WisDOT contract 20251111029 bid tabulation
STH 37 - Gilmanton; STH 37 to STH 88 (CTH B, Buffalo County STH 37 - Gilmanton). Let by Wisconsin DOT on November 11, 2025, Buffalo. 4 bids received; low bid $1,664,877 by Mattison Contractors, Inc..
- Owner
- Wisconsin DOT
- Letting
- 11 NOV 2025
- Pay items
- 75
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Mattison Contractors, Inc. | $1,664,877 | Low |
| 2 | Haas Sons, Inc. | $1,772,790 | +6.0% |
| 3 | A-1 Excavating LLC | $1,776,616 | +7.0% |
| 4 | McCabe Construction, Inc. | $1,830,470 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Mattison Contractors, Inc. | 2. Haas Sons, Inc. | 3. A-1 Excavating LLC | 4. McCabe Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0110) | SY | 80 | $8.50 | $56.75 | $10.00 | $15.50 |
| 2 | Grubbing (201.0210) | SY | 80 | $4.20 | $11.28 | $20.00 | $10.50 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 7 | $335.00 | $541.00 | $544.00 | $365.00 |
| 4 | Removing concrete pavement (204.0100) | SY | 50 | $8.40 | $17.53 | $10.00 | $24.00 |
| 5 | Removing asphaltic surface (204.0110) | SY | 610 | $2.70 | $2.90 | $6.00 | $5.50 |
| 6 | Removing asphaltic surface butt joints (204.0115) | SY | 2,480 | $0.70 | $1.79 | $6.00 | $3.00 |
| 7 | Removing curb & gutter (204.0150) | LF | 86 | $4.20 | $9.53 | $10.00 | $10.00 |
| 8 | Removing guardrail (204.0165) | LF | 288 | $3.35 | $3.35 | $5.00 | $3.52 |
| 9 | Removing inlets (204.0220) | EACH | 2 | $335.00 | $626.00 | $500.00 | $370.00 |
| 10 | Removing storm sewer (size) 01. 18-inch (204.0245) | LF | 252 | $6.70 | $22.58 | $15.00 | $20.00 |
| 11 | Excavation common (205.0100) | CY | 6,476 | $8.00 | $22.54 | $15.00 | $20.50 |
| 12 | Finishing roadway (project) 01. 7229-00-70 (213.0100) | EACH | 1 | $1,000.00 | $1.00 | $300.00 | $2,510.00 |
| 13 | Base aggregate dense 3/4-inch (305.0110) | TON | 3,020 | $21.75 | $26.22 | $22.50 | $22.25 |
| 14 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 16,140 | $19.35 | $18.43 | $18.50 | $18.35 |
| 15 | Pulverize and relay (325.0100) | SY | 22,770 | $0.93 | $1.02 | $2.00 | $1.40 |
| 16 | Tack coat (455.0605) | GAL | 2,430 | $3.41 | $3.41 | $3.50 | $3.58 |
| 17 | Incentive density HMA pavement (460.2000) | DOL | 4,960 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 4,360 | $89.73 | $89.73 | $92.00 | $94.25 |
| 19 | HMA pavement 4 LT 58-34 S (460.5244) | TON | 3,390 | $94.65 | $94.65 | $97.00 | $99.42 |
| 20 | Asphaltic surface (465.0105) | TON | 150 | $182.53 | $182.53 | $198.00 | $191.73 |
| 21 | Asphaltic surface driveways and field entrances (465.0120) | TON | 65 | $254.55 | $254.55 | $272.00 | $267.38 |
| 22 | Apron endwalls for culvert pipe steel 24-inch (521.1024) | EACH | 2 | $415.00 | $520.50 | $390.00 | $390.95 |
| 23 | Apron endwalls for culvert pipe steel 36-inch (521.1036) | EACH | 12 | $985.00 | $870.50 | $920.00 | $822.75 |
| 24 | Culvert pipe corrugated steel 24- inch (521.3124) | LF | 60 | $68.00 | $79.77 | $62.00 | $212.00 |
| 25 | Culvert pipe corrugated steel 36- inch (521.3136) | LF | 305 | $105.00 | $116.21 | $90.00 | $245.00 |
| 26 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 1 | $1,425.00 | $1,417.00 | $1,400.00 | $1,005.00 |
| 27 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 97 | $45.00 | $84.36 | $50.00 | $88.61 |
| 28 | Concrete driveway 6-inch (602.0810) | SY | 50 | $108.00 | $67.70 | $120.00 | $71.11 |
| 29 | Storm sewer pipe reinforced concrete class II 12-inch (608.0212) | LF | 245 | $88.50 | $76.79 | $75.00 | $65.50 |
| 30 | Inlet covers type F (611.0615) | EACH | 2 | $2,355.00 | $1,828.75 | $2,410.00 | $1,890.00 |
| 31 | Inlets 4-FT diameter (611.3004) | EACH | 2 | $3,495.00 | $3,508.00 | $3,963.00 | $3,060.00 |
| 32 | MGS guardrail 3 (614.2300) | LF | 225 | $23.00 | $23.00 | $26.00 | $24.16 |
| 33 | MGS thrie beam transition (614.2500) | LF | 315.20 | $94.00 | $94.00 | $103.00 | $98.74 |
| 34 | MGS guardrail terminal eat (614.2610) | EACH | 8 | $3,390.00 | $3,390.00 | $3,730.00 | $3,560.89 |
| 35 | Maintenance and repair of haul roads (project) 01. 7229-00-70 (618.0100) | EACH | 1 | $125.00 | $1.00 | $300.00 | $1.00 |
| 36 | Mobilization (619.1000) | EACH | 1 | $132,875 | $108,325 | $130,825 | $116,005 |
| 37 | Water (624.0100) | MGAL | 292 | $1.75 | $1.00 | $5.00 | $42.00 |
| 38 | Salvaged topsoil (625.0500) | SY | 16,510 | $1.00 | $3.42 | $2.00 | $1.50 |
| 39 | Mulching (627.0200) | SY | 15,330 | $0.32 | $0.32 | $0.35 | $0.34 |
| 40 | Silt fence (628.1504) | LF | 15,620 | $1.85 | $1.85 | $2.00 | $1.94 |
| 41 | Silt fence maintenance (628.1520) | LF | 15,620 | $0.01 | $0.01 | $0.01 | $0.01 |
| 42 | Mobilizations erosion control (628.1905) | EACH | 5 | $170.00 | $170.00 | $187.00 | $178.57 |
| 43 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $110.00 | $110.00 | $121.00 | $115.55 |
| 44 | Erosion mat urban class I type B (628.2008) | SY | 1,180 | $1.75 | $1.75 | $2.00 | $1.84 |
| 45 | Turbidity barriers (628.6005) | SY | 30 | $35.00 | $35.00 | $39.00 | $36.76 |
| 46 | Culvert pipe checks (628.7555) | EACH | 46 | $15.00 | $15.00 | $17.00 | $15.76 |
| 47 | Fertilizer type B (629.0210) | CWT | 10.46 | $89.00 | $89.00 | $98.00 | $93.49 |
| 48 | Seeding mixture no. 20 (630.0120) | LB | 749 | $6.75 | $6.75 | $8.00 | $7.09 |
| 49 | Seeding temporary (630.0200) | LB | 452 | $2.75 | $2.75 | $3.00 | $2.89 |
| 50 | Seed water (630.0500) | MGAL | 371 | $0.01 | $0.01 | $0.01 | $0.01 |
| 51 | Moving signs type II (638.2102) | EACH | 28 | $85.00 | $85.00 | $94.00 | $89.28 |
| 52 | Removing small sign supports (638.3000) | EACH | 2 | $35.00 | $35.00 | $39.00 | $36.76 |
| 53 | Moving small sign supports (638.4000) | EACH | 23 | $75.00 | $75.00 | $83.00 | $78.78 |
| 54 | Field office type B (642.5001) | EACH | 1 | $27,000 | $8,300.00 | $7,000.00 | $7,500.00 |
| 55 | Traffic control drums (643.0300) | DAY | 2,260 | $0.50 | $0.50 | $0.55 | $0.53 |
| 56 | Traffic control barricades type III (643.0420) | DAY | 1,582 | $0.50 | $0.50 | $0.55 | $0.53 |
| 57 | Traffic control warning lights type A (643.0705) | DAY | 904 | $0.25 | $0.25 | $0.30 | $0.26 |
| 58 | Traffic control signs (643.0900) | DAY | 4,746 | $0.50 | $0.50 | $0.55 | $0.53 |
| 59 | Traffic control covering signs type II (643.0920) | EACH | 10 | $40.00 | $40.00 | $44.00 | $42.02 |
| 60 | Traffic control (643.5000) | EACH | 1 | $1,702.00 | $1,702.00 | $4,000.00 | $1,787.80 |
| 61 | Marking line epoxy 4-inch (646.1020) | LF | 48,105 | $0.36 | $0.38 | $0.40 | $0.38 |
| 62 | Marking stop line epoxy 18-inch (646.6120) | LF | 38 | $16.00 | $28.00 | $30.00 | $16.81 |
| 63 | Locating no-passing zones (648.0100) | MI | 2.62 | $550.00 | $990.00 | $1,000.00 | $577.73 |
| 64 | Construction staking storm sewer (650.4000) | EACH | 3 | $300.00 | $300.00 | $330.00 | $315.12 |
| 65 | Construction staking base (650.5000) | LF | 4,570 | $0.50 | $0.50 | $0.55 | $0.53 |
| 66 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 97 | $2.00 | $2.00 | $3.00 | $2.10 |
| 67 | Construction staking pipe culverts (650.6000) | EACH | 7 | $300.00 | $300.00 | $330.00 | $315.12 |
| 68 | Construction staking resurfacing reference (650.8000) | LF | 9,250 | $0.10 | $0.10 | $0.15 | $0.11 |
| 69 | Construction staking supplemental control (project) 01. 7229-00-70 (650.9911) | EACH | 1 | $1,000.00 | $1,000.00 | $2,000.00 | $1,050.41 |
| 70 | Construction staking slope stakes (650.9920) | LF | 4,534 | $0.55 | $0.55 | $1.00 | $0.58 |
| 71 | Sawing asphalt (690.0150) | LF | 474 | $1.95 | $2.00 | $3.00 | $2.05 |
| 72 | Sawing concrete (690.0250) | LF | 40 | $2.95 | $4.00 | $9.00 | $3.10 |
| 73 | Incentive iri ride (740.0440) | DOL | 10,239 | $1.00 | $1.00 | $1.00 | $1.00 |
| 74 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 75 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.