers (611.8115) | EACH | 4 | $1,080.95 | $800.00 |
| 34 | Insulation board polystyrene (inch) 01. 2-inch (612.0902.S) | SY | 28.48 | $21.33 | $18.50 |
| 35 | Maintenance and repair of haul roads (project) 01. 5990-02-41 (618.0100) | EACH | 1 | $0.01 | $500.00 |
| 36 | Mobilization (619.1000) | EACH | 1 | $68,713 | $97,000 |
| 37 | Dust control surface treatment (623.0200) | SY | 14,325 | $0.01 | $0.25 |
| 38 | Water (624.0100) | MGAL | 135 | $26.60 | $50.00 |
| 39 | Topsoil (625.0100) | SY | 3,500 | $1.00 | $13.50 |
| 40 | Mobilizations erosion control (628.1905) | EACH | 12 | $1.00 | $1.00 |
| 41 | Mobilizations emergency erosion control (628.1910) | EACH | 6 | $1.00 | $1.00 |
| 42 | Inlet protection type D (628.7020) | EACH | 39 | $125.00 | $130.00 |
| 43 | Tracking pads (628.7560) | EACH | 2 | $1,420.00 | $630.00 |
| 44 | Fertilizer type B (629.0210) | CWT | 2.30 | $150.00 | $150.00 |
| 45 | Sod water (631.0300) | MGAL | 200 | $0.01 | $0.01 |
| 46 | Sod lawn (631.1000) | SY | 3,500 | $14.00 | $14.50 |
| 47 | Posts tubular steel 2X2-inch X 12- FT (634.0812) | EACH | 50 | $300.00 | $310.00 |
| 48 | Signs type II reflective H (637.2210) | SF | 189.62 | $25.00 | $25.75 |
| 49 | Signs type II reflective SH (637.2220) | SF | 13.26 | $26.00 | $26.75 |
| 50 | Signs type II reflective F (637.2230) | SF | 83.74 | $27.00 | $27.75 |
| 51 | Moving signs type II (638.2102) | EACH | 3 | $150.00 | $150.00 |
| 52 | Removing signs type II (638.2602) | EACH | 22 | $50.00 | $51.00 |
| 53 | Removing small sign supports (638.3000) | EACH | 18 | $50.00 | $51.00 |
| 54 | Moving small sign supports (638.4000) | EACH | 2 | $1.00 | $1.00 |
| 55 | Field office type C (642.5201) | EACH | 1 | $5,000.00 | $6,500.00 |
| 56 | Traffic control drums (643.0300) | DAY | 1,000 | $0.43 | $0.45 |
| 57 | Traffic control barricades type III (643.0420) | DAY | 2,700 | $0.62 | $0.65 |
| 58 | Traffic control warning lights type A (643.0705) | DAY | 5,400 | $0.16 | $0.15 |
| 59 | Traffic control warning lights type C (643.0715) | DAY | 230 | $0.70 | $0.70 |
| 60 | Traffic control signs (643.0900) | DAY | 11,700 | $0.33 | $0.35 |
| 61 | Traffic control covering signs type II (643.0920) | EACH | 2 | $157.36 | $160.00 |
| 62 | Traffic control signs fixed message (643.1000) | SF | 90 | $22.99 | $23.75 |
| 63 | Traffic control signs PCMS (643.1050) | DAY | 20 | $60.00 | $62.00 |
| 64 | Temporary marking line removable tape 6-inch (643.3180) | LF | 350 | $3.51 | $3.60 |
| 65 | Traffic control (643.5000) | EACH | 1 | $7,640.58 | $7,900.00 |
| 66 | Temporary pedestrian surface asphalt (644.1410) | SF | 1,000 | $5.16 | $5.90 |
| 67 | Temporary pedestrian surface plate (644.1430) | SF | 1,000 | $1.14 | $1.20 |
| 68 | Temporary pedestrian surface matting (644.1440) | SF | 1,500 | $1.30 | $1.30 |
| 69 | Temporary pedestrian curb ramp (644.1601) | DAY | 1,150 | $4.72 | $4.90 |
| 70 | Temporary pedestrian detectable warning field (644.1605) | SF | 120 | $7.44 | $7.70 |
| 71 | Temporary pedestrian barricade (644.1810) | LF | 500 | $7.37 | $7.60 |
| 72 | Marking line epoxy 4-inch (646.1020) | LF | 10,165 | $0.71 | $1.00 |
| 73 | Marking line epoxy 8-inch (646.3020) | LF | 80 | $1.45 | $2.10 |
| 74 | Marking arrow epoxy (646.5020) | EACH | 21 | $225.00 | $310.00 |
| 75 | Marking word epoxy (646.5120) | EACH | 6 | $240.00 | $340.00 |
| 76 | Marking symbol epoxy (646.5220) | EACH | 19 | $450.00 | $290.00 |
| 77 | Marking stop line epoxy 18-inch (646.6120) | LF | 180 | $12.50 | $20.50 |
| 78 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 725 | $10.75 | $13.50 |
| 79 | Marking crosswalk epoxy block style 24-inch (646.7520) | LF | 78 | $20.00 | $25.75 |
| 80 | Construction staking storm sewer (650.4000) | EACH | 24 | $25.00 | $150.00 |
| 81 | Construction staking subgrade (650.4500) | LF | 2,392 | $0.01 | $0.01 |
| 82 | Construction staking base (650.5000) | LF | 2,392 | $0.01 | $1.00 |
| 83 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 4,954 | $0.40 | $1.00 |
| 84 | Construction staking curb ramps (650.9000) | EACH | 32 | $100.00 | $210.00 |
| 85 | Construction staking sidewalk (project) 01. 5990-02-41 (650.9500) | EACH | 1 | $3,000.00 | $2,100.00 |
| 86 | Construction staking supplemental control (project) 01. 5990-02-41 (650.9911) | EACH | 1 | $3,000.00 | $6,200.00 |
| 87 | Construction staking slope stakes (650.9920) | LF | 2,392 | $0.25 | $0.01 |
| 88 | Sawing asphalt (690.0150) | LF | 320 | $1.20 | $1.80 |
| 89 | Sawing concrete (690.0250) | LF | 930 | $3.25 | $2.80 |
| 90 | Incentive iri ride (740.0440) | DOL | 1,808 | $1.00 | $1.00 |
| 91 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,200 | $5.00 | $5.00 |
| 92 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 |
| 93 | Special 01. watermain granular backfill special (SPV.0035) | CY | 210 | $14.03 | $23.00 |
| 94 | Special 01. remove and salvage flashing stop sign assembly (SPV.0060) | EACH | 1 | $500.00 | $510.00 |
| 95 | Special 02. install city supplied street name sign (SPV.0060) | EACH | 10 | $350.00 | $360.00 |
| 96 | Special 03. V-loc post anchor VS2 (SPV.0060) | EACH | 50 | $200.00 | $210.00 |
| 97 | Special 04. manhole cover type special logo (SPV.0060) | EACH | 11 | $920.15 | $890.00 |
| 98 | Special 05. inlet cover type H special logo (SPV.0060) | EACH | 8 | $1,187.24 | $1,300.00 |
| 99 | Special 06. inlet cover type H special logo LP (SPV.0060) | EACH | 8 | $1,187.24 | $1,300.00 |
| 100 | Special 07. saddle inlet (SPV.0060) | EACH | 1 | $3,678.48 | $3,200.00 |
| 101 | Special 08. 8-inch X 8-inch D.I. tee (SPV.0060) | EACH | 4 | $1,016.83 | $2,000.00 |
| 102 | Special 09. 8-inch X 6-inch D.I. reducer (SPV.0060) | EACH | 1 | $688.58 | $1,600.00 |
| 103 | Special 10. 8-inch D.I. 45 deg bend (SPV.0060) | EACH | 4 | $745.14 | $1,600.00 |
| 104 | Special 11. gate valve with valve box, 8-inch (SPV.0060) | EACH | 6 | $3,332.07 | $4,500.00 |
| 105 | Special 12. removing water valve manhole (SPV.0060) | EACH | 1 | $770.24 | $580.00 |
| 106 | Special 13. construction staking watermain (SPV.0060) | EACH | 1 | $3,000.00 | $7,200.00 |
| 107 | Special 14. manhole structure chimney repair (SPV.0060) | EACH | 9 | $2,224.29 | $1,200.00 |
| 108 | Special 15. sanitary structure replacement (SPV.0060) | EACH | 1 | $11,439 | $8,600.00 |
| 109 | Special 16. sanitary structure standard barrel section (SPV.0060) | EACH | 1 | $4,363.70 | $3,300.00 |
| 110 | Special 17. manhole cover type special logo sanitary (SPV.0060) | EACH | 8 | $1,245.55 | $890.00 |
| 111 | Special 01. ductile iron watermain 8-inch (SPV.0090) | LF | 234 | $163.90 | $170.00 |
| 112 | Special 02. remove existing watermain (SPV.0090) | LF | 240 | $46.05 | $36.50 |
| 113 | Special 03. concrete curb & gutter 30-inch type L special (4-inch curb head height) (SPV.0090) | LF | 110 | $30.00 | $45.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.